Home / Browse projects / Satara, Maharashtra / Govind Park B
Govind Park B
RG-MH-76020 · RERA P52700054856 · Last updated on MahaRERA portal: 8 Aug 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Govind Park B is a Residential / Group Housing project by Vikram Sanjay Nimbalkar in Satara, Maharashtra, registered with MahaRERA as P52700054856 on 15 Feb 2024. The registration is recorded completed; possession was promised by 31 Aug 2027. 7 of the 30 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameGovind Park B
- TypeResidential / Group Housing
- Location
- Kolki- Jadhavwadi Shiv Road
- Phakhale Mala
- Kolki (CT)
- Phaltan
- Satara
- 415523
- Pincode415523
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700054856
- ReraGenie IDRG-MH-76020
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Feb 2024
- Promised completion31 Aug 2027
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Current status
Figures as on 8 Aug 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Govind Park B | NA | 6 | 6 | 24 | 6 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Govind Park B: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed36
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| For OM SAI Developers Mrs. Sangeeta Bhimsen Jadhav | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Govind Park B | NA | Rs 2.05 cr | Rs 1.95 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mahendra Mugutrao Jadhav |
| Engineer | Yuvraj Suhas Nikam |
| Chartered Accountant | V S Jadhav And Company |
| Chartered Accountant | Samadhan Ramdas Kadam |
| Partner | Role in project |
|---|---|
| Vikram Sanjay Nimbalkar | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Nov 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed82
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 8 Aug 2025 |
| Occupational CertificateFile: PART COMLITION.pdf | 16 Jul 2025 |
| Withdrawal Update Form 1File: form 1 arch.pdf | 11 Jul 2025 |
| Withdrawal Update Form 2File: 1st qat Engg form2 2425.pdf | 11 Jul 2025 |
| Withdrawal Update Form 3File: Adobe Scan 11 Jul 2025.pdf | 11 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca.pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: disc of inventiry.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: inventory disc.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3CA.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg form2.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: inventory disc.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3CA.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg form2.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3CA.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg form2.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: inventory disc.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING INVENTRY.pdf | 14 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING INVENTRY.pdf | 14 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING INVENTRY.pdf | 14 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING INVENTRY.pdf | 14 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM32ndqat2425.pdf | 11 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM32ndqat2425.pdf | 11 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM32ndqat2425.pdf | 11 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM32ndqat2425.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT .pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT .pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT .pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT .pdf | 10 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2324.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2324.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2324.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2324.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1st qat arch form 1 2425 .pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1st qat Engg form2 2425.pdf | 8 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 1qat inventory disc 2425.pdf | 8 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1qat form 3 2425.pdf | 8 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate of Vikram Nimbalkar_compressed (1).pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 final quarter 2324.pdf | 10 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 final quarter 2324.pdf | 10 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 2324.pdf | 10 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold inventory final quarter 2324.pdf | 10 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 final quater 2324.pdf | 10 Apr 2024 |
| Building plan approvalFile: building A.pdf | 19 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: building A.pdf | 19 Dec 2023 |
| Building plan approvalFile: HIGHLIGHTED BUILDING B LAYOUT feb 2024.pdf | 14 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HIGHLIGHTED BUILDING B LAYOUT feb 2024.pdf | 14 Dec 2023 |
| Copy of the legal title reportFile: legal title report.pdf | 22 Nov 2023 |
| Copy of the legal title reportFile: MUTATION.pdf | 22 Nov 2023 |
| Declaration about Commencement CertificateFile: FORMAT D.pdf | 22 Nov 2023 |
| Other - LegalFile: TapScanner 11-10-2023-10꞉15 (p1).pdf | 10 Nov 2023 |
| Other - TechnicalFile: SKM_C25824021215330.pdf | 12 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: no financial dues pending.pdf | 22 Sep 2023 |
| Details of encumbrances concerned to LegalFile: no financial dues pending.pdf | 22 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3.pdf | 22 Sep 2023 |
| Proforma of Agreement for saleFile: agreement to sale.pdf | 22 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2.pdf | 14 Sep 2023 |
| CERSAI detailsFile: cersai.pdf | 8 Sep 2023 |
| Layout approvalFile: layout .pdf | 7 Sep 2023 |
| Building plan approvalFile: building B.pdf | 7 Sep 2023 |
| PAN CardFile: PAN.pdf | 7 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: legal encumbrances.pdf | 7 Sep 2023 |
| Details of encumbrances concerned to LegalFile: legal encumbrances.pdf | 7 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: layout .pdf | 7 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: building B.pdf | 7 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: cc.pdf | 7 Sep 2023 |
| Declaration in FORM BFile: form B promoter.pdf | 7 Sep 2023 |
| Declaration in FORM BFile: form b land owner_compressed.pdf | 7 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 7 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: dis of other reak estate org.pdf | 7 Sep 2023 |
| Proforma of Allotment letterFile: allotment latter.pdf | 7 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: dec seperate bank acc.pdf | 7 Sep 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Govind Park Bp52700054856 | 55/5, Kolki- Jadhavwadi Shiv Road, Phakhale Mala, Kolki (CT), Phaltan, Satara, 415523, MAHARASHTRA | - | Ongoing | Aug 2027 | Not due yet |
| Rambaug City A4 | Gut No 1373-2 Behind Shirke Paper Mill Shirwal Khandala | 80 | Completed | May 2021 | Late, Mar 2022 |
| Rambaug CityA1 | Gut No 1373-2 Behind Shirke Paper Mill Shirwal Khandala | 63 | Completed | Dec 2019 | Nov 2018 |
| Rambaug City A2 and A3 | Gut No 1373 -2 Behind Shirke Paper Mill Shirwal Khandala | 64 | Completed | Jun 2017 | Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 82 filed documents as one ZIP, foldered, with a manifest
Keep Govind Park B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Phakhale Mala1,100+ in Satara
Filed coordinates, straight-line distance. 43 registered projects within 2 km.
Plotted development scheme at S.No.129.Wathar
Pune Housing & Area Development Board
ALPHA WORLD
PARAG PRAMOD DHADIWAL
INDUS LANDMARK
INDUS PROMOTERS
SWARA CITY
JAGDISH RAMVILAS KARVA
EMPIRE TOWERS
RAM AND J K ASSOCIATES
TRIANGLE HEIGHTS
MIG CONSTRUCTION LLP
See every Satara project, with the district possession charts
Builder: Vikram Sanjay Nimbalkar
Vikram Sanjay Nimbalkar has 2 registrations on MahaRERA, including Govind Park B and Govind Park A. Its filings disclose 5 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if Govind Park B is delayed beyond 31 Aug 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Govind Park B?
The registered promoter entity is Vikram Sanjay Nimbalkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Govind Park B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Govind Park B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Govind Park B?
The professionals named in the filing: Architect: Mahendra Mugutrao Jadhav; Engineer: Yuvraj Suhas Nikam; Chartered Accountant: V S Jadhav And Company; Chartered Accountant: Samadhan Ramdas Kadam. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Govind Park B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback