ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / GOKULDHAM

Registered No litigation declared Residential / Group Housing project

GOKULDHAM

By GOKULDHAM

RG-MH-93122 · RERA P52700047203 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 1.50 crore secured on the land, in favour of THE PANDHARPUR URBAN CO OP BANK LTD PANDHARPUR

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
10 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 15%
46 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

GOKULDHAM is a Residential / Group Housing project by GOKULDHAM in Satara, Maharashtra, registered with MahaRERA as P52700047203 on 11 Oct 2022. Possession is promised by 31 Dec 2027. 10 of the 56 units on this registration are recorded sold or booked, and 10 of 18 construction stages are filed complete.

At a glance

Project

  • NameGOKULDHAM
  • TypeResidential / Group Housing
  • Location
    • -
    • LAXMINAGAR
    • Jadhavwadi (563279)
    • Phaltan
    • Satara
    • 415523
  • Pincode415523
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700047203
  • ReraGenie IDRG-MH-93122

Builder

  • NameGOKULDHAM
  • Entity typePartnership
  • PartnersSACHIN SADASHIV GOSAVI, KALPANA MANOJ PHADTARE, MANOJ NARAYAN PHADTARE, SUNIL NARAYAN PHADTARE
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Oct 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed110 files

Current status

18%10 of 56 units booked
48.7%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BULDING ANA3316016
BULDING BNA4440040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 15%.

BULDING A89%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BULDING B24%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered11
Open Space52
BuildingClosed/CoveredOpen SpaceTotal
BULDING A31518
BULDING B83745

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,891 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTHE PANDHARPUR URBAN CO OP BANK LTD PANDHARPUR
Secured amountRs 1.50 crore
CERSAI search filedYes
Declared on20 Sep 2025

Approvals and building plan

Sanctioning authorityCOLLECTOR OF SATARA
Permissible FSI6015.48
Proposed, not sanctioned3,515 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE
Estimated costRs 6.04 cr
Cost incurredRs 2.94 cr
Work done48.71%
BuildingWingEstimatedIncurred
BULDING BNARs 3.93 crRs 1.07 cr
BULDING ANARs 1.87 crRs 1.87 cr
-NARs 24.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL B ATAK
EngineerYASH CONSTRUCTIONS
Chartered AccountantTanmay Patil
PartnerRole in project
GOKULDHAM-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate 30-12-2025.pdf29 Jun 2026
Withdrawal Update Form 1File: Architect Certificate 30-03-2026.pdf29 Jun 2026
Withdrawal Update Form 2File: Engineers Certificate December Quater.pdf29 Jun 2026
Withdrawal Update Form 2File: Engineers certificate March Quater .pdf29 Jun 2026
Withdrawal Update Form 3File: CA CERTIFICATE DECEMBER 2025_removed.pdf29 Jun 2026
Withdrawal Update Form 3File: CA CERTIFICATE DECEMBER 2025_removed.pdf29 Jun 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf19 Jun 2026
Withdrawal Update Form 2File: Engineers Certificate June 2025.pdf19 Jun 2026
Withdrawal Update Form 3File: form 3- 30-09-2025.pdf19 Jun 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf17 Apr 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf17 Apr 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf17 Apr 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf17 Apr 2026
Withdrawal Update Form 2File: Engineers Certificate June 2025.pdf17 Apr 2026
Withdrawal Update Form 2File: Engineers Certificate June 2025.pdf17 Apr 2026
Withdrawal Update Form 2File: Engineers Certificate June 2025.pdf17 Apr 2026
Withdrawal Update Form 2File: Engineers Certificate June 2025.pdf17 Apr 2026
Withdrawal Update Form 3File: CA Certificate 30 June 2025.pdf17 Apr 2026
Withdrawal Update Form 3File: CA Certificate 30 June 2025.pdf17 Apr 2026
Withdrawal Update Form 3File: CA Certificate 30 June 2025.pdf17 Apr 2026
Withdrawal Update Form 3File: form 3- 30-09-2025.pdf17 Apr 2026
Withdrawal Update Form 1File: FORM-1 30-09-2025.pdf4 Mar 2026
Withdrawal Update Form 1File: FORM-1 30-09-2025.pdf4 Mar 2026
Withdrawal Update Form 2File: Engineers Certificate September 2025 (1).pdf4 Mar 2026
Withdrawal Update Form 2File: Engineers Certificate September 2025 (1).pdf4 Mar 2026
Withdrawal Update Form 3File: form 3- 30-09-2025.pdf4 Mar 2026
Withdrawal Update Form 3File: form 3- 30-09-2025.pdf4 Mar 2026
Form 1File: FORM-1 30-06-2024.pdf27 Jan 2026
Form 2File: FORM 2- 31-06-2024.pdf27 Jan 2026
Form 3File: FORM 3- 30-06-2024.pdf27 Jan 2026
Disclosure of Sold and Booked InventoryFile: sold and unsold final 31-06-2024.pdf27 Jan 2026
Form 1File: FORM 1 31-12-2023.pdf27 Jan 2026
Form 2File: FORM 2- 31-12-2023.pdf27 Jan 2026
Form 3File: Form -3 31-12-2023.pdf27 Jan 2026
Disclosure of Sold and Booked InventoryFile: final Sold and Unsold 31-12-2023.pdf27 Jan 2026
Form 1File: FORM 1- 30-06-2023.pdf19 Jan 2026
Form 2File: FORM 2- 30-06-2023.pdf19 Jan 2026
Form 3File: FORM 3- 31-06-2023.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD 30-06-2023.pdf19 Jan 2026
Form 1File: FORM 1- 30-09-2023.pdf19 Jan 2026
Form 2File: FORM 2- 30-09-2023.pdf19 Jan 2026
Form 3File: FORM 3- 31-09-2023.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD 30-09-2023.pdf19 Jan 2026
Form 1File: FORM 1- 31-12-2024.pdf19 Jan 2026
Form 2File: FORM 2- 30-12-2024.pdf19 Jan 2026
Form 3File: FORM 3- 31-12-2024.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD 31-12-2024.pdf19 Jan 2026
Form 1File: FORM-1 31-12-2022.pdf19 Jan 2026
Form 2File: FORM 2- 31-12-2022.pdf19 Jan 2026
Form 3File: FORM 3- 31-12-2022.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD 30-12-2022.pdf19 Jan 2026
Form 1File: Architect Certificate 31-03-2025.pdf19 Jan 2026
Form 2File: Form 2 Engineers Certificate 31-03-2025.pdf19 Jan 2026
Form 3File: CA Certificate 31-03-2025.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD MARCH 25.pdf19 Jan 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gokuldham CA certificate_compressed.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate form 2 31-12-2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Gokuldham sold unsold updation.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31-12-2024.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30-09-2024 updated nd uploaded.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Form 2 30-09-2024.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_certificate_30_July__2024[1]_organized.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate 02 August 2024.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate 30-06-2024.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certifiacte Form -2A (2).pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Gokuldham Building A unslod flats.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Gokuldham Building B unsold flats.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2.pdf23 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate 2A.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold unsold merged (5).pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form(2) Engineers certificate1.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form(2A) Engineers certificate (1).pdf16 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Engineers Certificate.pdf6 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Gokuldham.pdf1 Nov 2023
Disclosure of sold/ booked inventoryFile: ilovepdf_merged (31).pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Report Gokuldham_removed_compressed.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate SEPTEMBER Quarter.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Engineers Certificate Gokuldham.pdf20 Oct 2023

How this compares with Satara

18%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep GOKULDHAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LAXMINAGAR1,100+ in Satara

2 kmGOKULDHAMCompleted 9Lapsed / revoked 7Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: GOKULDHAM

GOKULDHAM has 2 registrations on MahaRERA, including GOKULDHAM and GOKULDHAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if GOKULDHAM is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GOKULDHAM?

The registered promoter entity is GOKULDHAM, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GOKULDHAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GOKULDHAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GOKULDHAM?

The professionals named in the filing: Architect: RAHUL B ATAK; Engineer: YASH CONSTRUCTIONS; Chartered Accountant: Tanmay Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOKULDHAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOKULDHAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOKULDHAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.