GOKUL DHAM APT
RG-MH-86059 · RERA P99000015713 · Last updated on MahaRERA portal: 18 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOKUL DHAM APT is a Residential / Group Housing project by SAAKAR ENTERPRISES in Palghar, Maharashtra, registered with MahaRERA as P99000015713 on 19 Mar 2018. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameGOKUL DHAM APT
- TypeResidential / Group Housing
- Location
- UMROLI STATION ROAD
- PARASH NATH NAGARI
- Umroli
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000015713
- ReraGenie IDRG-MH-86059
Builder
- NameSAAKAR ENTERPRISES
- Entity typePartnership
- PartnerRAJAN RAMESH PANDEY
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Mar 2018
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 6 Dec 2019)
- Buildings1 building record
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GOKUL DHAM APT | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GOKUL DHAM APT: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SHREENATH ENTERPRISES | Vasai-Virar City (M Corp) | Palghar |
| SHREENATH ENTERPERISES | Vasai-Virar City (M Corp) | Palghar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| SAAKAR ENTERPRISES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, Due to current Covid-19 ongoing Pandemic, completion of entire project within agreed date seems unachievable. Therefore, we request you to grant us further extension of time till 30-06-2023.
Reason as filed by the promoterDue to certain Change in norms of competent authority and lack of market demand
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000429014 | DINESH SAMARJEET YADAV | SAAKAR ENTERPRISES | 30/01/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed38
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Form B Declaration REVISED1.pdf | 18 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: EX 1_ARCHITECT COMPLETION LETTER.pdf | 18 Mar 2025 |
| Certificates of CA (Form 3)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY INCORPORATION CERTIFICATE.pdf | 18 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold as on 31 12 2024 signed.pdf | 18 Mar 2025 |
| Other - FinanceFile: REQUEST LETTER FOR EXTENSION signed.pdf | 18 Mar 2025 |
| Other - FinanceFile: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Other - FinanceFile: EX 1_ARCHITECT COMPLETION LETTER.pdf | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: NO QPR Declaration signed with arch compl letter.pdf | 18 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5_FY 2019-20.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5_FY 2020-21.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5_FY 2021-22.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5_FY 2022-23.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5_FY 2023-24.pdf | 12 Mar 2025 |
| Declaration in FORM BFile: Form B Declaration REVISED - converted.pdf | 19 Nov 2024 |
| Declaration in FORM BFile: Form B Declaration REVISED - converted.pdf | 19 Nov 2024 |
| Declaration about Commencement CertificateFile: DECLARATION CC SIGNED.pdf | 7 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A SIGNED.pdf | 7 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A SIGNED.pdf | 7 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOL DETAILS SIGNED OPT.pdf | 7 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 2018.pdf | 7 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2019.pdf | 7 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 SELF DECLARATION.pdf | 7 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SELF DECLARATION.pdf | 7 Jul 2021 |
| Building plan approvalFile: BLUE PRINT.pdf | 14 Mar 2018 |
| Layout approvalFile: LAYOUT APPROVAL.pdf | 14 Mar 2018 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 14 Mar 2018 |
| Details of encumbrancesFile: DETAILS OF ENCUMBRANCES.pdf | 14 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf | 14 Mar 2018 |
| Building Plan Approval (IOD)File: BLUE PRINT.pdf | 14 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 14 Mar 2018 |
| Declaration in FORM BFile: FORM B PANDE JI.pdf | 14 Mar 2018 |
| Certificates of CA (Form 3)File: CA LETTER.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: SAAKAR ENTERPRISES- RERA AGREEMENT pdf.pdf | 14 Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 38 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GOKUL DHAM APT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PARASH NATH NAGARI3,200+ in Palghar
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: SAAKAR ENTERPRISES
SAAKAR ENTERPRISES has 1 registration on MahaRERA, including GOKUL DHAM APT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that GOKUL DHAM APT shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GOKUL DHAM APT is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOKUL DHAM APT?
The registered promoter entity is SAAKAR ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOKUL DHAM APT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GOKUL DHAM APT?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GOKUL DHAM APT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOKUL DHAM APT?
The professionals named in the filing: Architect: AJAY WADE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOKUL DHAM APT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback