Olympeo Neo City
RG-MH-47506 · RERA P52000014181 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 6 complaints at MahaRERA
- Completion date moved by 60 months
- 3 extensions taken
- Rs 18.15 crore secured on the land, in favour of CAPRI GLOBAL CAPITAL LIMITED
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Olympeo Neo City is a Others project by PRIZTINE INFRA LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000014181 on 13 Nov 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 291 of the 812 units on this registration are recorded sold or booked, and 35 of 176 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameOlympeo Neo City
- TypeOthers
- Location
- Maniwali
- Neral
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000014181
- ReraGenie IDRG-MH-47506
Builder
- NamePRIZTINE INFRA LLP
- Entity typePartnership
- PartnersPrabhat Ranjan, SAURAV KUMAR TUNTUN, INDERJEET SINGH PABLA, SATWINDER SINGH PABLA
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on13 Nov 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
- Buildings16 building records
- Documents filed197 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 5 | 5 | 50 | 0 | 50 |
| A2 | NA | 5 | 5 | 50 | 0 | 50 |
| A3 | NA | 5 | 5 | 50 | 0 | 50 |
| A4 | NA | 5 | 5 | 50 | 0 | 50 |
| A5 | NA | 5 | 5 | 50 | 0 | 50 |
| A6 | NA | 5 | 5 | 50 | 0 | 50 |
| A7 | NA | 5 | 5 | 50 | 0 | 50 |
| A8 | NA | 5 | 5 | 50 | 0 | 50 |
| B1 | NA | 5 | 5 | 55 | 0 | 55 |
| B2 | NA | 5 | 5 | 55 | 0 | 55 |
| B3 | NA | 5 | 5 | 55 | 0 | 55 |
| B4 | NA | 5 | 5 | 55 | 0 | 55 |
| B5 | NA | 5 | 5 | 55 | 0 | 55 |
| B6 | NA | 5 | 5 | 55 | 0 | 55 |
| B7 | NA | 5 | 5 | 55 | 0 | 55 |
| Commercial Plaza | NA | 2 | 2 | 0 | 27 | 27 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building16
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
35 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Installation of Lifts, at 75%.
A10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A333%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A470%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
A573%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A620%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A722%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 45% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A873%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B718%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Commercial Plaza32%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 33% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 30% |
| Landscaping & Tree Planting | Yes | 22% |
| Street Lighting | Yes | 20% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 10% |
| Solid Waste Management And Disposal | Yes | 10% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A1 | NA | Rs 2.16 cr | - |
| A2 | NA | Rs 2.16 cr | - |
| A3 | NA | Rs 2.16 cr | Rs 1.76 cr |
| A4 | NA | Rs 2.16 cr | Rs 2.16 cr |
| A5 | NA | Rs 2.16 cr | Rs 2.16 cr |
| A6 | NA | Rs 2.16 cr | Rs 1.02 cr |
| A7 | NA | Rs 2.16 cr | Rs 91.11 lakh |
| A8 | NA | Rs 2.16 cr | Rs 2.16 cr |
| B1 | NA | Rs 1.83 cr | - |
| B2 | NA | Rs 1.83 cr | - |
| B3 | NA | Rs 1.83 cr | - |
| B4 | NA | Rs 1.83 cr | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architect Vivek Kumar |
| Architect | Arunkumar Govind Giri |
| Architect | Sakshi Vinayak Khanorkar |
| Engineer | PRABHAT RANJAN |
| Engineer | Sushil Deshmukh |
| Chartered Accountant | Deepika Chandak Chartered Accountants |
| Chartered Accountant | Praveen Chandak and Associates |
| Chartered Accountant | R H Pothiwal & Associates |
| Partner | Role in project |
|---|---|
| PRIZTINE INFRA LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is under construction with Civil and Infrastructure work in progress, with 2 buildings (Building A8 & Building A5) complete and ready for possession, but progress of remaining buildings in project got hampered due to Pandemic and it has severely impacted the sales & collections. Because of prolonged liquidity constraints our construction timeline got impacted. Though significant work of the project is complete, but we would still need more time to complete the pending work and get Occupancy certificate from the competent authority.
Reason as filed by the promoterThe project is under construction with Civil and Infrastructure work in progress, with 3 buildings (Building A8, Building A4 & Building A5) complete and ready for possession, but project has still not fully recovered from impact of Pandemic. And sales & collections collections for project is yet to pick up. Because of prolonged liquidity constraints our construction timeline got impacted. Though significant work of the project is complete, but we would still need more time to complete the pending work and get Occupancy certificate from the competent authority. We hereby request you to grant us
Reason as filed by the promoterThe project is under construction with civil and infrastructure work in progress. Three buildings (A8, A4 & A5) are completed and ready for possession. However, the project is yet to fully recover from the impact of the COVID-19 pandemic. Sales and collections have been significantly affected, and prolonged liquidity constraints have impacted the construction timelines. Hence, we seek an extension of the project completion date up to 31st December 2027.
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000396055 | SANJAY SADASHIV SOLIM | PRIZTINE INFRA LLP | 03/06/2023 |
| CC12502721 | Mahtab Khurshid Shaikh | PRIZTINE INFRA LLP | 04/08/2025 |
| CC12502889 | Amar Dhurandhar | PRIZTINE INFRA LLP | 17/08/2025 |
| CC12503877 | Jaimini Sarkar | PRIZTINE INFRA LLP | 05/11/2025 |
| CC12600426 | Mayur Shivaji Jadhav | PRIZTINE INFRA LLP | 23/01/2026 |
| CC12600428 | SANDESH PANDURANG KANAL | PRIZTINE INFRA LLP | 23/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Nov 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Nov 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Nov 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed197
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 197 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Jun 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Jun 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_Jun 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_Jun 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate_Neo City_Jun 26.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate_Neo City_Jun 26.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Mar 2026.pdf | 29 Jun 2026 |
| Withdrawal Update Form 2File: Form 2_Mar 2026.pdf | 29 Jun 2026 |
| Withdrawal Update Form 3File: Form 3_Mar 2026.pdf | 29 Jun 2026 |
| Withdrawal Update Form 1File: Form 1_Dec 25 - 1.pdf | 19 Feb 2026 |
| Withdrawal Update Form 1File: Form 1_Dec 25 - 1.pdf | 19 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Dec_25.pdf | 19 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Dec-25.pdf | 19 Feb 2026 |
| Withdrawal Update Form 3File: CA Certificate_Neo City_Dec 25.pdf | 19 Feb 2026 |
| Withdrawal Update Form 3File: CA Certificate_Neo City_Dec 25.pdf | 19 Feb 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE Priztine Infra LLP 30-09-25.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE Priztine Infra LLP FORM 2 30-09-25.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: form 3 priztine infra.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: Form 1_June 25.pdf | 10 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_June 25.pdf | 10 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_June 25.pdf | 10 Oct 2025 |
| Form 2A (FY 2019-2020)File: Form 2A_March 20.pdf | 19 Sep 2025 |
| Form 2A (FY 2020-2021)File: Form 2A_March 21.pdf | 19 Sep 2025 |
| Form 2A (FY 2021-2022)File: Form 2A_March 22.pdf | 19 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_March 25.pdf | 19 Sep 2025 |
| Form 2A (FY 2023-2024)File: Form 2A_March 24.pdf | 19 Sep 2025 |
| Form 2A (FY 2022-2023)File: Form 2A_March 23.pdf | 19 Sep 2025 |
| Form 5 (FY 2024-2025)File: Form 5_FY 2024-25 .pdf | 19 Sep 2025 |
| Form 5 (FY 2023-2024)File: Form 5_FY 2023-24.pdf | 19 Sep 2025 |
| Form 5 (FY 2022-2023)File: Form 5_FY 2022-23.pdf | 19 Sep 2025 |
| Form 5 (FY 2021-2022)File: Form 5_FY 2021-22.pdf | 19 Sep 2025 |
| Form 5 (FY 2020-2021)File: Form 5_FY 2020-21.pdf | 19 Sep 2025 |
| Form 5 (FY 2019-2020)File: Form 5_FY 2019-20.pdf | 19 Sep 2025 |
| Form 5 (FY 2018-2019)File: Form 5_FY 2018-19.pdf | 19 Sep 2025 |
| Form 1File: Form 1_Dec 24.pdf | 28 Aug 2025 |
| Form 2File: Form 2_Dec 24.pdf | 28 Aug 2025 |
| Form 3File: Form 3_Dec 24.pdf | 28 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Dec 24.pdf | 28 Aug 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Neocity June 24 Form 2.pdf | 7 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Neocity March 24 Form 2.pdf | 7 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Neocity Sept 24 Form 2.pdf | 7 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Dec 24.pdf | 5 Apr 2025 |
| Certificates of CA (Form 3)File: Form 03.pdf | 5 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Olympeo Neocity.pdf | 5 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Soldbooked Inventory - Olympeo Neocity - converted.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 5 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 for FY 23-24 with DSC.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate.pdf | 9 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_11zon.pdf | 9 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3_merged_11zon.pdf | 9 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold-1-3.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold-4-6.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold-7-10.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3_Merged 1.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3_Merged 2.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3_Merged 3.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3_Merged 4.pdf | 6 Feb 2024 |
| Declaration in FORM BFile: Form B_Affidavit.pdf | 1 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 1 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_compressed.pdf | 1 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 1 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure on Sold Inventory_compressed.pdf | 1 Feb 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200294791169_For_Asset_Based_Search_27_01_2024_11_24_47_690.pdf | 1 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed_compressed-1-7.pdf | 1 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed_compressed-8-14.pdf | 1 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed_compressed-15-21.pdf | 1 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure in Other Real Estate Org.pdf | 1 Feb 2024 |
| Certificates of CA (Form 5)File: Form 5.pdf | 1 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 1 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Disclosure on separate Bank Account.pdf | 1 Feb 2024 |
| Certificates of CA (Form 5)File: Certificate_18-19.pdf | 24 Mar 2023 |
| Certificates of CA (Form 5)File: Certificate_19-20.pdf | 24 Mar 2023 |
| Certificates of CA (Form 5)File: Certificate_20-21.pdf | 24 Mar 2023 |
| Certificates of CA (Form 5)File: Certificate_21-22.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificate_18-19.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate_19-20.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Certificate_20-21.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Certificate_21-22.pdf | 24 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Adobe Scan 25-Feb-2023 (2)-1-3.pdf | 25 Feb 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Olympeo Riverside - Phase 1 | Village - Avsare Taluka - Karjat District - Raigad PIN CODE - 410101 | 280 | Completed | Jun 2018 | Jun 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 197 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Olympeo Neo City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Neral5,900+ in Raigarh
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
VRINDAVAN HEIGHTS
SAHAJANAND INFRATECH
See every Raigarh project, with the district possession charts
Builder: PRIZTINE INFRA LLP
PRIZTINE INFRA LLP has 1 registration on MahaRERA, including Olympeo Neo City. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Olympeo Neo City is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Olympeo Neo City?
The registered promoter entity is PRIZTINE INFRA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Olympeo Neo City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Olympeo Neo City?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Olympeo Neo City?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Olympeo Neo City?
The professionals named in the filing: Architect: Architect Vivek Kumar; Architect: Arunkumar Govind Giri; Architect: Sakshi Vinayak Khanorkar; Engineer: PRABHAT RANJAN; Engineer: Sushil Deshmukh; Chartered Accountant: Deepika Chandak Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Olympeo Neo City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.