Home / Browse projects / Mumbai Suburban, Maharashtra / Godrej Prime
Godrej Prime
By Godrej Redevelopers (Mumbai) Pvt. Ltd.
RG-MH-08825 · RERA P51800000519 · Last updated on MahaRERA portal: 7 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 41 months past the filed date
- 4 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Godrej Prime is a Residential / Group Housing project by Godrej Redevelopers (Mumbai) Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000519 on 18 Jul 2017. Possession was promised by 30 May 2023 and is now 41 months past that date. 4 complaints are on record with the regulator.
At a glance
Project
- NameGodrej Prime
- TypeResidential / Group Housing
- Location
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800000519
- ReraGenie IDRG-MH-08825
Builder
- NameGodrej Redevelopers (Mumbai) Pvt. Ltd.
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Jul 2017
- Promised completion30 May 2023
- Revised completionNone
- Buildings17 building records
- Documents filed102 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| S1 | NA | 17 | 0 | 0 | 0 | 0 |
| S2 | NA | 18 | 0 | 0 | 0 | 0 |
| S3 | NA | 18 | 0 | 0 | 0 | 0 |
| S4 | NA | 18 | 0 | 0 | 0 | 0 |
| S5 | NA | 18 | 0 | 0 | 0 | 0 |
| S6 | NA | 18 | 0 | 0 | 0 | 0 |
| S7 | NA | 18 | 0 | 0 | 0 | 0 |
| S8 | NA | 18 | 0 | 0 | 0 | 0 |
| Nova - S9 | NA | 18 | 0 | 0 | 0 | 0 |
| T1 | NA | 17 | 0 | 0 | 0 | 0 |
| T2 | NA | 17 | 0 | 0 | 0 | 0 |
| T3 | NA | 17 | 0 | 0 | 0 | 0 |
| T4 | NA | 17 | 0 | 0 | 0 | 0 |
| T5 | NA | 17 | 0 | 0 | 0 | 0 |
| T6 | NA | 17 | 0 | 0 | 0 | 0 |
| T7 | NA | 17 | 0 | 0 | 0 | 0 |
| T8 | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building17
As on 7 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
178 of 187 construction stages are filed complete across 17 buildings. The stage furthest along is Podiums (if any), at 0%.
S191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S691%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S791%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
S891%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Nova - S991%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
T8100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 7 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
| Club House | Yes | 100% |
Parking filed995
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| S1 | 132 | 0 | 132 |
| S2 | 85 | 1 | 86 |
| S3 | 71 | 0 | 71 |
| S4 | 70 | 0 | 70 |
| S5 | 70 | 0 | 70 |
| S6 | 70 | 0 | 70 |
| S7 | 70 | 0 | 70 |
| S8 | 70 | 0 | 70 |
| Nova - S9 | 66 | 0 | 66 |
| T1 | 34 | 3 | 37 |
| T2 | 36 | 1 | 37 |
| T3 | 36 | 0 | 36 |
| T4 | 36 | 0 | 36 |
| T5 | 36 | 0 | 36 |
| T6 | 36 | 0 | 36 |
| T7 | 31 | 5 | 36 |
| T8 | 31 | 5 | 36 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Godrej Properties Limited (Development Manager) | Kurla | Mumbai Suburban |
| Sahakar Nagar Vibhag -2 Co-Op Hsg Soc Ltd | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | P G Patki Architects |
| Engineer | Raje Structural Consultants Pvt Ltd |
| Partner | Role in project |
|---|---|
| Godrej Redevelopers (Mumbai) Pvt. Ltd. | - |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000198485 | Vasudha M. Asher | Godrej Redevelopers (Mumbai) Private Limited | 27/09/2021 |
| CC006000000193227 | Nagesh SIngh Chauhan | Urvashi Panchal | 25/05/2020 |
| CC006000000241289 | Ravi Tewari | Godrej Redevelopers (Mumbai) Private Limited | 26/05/2022 |
| CC006000000408088 | CP Ravindra Menon | Godrej Redevelopers (Mumbai) Pvt. Ltd. | 06/11/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Mar 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jun 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 9 Aug 2024
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Prime Form 5 FY 2023 2204.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Prime Form 5 FY 2023 2204.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Prime Form 5 FY 2023 2204.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Prime Form 5 FY 2023 2204.pdf | 7 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing T1 to T8 OC Certificate dt 26th April 2019.pdf | 9 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing S2 to S9 Part Occupation Certificate dtd 27th Dec 2019.pdf | 9 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: S1 Full Occupation Certificate dtd 27th Dec 2019.pdf | 9 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SN 2 Tenanta Bldg Podium Toilet Approval Letter Devloper 03012020.pdf | 9 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing S8 OC Certificate dtd 4th Feb 2021.pdf | 9 Aug 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SN 2 Wing S5 and S7 OC letter dtd 16 June2022.pdf | 9 Aug 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Prime - Society Registration Certificate.pdf | 17 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Final Form 5 Prime SIGNED.pdf | 28 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Godrej Prime.pdf | 27 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dated 31st Dec 2021.pdf | 13 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ PRIME CERTIFICATE SEPT'22 - Final.pdf | 13 Jan 2023 |
| Certificates of CA (Form 3)File: Prime CA Certificate Sept 22 - Form 3.pdf | 12 Jan 2023 |
| Certificates of CA (Form 5)File: Godrej Prime Form 5 CA.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Godrej Prime Form 5 Annual Statement.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Godrej Prime Form 5 Annual Statement.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Godrej Prime_Combined.pdf | 30 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5.pdf | 30 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Godrej_Prime_Form_5.pdf | 30 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prime Architect Certificate 20-05-31 May.pdf | 6 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GODREJ PRIME CERTIFICATE NOV21 - Final.pdf | 6 Apr 2022 |
| Proforma of Allotment letterFile: Godrej Central updated AFS.pdf | 24 Nov 2021 |
| Proforma of Allotment letterFile: Godrej Central updated AFS Rehab Sale flats.pdf | 24 Nov 2021 |
| Certificates of CA (Form 5)File: Signed Godrej Prime_Audit Opinion_Form 5_Annexure 2-compressed.pdf | 30 Sep 2021 |
| Building plan approvalFile: SN2 Plot 1 Sale Wing S1 Full Occupation Plans dtd 27th Dec 2019.pdf | 21 Jun 2021 |
| Building Plan Approval (IOD)File: SN2 Plot 1 Sale Wing S1 Full Occupation Plans dtd 27th Dec 2019.pdf | 21 Jun 2021 |
| Building plan approvalFile: SN-2(Plot-2)Sale Wing-S2toS9PartOccupationCertificate.pdf | 16 Mar 2021 |
| Layout approvalFile: SN-2(Plot-2)SaleWing-S2toS9PartOccupationPlans.pdf | 16 Mar 2021 |
| Layout approvalFile: SN2S8WingPartOCPlan.pdf | 16 Mar 2021 |
| Building plan approvalFile: SN-2S8WingPartOCLetter.pdf | 16 Mar 2021 |
| Copy of Layout Approval (in case of layout)File: SN-2(Plot-2)SaleWing-S2toS9PartOccupationPlans.pdf | 16 Mar 2021 |
| Copy of Layout Approval (in case of layout)File: SN2S8WingPartOCPlan.pdf | 16 Mar 2021 |
| Building Plan Approval (IOD)File: SN-2(Plot-2)Sale Wing-S2toS9PartOccupationCertificate.pdf | 16 Mar 2021 |
| Building Plan Approval (IOD)File: SN-2S8WingPartOCLetter.pdf | 16 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Prime Form 5 - Signed.pdf | 30 Sep 2020 |
| Building plan approvalFile: Plot 1 Amended Letter 16-02-2018.pdf | 11 Oct 2019 |
| Layout approvalFile: Plot 1 Layout Approval 16-2-2018.pdf | 11 Oct 2019 |
| Copy of Layout Approval (in case of layout)File: Plot 1 Layout Approval 16-2-2018.pdf | 11 Oct 2019 |
| Building Plan Approval (IOD)File: Plot 1 Amended Letter 16-02-2018.pdf | 11 Oct 2019 |
| Certificates of CA (Form 5)File: Signed Form 5 - Prime - Upload 1.pdf | 30 Sep 2019 |
| Building plan approvalFile: SN-2 Wing T1 to T8 Occupation letter.pdf | 13 Jun 2019 |
| Layout approvalFile: SN2 SALE AUG 2018.pdf | 13 Jun 2019 |
| Building plan approvalFile: SN-II Plot-2 Sale Amended Approval MHADA Letter dt 21_08_2018.pdf | 13 Jun 2019 |
| Layout approvalFile: Rehab OC plan.pdf | 13 Jun 2019 |
| Copy of Layout Approval (in case of layout)File: SN2 SALE AUG 2018.pdf | 13 Jun 2019 |
| Copy of Layout Approval (in case of layout)File: Rehab OC plan.pdf | 13 Jun 2019 |
| Building Plan Approval (IOD)File: SN-2 Wing T1 to T8 Occupation letter.pdf | 13 Jun 2019 |
| Building Plan Approval (IOD)File: SN-II Plot-2 Sale Amended Approval MHADA Letter dt 21_08_2018.pdf | 13 Jun 2019 |
| Layout approvalFile: Building Plan.pdf | 9 May 2019 |
| Copy of Layout Approval (in case of layout)File: Building Plan.pdf | 9 May 2019 |
| Proforma of Allotment letterFile: Godrej Prime AFS.pdf | 9 May 2019 |
| Proforma of Allotment letterFile: Godrej Prime App Form (subvention).pdf | 9 May 2019 |
| Proforma of Allotment letterFile: RERA updated Application 23012019.pdf | 5 Feb 2019 |
| Proforma of Allotment letterFile: RERA updated Allotment 23012019.pdf | 5 Feb 2019 |
| Proforma of Allotment letterFile: Godrej Prime AFS 01022019 clean.pdf | 3 Feb 2019 |
| Certificates of CA (Form 5)File: Prime.pdf | 29 Sep 2018 |
| Certificates of CA (Form 5)File: Prime.pdf | 29 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN 2 Plot 1 CC.pdf | 13 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN 2 Plot 2 CC.pdf | 13 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN-2 Plot-2 (Sale) Full CC dated 26-02-2018.pdf | 4 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN-2 Plot-1 (Rehab-Sale) Full CC dated 26-02-2018.pdf | 4 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Prime Architect Certificate Dec 31 2017 Part 1.pdf | 19 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Prime Architect Certificate Dec 31 2017 Part 2.pdf | 19 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Prime Architect Certificate Dec 31 2017 Part 3.pdf | 19 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Prime Architect Certificate Dec 31 2017 Part 4.pdf | 19 Jan 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prime - RERA Engg Cert 31-12-2017.pdf | 19 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN 2 Plot 1.pdf | 17 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SN 2 Plot 2.pdf | 17 Jan 2018 |
| Building plan approvalFile: SN-02 Plot-2 (Sale) Approval letter 19-08-2017.pdf | 12 Oct 2017 |
| Building plan approvalFile: SN-02 Plot-1 (Rehab-Sale) Approval letter 19-08-2017.pdf | 12 Oct 2017 |
| Building Plan Approval (IOD)File: SN-02 Plot-2 (Sale) Approval letter 19-08-2017.pdf | 12 Oct 2017 |
| Building Plan Approval (IOD)File: SN-02 Plot-1 (Rehab-Sale) Approval letter 19-08-2017.pdf | 12 Oct 2017 |
| PAN CardFile: PAN - GR(M)PL.pdf | 13 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert Plot 1.pdf | 13 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert Plot 2.pdf | 13 Jul 2017 |
| Certificates of CA (Form 3)File: Prime - CA-Certificate Part 1.pdf | 13 Jul 2017 |
| Certificates of CA (Form 3)File: Prime - CA-Certificate Part 2.pdf | 13 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Godrej Prime on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 383 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Godrej Redevelopers (Mumbai) Pvt. Ltd.
Godrej Redevelopers (Mumbai) Pvt. Ltd. has 1 registration on MahaRERA, including Godrej Prime. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Godrej Prime shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Godrej Prime is delayed beyond 30 May 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Godrej Prime?
The registered promoter entity is Godrej Redevelopers (Mumbai) Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Godrej Prime?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Prime?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Godrej Prime?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Godrej Prime?
The professionals named in the filing: Architect: P G Patki Architects; Engineer: Raje Structural Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Prime?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.