Godrej Skyline Developers Limited has 8 registrations on MahaRERA, including Godrej Park Greens and Godrej Nurture. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 3 of its registrations.

8RERA registrations
4Past projects disclosed
on timeMedian delivery slip
3Registrations with litigation
Follow this developer. An email when Godrej Skyline Developers Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 8 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Godrej Park GreensP52100019639Mamurdi, Pune, 412101121099%20 Feb 2019Registered
FOREST GROVE AT GODREJ PARK GREENSP52100023129MAMURDI VILLAGE, Pune, 412101113999%2 Dec 2019Registered
Godrej NurtureP52100020686Mamurdi, Pune, 41210171499%3 May 2019Registered
GODREJ SERENEP52100047405MAMURDI, Pune, 41210155766%27 Oct 2022Registered
MADHUBANP52100045236VILLAGE MAMURDI, Pune, 41210132444%10 May 2022Registered
Mamurdi MHADA NorthP52100024142MAMURDI VILLAGE, Pune, 41210120599%21 Jan 2020Registered
GODREJ CARNIVALP52100047567MAMURDI, Pune, 41210115064%9 Nov 2022Registered
SPARKLE AT GODREJ SERENEP52100048467MAMURDI, Pune, 412101--3 Jan 2023Registered

What this promoter declares as its own experience

Godrej Skyline Developers Limited declares experience on 4 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

2 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether those projects were delivered on time.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
GODREJ PARK GREENS
31 Mar 202331 Mar 2023On time
GODREJ CENTRAL PARK
31 Mar 202331 Mar 2023On time
FOREST GROVE AT GODREJ PARK GREENS
P52100023129
30 Sep 2027Not completed yetOngoing
Godrej Park Greens
P52100019639
30 Mar 2028Not completed yetOngoing

Frequently asked questions

How do I verify Godrej Skyline Developers Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45309MH2016PTC287858 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Godrej Skyline Developers Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Godrej Skyline Developers Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the Godrej Skyline Developers Limited developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.