GLOBE BUSINESS AVENUE
RG-MH-42072 · RERA P51700033290 · Last updated on MahaRERA portal: 2 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GLOBE BUSINESS AVENUE is a Mixed project by Globe Solitaire LLP in Thane, Maharashtra, registered with MahaRERA as P51700033290 on 15 Feb 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 48 of the 89 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameGLOBE BUSINESS AVENUE
- TypeMixed
- Location
- OFF MANPADA ROAD
- MIDC PHASE II
- Kalyan-Dombivali (M Corp.)
- Kalyan
- Thane
- 421204
- Pincode421204
- RERA no.P51700033290
- ReraGenie IDRG-MH-42072
Builder
- NameGlobe Solitaire LLP
- Entity typePartnership
- PartnersRAJESH ANANTRAO THAKARE, ASHWIN MADHAVJI CHANDAN, MADHAV JAGMOHAN SINGH, ASHOK RAMESHLAL MANKANI, KISHANBIHARI SATYANARAIN KAGZI, NEHA GAGAN BARMECHA, RAJARAM BACHRAJ PODDAR, RAMESH PARMANAND MANKANI, GAUTAM GOVIND SINGH, SHAKTI BALKISHAN SINGH, KARAN MADAV SINGH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Feb 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed157 files
Current status
Figures as on 2 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GLOBE SOLITAIRE | NA | 10 | 10 | 0 | 89 | 89 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GLOBE SOLITAIRE: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed22
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GLOBE SOLITAIRE | NA | Rs 25.00 cr | Rs 25.00 cr |
| - | NA | Rs 2.00 cr | Rs 2.00 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH THAKARE |
| Engineer | RAJESH THAKARE THAKARE |
| Chartered Accountant | ANKUR SANGOI & ASSOCIATES |
| Chartered Accountant | Nikita Vishal Lapasia |
| Chartered Accountant | NIKITA VISHAL LAPSHIA |
| Chartered Accountant | ANKUR SANGOI & ASSOCIATED |
| Partner | Role in project |
|---|---|
| Globe Solitaire LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoternearly 90% internal work is done and 30% work is only completed for external work like plumbing , plastering, waterproofing etc. So to finish the project and aquiring OC and dealing with all such formalities we need extension
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jan 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Feb 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed157
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 157 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Globe Solitaire LLP Architect Certificate _31 March 2026.pdf | 2 Jun 2026 |
| Withdrawal Update Form 2File: Form 2_Globe Solitaire LLP Engineers Certificate 31 March 2026.pdf | 2 Jun 2026 |
| Withdrawal Update Form 3File: Form 3_Globe Solitaire LLP March 2026_Signed.pdf | 2 Jun 2026 |
| Withdrawal Update Form 1File: (From 1)_Globe Solitaire LLP Architect Certificate Dec 2025.pdf | 27 Feb 2026 |
| Withdrawal Update Form 2File: (Form 2)_Globe Solitaire LLP Engineer Certificate Dec 2025.pdf | 27 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_Globe Solitaire LLP Dec 2025 (Q3)_Final_Signed.pdf | 27 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Globe Solitaire LLP 30sept25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Globe Solitaire LLP 30sept 25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: Globe Solitaire LLP Form3 Sep 2025vSigned.pdf | 17 Jan 2026 |
| Layout approvalFile: MIDC REVISED APPROVED PLAN B-22-1 Globe Business Avenue (2).pdf | 12 Jan 2026 |
| Form 1File: Architect Certificate Form 1 30th June 2022.pdf | 8 Jan 2026 |
| Form 2File: Q1 Engineer Certificate Form 2 30th June 2022.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q1 Disclosure of sold booked inventory 30th June 2022.pdf | 8 Jan 2026 |
| Form 1File: Architect Certificate Form 1 30th Sep 2022.pdf | 8 Jan 2026 |
| Form 2File: Q2 Engineer Certificate Form 2 30th Sep 2022.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold booked inventory 30th Sep 2022.pdf | 8 Jan 2026 |
| Form 1File: Q3 Architect Certificate Form 1 30th Dec 2022.pdf | 8 Jan 2026 |
| Form 2File: Q3 Engineer Certificate Form 2 30th Dec 2022.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold booked inventory 30th Dec 2022.pdf | 8 Jan 2026 |
| Form 1File: Q4 Architect Certificate Form 1 31st March 2023.pdf | 8 Jan 2026 |
| Form 2File: Q4 Engineer Certificate Form 2 31st March 2023.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold booked inventory 31st March 2023.pdf | 8 Jan 2026 |
| Form 1File: Q1 Architect Certificate Form 1 30th June 2023.pdf | 8 Jan 2026 |
| Form 2File: Q1 Architect Certificate Form 2 30th June 2023.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q1 Disclosure of sold booked inventory 30th June 2023.pdf | 8 Jan 2026 |
| Form 1File: Q1 Architect Certificate Form 1 30th June 2023.pdf | 8 Jan 2026 |
| Form 2File: Q2 Engineers Certificate Form 2 30th Sep 2023.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q2 Disclosure of sold booked inventory 30th Sep 2023.pdf | 8 Jan 2026 |
| Form 1File: Q3 Architect Certificate Form 1 31st Dec 2023.pdf | 8 Jan 2026 |
| Form 2File: Q3 Engineers Certificate Form 2 31st Dec 2023.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold booked inventory 31st Dec 2023.pdf | 8 Jan 2026 |
| Form 1File: Q4 Architect Certificate Form 1 31st March 2024.pdf | 8 Jan 2026 |
| Form 2File: Q4 Engineers Certificate Form 2 31st Dec 2024.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4 Disclosure of sold booked inventory 31st Dec 2024.pdf | 8 Jan 2026 |
| Form 1File: Q3 Architect Certificate Form 1 31 Dec 2024.pdf | 8 Jan 2026 |
| Form 2File: Q3 Engineers Certificate Form 2 31st Dec 2024.pdf | 8 Jan 2026 |
| Form 3File: Q3 Globe SOLITAIRE LLP Dec 24 FORM 3 signed.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold_ booked inventory Dec 2024.pdf | 8 Jan 2026 |
| Form 1File: Q4 Architect Certificate Form 1 31 March 2025.pdf | 8 Jan 2026 |
| Form 2File: Q4 Engineers Certificate Form 2 31st March 2025.pdf | 8 Jan 2026 |
| Form 3File: Form 3 Solitaire Signed_compressed.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4 March 2025 GLOBE SOLITAIRE SOLD BOOKED INVENTORY.pdf | 8 Jan 2026 |
| Form 1File: (Form 1 )_Q1 Architect Certificate 30th June 2022.pdf | 8 Jan 2026 |
| Form 2File: (Form 2)_Q1 Engineer Certificate 30th June 2022.pdf | 8 Jan 2026 |
| Form 3File: PDF.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory_Q1_ 30th June 2022.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FOR MARCH 2023.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FOR MARCH 2023.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FOR MARCH 2023.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FOR MARCH 2023.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FOR MARCH 2023.pdf | 8 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 FOR MARCH 23.pdf | 8 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 FOR MARCH 23.pdf | 8 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 FOR MARCH 23.pdf | 8 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 FOR MARCH 23.pdf | 8 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 FOR MARCH 23.pdf | 8 Jan 2026 |
| Withdrawal Update Form 3File: Form3signed_compressed.pdf | 8 Jan 2026 |
| Withdrawal Update Form 3File: Form3signed_compressed.pdf | 8 Jan 2026 |
| Withdrawal Update Form 3File: Form3signed_compressed.pdf | 8 Jan 2026 |
| Withdrawal Update Form 3File: Form3signed_compressed.pdf | 8 Jan 2026 |
| Withdrawal Update Form 3File: Form3signed_compressed.pdf | 8 Jan 2026 |
| Form 2A (FY 2022-2023)File: Engineers Certificate on Quality Assurance Form 2A FY 2022-23.pdf | 8 Jan 2026 |
| Form 2A (FY 2023-2024)File: Engineers Certificate on Quality Assurance Form 2A FY 2023-24.pdf | 8 Jan 2026 |
| Form 2A (FY 2021-2022)File: Form 2A_Quality Assurance Certificate_FY 2021-22.pdf | 8 Jan 2026 |
| Form 1File: Form 1_Globe Solitaire LLP Architect Certificate 30 june25.pdf | 7 Jan 2026 |
| Form 2File: Form 2_Globe Solitaire LLP Engineer certificate 30 june 2025.pdf | 7 Jan 2026 |
| Form 3File: Globe Solitaire LLP Form June 2025_Signed.pdf | 7 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Globe Solitaire LLP Sold inventory 30 june 25.pdf | 7 Jan 2026 |
| Form 1File: Form 1 Globe Solitaire LLP 30sept25.pdf | 7 Jan 2026 |
| Form 2File: Form 2_Globe Solitaire LLP 30sept 25.pdf | 7 Jan 2026 |
| Form 3File: Globe Solitaire LLP Form3 Sep 2025vSigned.pdf | 7 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: final 30092025 Globe Solitaire LLP Sold and Booked Inventory.pdf | 7 Jan 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 157 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GLOBE BUSINESS AVENUE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MIDC PHASE II7,600+ in Thane
Constrcution of 2557 EWS tenements at S.No.157
ARUN SHANKARRAO BORGAVE
Runwal Gardens Phase I
Runwal Residency Private Limited
Runwal Garden City Cluster 6 Tower 6 to 9
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 6A Bldg No. 53-54
Runwal Residency Private Limited
RGC Runwal My City EWS - LIG Building
HORIZON PROJECTS PVT LTD
BALAJI ESTATE PHASE 2
M/S SAI BALAJI BUILDCON
See every Thane project, with the district possession charts
Builder: Globe Solitaire LLP
Globe Solitaire LLP has 1 registration on MahaRERA, including GLOBE BUSINESS AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if GLOBE BUSINESS AVENUE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GLOBE BUSINESS AVENUE?
The registered promoter entity is Globe Solitaire LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GLOBE BUSINESS AVENUE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GLOBE BUSINESS AVENUE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GLOBE BUSINESS AVENUE?
The professionals named in the filing: Architect: RAJESH THAKARE; Engineer: RAJESH THAKARE THAKARE; Chartered Accountant: ANKUR SANGOI & ASSOCIATES; Chartered Accountant: Nikita Vishal Lapasia; Chartered Accountant: NIKITA VISHAL LAPSHIA; Chartered Accountant: ANKUR SANGOI & ASSOCIATED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GLOBE BUSINESS AVENUE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback