Home / Browse projects / Pune, Maharashtra / GT PRIDE
GT PRIDE
RG-MH-55253 · RERA P52100048595 · Last updated on MahaRERA portal: 7 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 31 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GT PRIDE is a Residential / Group Housing project by G T ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100048595 on 10 Jan 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 31 months from the original filing. 50 of the 81 units on this registration are recorded sold or booked, and 27 of 44 construction stages are filed complete.
At a glance
Project
- NameGT PRIDE
- TypeResidential / Group Housing
- Location
- NEAR SANTOSA RESORT
- RAVET
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100048595
- ReraGenie IDRG-MH-55253
Builder
- NameG T ASSOCIATES
- Entity typePartnership
- PartnersNIKHIL VILAS GAIKWAD, GAURAV DILIP TARAS
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Jan 2023
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 May 2025)
- Buildings4 building records
- Documents filed163 files
Current status
Figures as on 7 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 9 | 7 | 28 | 0 | 28 |
| WING B | NA | 9 | 7 | 28 | 0 | 28 |
| WING C | NA | 9 | 7 | 14 | 0 | 14 |
| WING D | NA | 8 | 7 | 0 | 11 | 11 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 7 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
27 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 90%.
WING A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING D49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 7 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed164
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 42 | 42 |
| WING B | 42 | 42 |
| WING C | 40 | 40 |
| WING D | 40 | 40 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| DNYANDEV ANANDA KATE | Kivale | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING B | NA | Rs 7.12 cr | Rs 7.12 cr |
| WING A | NA | Rs 7.12 cr | Rs 7.12 cr |
| WING C | NA | Rs 4.73 cr | Rs 4.67 cr |
| WING D | NA | Rs 4.73 cr | Rs 2.84 cr |
| - | NA | Rs 1.61 cr | Rs 1.33 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIKET MULUK MULUK |
| Engineer | RAVINDRA A KARNAVAT KARNAVAT |
| Engineer | Vastukalpa Associates |
| Engineer | Rohit Shikhare |
| Engineer | Rohinee Badgujar |
| Chartered Accountant | CA SUHAS SURESH SATHE SURESH SATHE |
| Chartered Accountant | Vaishali R Gole |
| Chartered Accountant | PRAVIN E EPISE E EPISE |
| Partner | Role in project |
|---|---|
| G T ASSOCIATES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere is daily for project started and issue for labour contractor. There is no single booking in our project.
Reason as filed by the promoterhe completion of the project has been delayed due to revisions in the sanctioned plans of the project. The process of obtaining revised sanctions involved submission of updated drawings, recalculation of permissible and sanctioned built-up area, and incorporation of changes in building configuration and statutory compliances as per prevailing regulations. The time consumed in scrutiny, observations, and approvals by the competent authorities was beyond the control of the promoter, which consequently affected the project execution schedule and led to delay in completion." The completion date of
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Sep 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Sep 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed163
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 163 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: Main Layout (11)_11zon.pdf | 7 Sep 2026 |
| Building plan approvalFile: Floor Plan 2-5_11zon.pdf | 7 Sep 2026 |
| Building plan approvalFile: Floor Plan 3-5_11zon.pdf | 7 Sep 2026 |
| Building plan approvalFile: Floor Plan 4-5_11zon.pdf | 7 Sep 2026 |
| Building plan approvalFile: Floor Plan 5-5_11zon.pdf | 7 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Mar 2026.pdf | 7 Sep 2026 |
| Withdrawal Update Form 1File: form 1 gt pride jun 26 (1) (1).pdf | 7 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Mar 2026.pdf | 7 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 (19).pdf | 7 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Mar 2026.pdf | 7 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 (36).pdf | 7 Sep 2026 |
| Form 2A (FY 2025-2026)File: Form 2A GT PRIDE.pdf | 13 Aug 2026 |
| Form 5 (FY 2023-2024)File: Form 5 23-24 (1).pdf | 13 Aug 2026 |
| Form 5 (FY 2024-2025)File: Form 5 24-25 (1).pdf | 13 Aug 2026 |
| Form 5 (FY 2025-2026)File: Form 5 gt pride 2025-26.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Adobe Scan 19 Jan 2026 (1) (1).pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: ilovepdf_merged (1).pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 23 Jan 2026 |
| Form 1File: october 25 Architect form 1 (1).pdf | 8 Oct 2025 |
| Form 2File: Form 2 sept 25.pdf | 8 Oct 2025 |
| Form 3File: Form 3 sep 2025.pdf | 8 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold sept 2025.pdf | 8 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 3 Sep 2025 |
| Form 2A (FY 2023-2024)File: form 2A 23-24.pdf | 26 Aug 2025 |
| Form 2A (FY 2022-2023)File: Form 2A GT Pride 22-23.pdf | 18 Aug 2025 |
| Form 5 (FY 2022-2023)File: Form 5 GT Pride 22-23.pdf | 18 Aug 2025 |
| Form 1File: Architect form 1 July 2025 (4).pdf | 16 Jul 2025 |
| Form 2File: form 2 July 2025 (2).pdf | 16 Jul 2025 |
| Form 3File: Form 3 July 2025.pdf | 16 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold june 2025 (4).pdf | 16 Jul 2025 |
| Form 1File: Form 1 (30 Sepetember 2024).pdf | 18 Jun 2025 |
| Form 2File: Form 2 (17 Octomber 2024).pdf | 18 Jun 2025 |
| Form 3File: Form 3 (25 November 2024).pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 12 September 2024.pdf | 18 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: july-september 2024 Declaration.pdf | 18 Jun 2025 |
| Form 1File: Form 1 (4 April 2025).pdf | 18 Jun 2025 |
| Form 2File: 11 April 2025 Form 2.pdf | 18 Jun 2025 |
| Form 3File: Form 3 (17 April 2025).pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 10 April 2025.pdf | 18 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: jan-march 2025 (1).pdf | 18 Jun 2025 |
| Form 1File: fORM 1 (1 Octomber 2023).pdf | 15 Jun 2025 |
| Form 2File: form 2 (1 November 2023).pdf | 15 Jun 2025 |
| Form 3File: Form 3 (23 Sepetember 2023).pdf | 15 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 1 Nov 2023.pdf | 15 Jun 2025 |
| Form 1File: Form 1 (1 January 2023).pdf | 15 Jun 2025 |
| Form 2File: Form 2 (1 Octomber 2023).pdf | 15 Jun 2025 |
| Form 3File: Form 3 (2 November 2023).pdf | 15 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 4 January 2024.pdf | 15 Jun 2025 |
| Form 1File: Form 1 (10 April 2024).pdf | 15 Jun 2025 |
| Form 2File: Form 2 (10 Apr 2024).pdf | 15 Jun 2025 |
| Form 3File: Form 3 (14 May 2024).pdf | 15 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 10 Aprill 2024.pdf | 15 Jun 2025 |
| Form 1File: Form 1 (1 July 2024).pdf | 15 Jun 2025 |
| Form 2File: Form 2 (1 Julyy 2024).pdf | 15 Jun 2025 |
| Form 3File: Form 3 (14 July 2024).pdf | 15 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 12 July 2024.pdf | 15 Jun 2025 |
| Form 1File: Form 1 (5 January 2025).pdf | 15 Jun 2025 |
| Form 2File: Form 2 (11 January 2024).pdf | 15 Jun 2025 |
| Form 3File: Form 3 (15 January 2024).pdf | 15 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold (10 January 2025).pdf | 15 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect form 1 April 25 (1).pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1pride (1).pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 April 2025.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 April 2025.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate April 2025.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 GT PRIDE (1)_compressed.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold march 25.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 1 architect dec 2024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer cer jan 25.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold jan 2025.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 Sep.pdf | 4 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Gt Pride Form 2 SEP 2024 (1).pdf | 11 Nov 2024 |
| Layout approvalFile: 1_11zon (1).pdf | 13 Aug 2024 |
| Building plan approvalFile: 2_11zon (1).pdf | 13 Aug 2024 |
| Building plan approvalFile: 3_11zon.pdf | 13 Aug 2024 |
| Building plan approvalFile: 4_11zon.pdf | 13 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: 1_11zon (1).pdf | 13 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_11zon (1).pdf | 13 Aug 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 163 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GT PRIDE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAVET13,700+ in Pune
Filed coordinates, straight-line distance. 227 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: G T ASSOCIATES
G T ASSOCIATES has 1 registration on MahaRERA, including GT PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GT PRIDE is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GT PRIDE?
The registered promoter entity is G T ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GT PRIDE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GT PRIDE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GT PRIDE?
The professionals named in the filing: Architect: ANIKET MULUK MULUK; Engineer: RAVINDRA A KARNAVAT KARNAVAT; Engineer: Vastukalpa Associates; Engineer: Rohit Shikhare; Engineer: Rohinee Badgujar; Chartered Accountant: CA SUHAS SURESH SATHE SURESH SATHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GT PRIDE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.