Home / Browse projects / Raigarh, Maharashtra / GLOBE FANTASIAA - MOONSTONE
GLOBE FANTASIAA - MOONSTONE
RG-MH-06358 · RERA P52000052361 · Last updated on MahaRERA portal: 28 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GLOBE FANTASIAA - MOONSTONE is a Residential / Group Housing project by GLOBE INDIA INFRA in Raigarh, Maharashtra, registered with MahaRERA as P52000052361 on 21 Aug 2023. Possession is promised by 31 Dec 2026. 29 of the 78 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameGLOBE FANTASIAA - MOONSTONE
- TypeResidential / Group Housing
- Location
- KASHELI ROAD
- NERAL
- Borle
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000052361
- ReraGenie IDRG-MH-06358
Builder
- NameGLOBE INDIA INFRA
- Entity typePartnership
- PartnersRAJESH ANANTRAO THAKARE, MADHAV JAGMOHAN SINGH, ASHOKE RAMESHLAL MANKANI, SHAKTI BALKISHAN SINGH, GAUTAM GOVIND SINGH, AMAN MADHAV SINGH, AMEETT ASHOKE MANKANI, JIYA SATISH MANKANI, kalpana dilip bhamare, KISHANBIHARI SATYANARAYAN KAGZI, NEHA GAGAN BARMECHA, shweta raja mankani
- Other registrations2 more →
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Aug 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed94 files
Current status
Figures as on 28 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Globe Fantasiaa - Moonstone | NA | 8 | 0 | 63 | 15 | 78 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 97%.
Globe Fantasiaa - Moonstone: 62% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 97% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed92
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Globe Fantasiaa - Moonstone | NA | Rs 5.00 cr | Rs 4.85 cr |
| - | NA | Rs 1.00 cr | Rs 80.00 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KASHELKAR DESIGNS PRIVATE LIMITED |
| Engineer | RAJESH THAKARE & ASSOCIATES |
| Engineer | RAJESH ANANTRAO THAKARE |
| Chartered Accountant | ANKUR SANGOI & ASSOCIATES |
| Chartered Accountant | NIKITA VISHAL LAPSHIA |
| Partner | Role in project |
|---|---|
| GLOBE INDIA INFRA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: (Form 1)_Architects Certificate_Moonstone_Dec 2025.pdf | 28 Mar 2026 |
| Withdrawal Update Form 2File: (Form 2)_Engineers Certificate_Moonstone_Dec 2025.pdf | 28 Mar 2026 |
| Withdrawal Update Form 3File: Form 3_Moonstone Dec 2025_Final_signed.pdf | 28 Mar 2026 |
| Form 5 (FY 2024-2025)File: Glone India Infra Form 5_FY 2024-25_Moonstone_Sign and Stamped.pdf | 5 Mar 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 23 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 23 Feb 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 23 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_Moonstone.pdf | 20 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: 7 Disclosure of sold booked inventory.pdf | 1 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31-03-2025 Enginers Certificate Moonstone globe india infra form 2.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Moonstone.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Moonstone 30 DEC 2024.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30SEPT 24 moonstone.pdf | 19 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MOONSTONE FORM3 SEPT 24_compressed.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 30 SEPT 2024 moonstone.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Moonstone 31 DEC 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Globe Fantasiaa Moonstone - Inventory 30SEPT 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Moonstone - Sold inventory - 31 DEC 2024.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: mOONSTONE fORM 2 AT THE TIME OF REGISTRATION.pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Moonstone 30 SEPT 2023.pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Moonstone 31 DEC 2023.pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 MOONSTOME 31 mARCH 2024.pdf | 10 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: mOONSTONE fORM 2 30 JUNE 2024.pdf | 10 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Moonstone AT THE TIME OF REGN JUNE 2023.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fORM 1 MOONSTONE FOR DEC 2023.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MOONSTONE MARCH 2024.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MOONSTONE15JULY2024.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MOONSTONE FORM 1 FOR SEPT 2023.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MOONSTONE fORM 3 DECLARATION FOR 31 mARCH 2024.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: For 31dec 23 Globe Fantasiaa moonstone Form3 declaration.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: For 30sept2023 Globe fantasiaa moonstone Form3 declaration.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Moonstone FOR 30APRIL2024_compressed.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Moonstone Form 3 fOR 30 jUNE 2024.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A moonstone 31mARCH 2024.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Globe Moonstone FY 23 24.pdf | 9 Oct 2024 |
| Form 3File: Moonstone Form 3 for 30 june 2024.pdf | 25 Sep 2024 |
| Form 2File: Moonstone Form 2 for 30.6.2024.pdf | 25 Sep 2024 |
| Form 1File: moonstone form 1 for 15.7.24.pdf | 25 Sep 2024 |
| Disclosure of Sold and Booked InventoryFile: MOONSTONE INVENTORY SOLD 30JUNE2024.pdf | 25 Sep 2024 |
| Form 5 (FY 2023-2024)File: Form 5 Globe Moonstone FY 23 24.pdf | 11 Sep 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Moonstone Arch certificate 25 JAN 2024.pdf | 6 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Moonstone Arch certificate 15 JULY 2024.pdf | 6 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Globe India Infra MOONSTONE FORM 2 30JUNE24.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Globe Fantasiaa Moonstone Inventory 30 9 2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Globe Fantasiaa Moonstone 31 12 2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: MOONSTONE 31MARCH 2024.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Globe Fantasiaa MOONSTONE INVENTORY SOLD 30JUNE2024.pdf | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Globe India infra Architect's certificate 29-3-2024 moonstone.pdf | 6 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: globe India infra engineer's certificate 31-3-2024 moonstone.pdf | 6 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Moonstone.pdf | 6 Jul 2024 |
| Other - LegalFile: moon stone 47-6 PURCHASE AGREEMENT COPY_compressed (1).pdf | 17 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: MOONSTONE - FINANCIAL ENCUMBRANCE.pdf | 10 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: MOONSTONE LEGAL ENCUMBRANCES.pdf | 10 Aug 2023 |
| Details of encumbrances concerned to LegalFile: MOONSTONE - FINANCIAL ENCUMBRANCE.pdf | 10 Aug 2023 |
| Details of encumbrances concerned to LegalFile: MOONSTONE LEGAL ENCUMBRANCES.pdf | 10 Aug 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200277041710_For_Asset_Based_Search_10_08_2023_12_55_25_188.pdf | 10 Aug 2023 |
| CERSAI detailsFile: MOONSTONE - CERSAI UNDERTAKING.pdf | 10 Aug 2023 |
| Other - LegalFile: MOONSTONE - INDEX 2.pdf | 10 Aug 2023 |
| Declaration about Commencement CertificateFile: Globe Fantasiaa-Moonstone Format D.pdf | 24 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GLOBE FANTASIAA - MOONSTONE FORM3.pdf | 24 Jul 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER GLOBE FANTASIAA- MOONSTONE 47-6.pdf | 24 Jul 2023 |
| Deviation Report with respect to Allotment letterFile: Globe Fantasiaa-Moonstone Declaration regarding no deviation with respect to Allotment let | 24 Jul 2023 |
| Layout approvalFile: Plan Approval Neral Plot 47-6 Globe Fantacia-Moonstone.pdf | 22 Jul 2023 |
| Building plan approvalFile: Plan Approval Neral Plot 47-6 Globe Fantacia-Moonstone.pdf | 22 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Moonstone encumbramce to legal.pdf | 22 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Moonstone encumbramce to legal.pdf | 22 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Plan Approval Neral Plot 47-6 Globe Fantacia-Moonstone.pdf | 22 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Approval Neral Plot 47-6 Globe Fantacia-Moonstone.pdf | 22 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GLOBE FANTASIAA MOONSTONE ARCHITECTCERTIFICATE.pdf | 22 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Globe Fantasiaa - Moonstone Engineer certificate final.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Aman Singh_Annexure A.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Ameett Mankani_Annexure A_.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Ashoke Mankani.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Gautam Singh.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_K B Kagzi.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Karan Singh.pdf | 22 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Madhav Singh.pdf | 22 Jul 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| GLOBE FANTASIAA- CELESTIAP52000052366 | NERAL, Raigarh | 46 | Aug 2023 | Ongoing | Dec 2026 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GLOBE FANTASIAA - MOONSTONE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NERAL5,900+ in Raigarh
Filed coordinates, straight-line distance. 127 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: GLOBE INDIA INFRA
GLOBE INDIA INFRA has 3 registrations on MahaRERA, including GLOBE FANTASIAA- CELESTIA and GLOBE FANTASIAA - MOONSTONE. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if GLOBE FANTASIAA - MOONSTONE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GLOBE FANTASIAA - MOONSTONE?
The registered promoter entity is GLOBE INDIA INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GLOBE FANTASIAA - MOONSTONE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GLOBE FANTASIAA - MOONSTONE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GLOBE FANTASIAA - MOONSTONE?
The professionals named in the filing: Architect: KASHELKAR DESIGNS PRIVATE LIMITED; Engineer: RAJESH THAKARE & ASSOCIATES; Engineer: RAJESH ANANTRAO THAKARE; Chartered Accountant: ANKUR SANGOI & ASSOCIATES; Chartered Accountant: NIKITA VISHAL LAPSHIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GLOBE FANTASIAA - MOONSTONE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback