Registered Litigation declared Others project

GINI VIVANTE PHASE 01

By Gini Citicorp Realty LLP

RG-MH-27431 · RERA P52100034447 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 12 cases
  • 7 complaints at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
25 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 90%
44 of 581Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 225 documents Report an error

GINI VIVANTE PHASE 01 is a Others project by Gini Citicorp Realty LLP in Pune, Maharashtra, registered with MahaRERA as P52100034447 on 5 Apr 2022. Possession is promised by 31 Dec 2026. 537 of the 581 units on this registration are recorded sold or booked, and 25 of 33 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameGINI VIVANTE PHASE 01
  • TypeOthers
  • Location
    • VILLAGE KIWALE
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034447
  • ReraGenie IDRG-MH-27431

Builder

  • NameGini Citicorp Realty LLP
  • Entity typePartnership
  • GSTIN27AAJFG4973H1Z1
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersGautam Vinod Harlalka, Manish Vinod Harlalka, Pranav Deepak Harlalka, Deepak Vishwanath Harlalka, Vinod Sewaram Harlalka, Karan Deepak Harlalka, Gautam Vinod Harlalka, Pranav Deepak Harlalka, Vinod Sewaram Harlalka, Manish Vinod Harlalka, Karan Deepak Harlalka, Deepak Vishwanath Harlalka
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredApr 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed225 files

Current status

92%537 of 581 units booked
96.4%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING - A1NA232015312165
BULIDING - A2NA232015312165
BUILDING - A3NA232023318251

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 90%.

BUILDING - A1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BULIDING - A2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING - A372%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)80%
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes20%
Street LightingYes20%
Community BuildingsYes10%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes30%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1845

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,845
Closed/Covered1,845
BuildingClosed/CoveredTotal
BUILDING - A1615615
BULIDING - A2615615
BUILDING - A3615615

Land and ownership39

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,044 sq m
Land owned byThe promoter, with other names on the file
Named landowners39
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2025
LandownerVillageDistrict
Rajesh Jeevan UttamchandaniWAGHOLIPune
Pravin Dadabhau GaikwadKivalePune
Pradnya Pravin GaikwadKivalePune
WINDSOR TOWN AND COUNTRY INDIA PRIVATE LIMITEDPune (M Corp.)Pune
VIJAY NARAYAN GAIKWADKivalePune
LAXMIBAI KASHINATH JAGTAPKivalePune
YASHWANT BANDU GAIKWADKivalePune
SAYAJI BANDU GAIKWADKivalePune
SUNIL DADU GAIKWADKivalePune
VIJAY KUNDLIK ROKADEKivalePune
VILAS KUNDALIK ROKDEKivalePune
ARUN KUNDALIK ROKDEKivalePune
SUDHIR KUNDLIK ROKADEKivalePune
SHOBHA YASHWANT GAIKWADKivalePune
RAVI SADASHIV BHOSALEKivalePune
KUNAL RAVI BHOSALEKivalePune
SHUBHAM RAVI BHASALEKivalePune
PUSHPA MARUTI GAIKWADKivalePune
ANITA ARUN KAMBLEKivalePune
KALPANA ULHAS KAMBLEKivalePune
JANABAI ARJUN GAIKWADKivalePune
DEEPALI MARUTI GAIKWADKivalePune
PRASHANT MARUTI GAIKWADKivalePune
MAYUR MARUTI GAIKWADKivalePune
RAVINDRA ARJUN GAIKWADKivalePune
RAHUL ARJUN GAIKWADKivalePune
VIKAS MARUTI GAIKWADKivalePune
SUDHIR SANJAY GAIKWADKivalePune
SUNITA VIJAY VISHWAKARMAKivalePune
SUWARNA LAXMAN JADHAVKivalePune
SANGITA SANJAY GAIKWADKivalePune
SANTOSH ARJUN GAIKWADKivalePune
SANDHYA VASANT MOREKivalePune
MANGAL DADU KADAMKivalePune
ANJANABAI TUKARAM GAIKWADKivalePune
SHEELA PRAVIN KAMBLEKivalePune
SUNITA SANDEEP SASANEKivalePune
PRAVIN TUKARAM GAIKWADKivalePune
NIRMALA CHANDRAKANT SHINDEKivalePune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI52049.75
Proposed, not sanctioned50,684 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5C/Li MITTAL COURT,224,NARIMAN POINT,MUMBAI - 400021
Estimated costRs 144.45 cr
Cost incurredRs 139.25 cr
Work done96.4%
BuildingWingEstimatedIncurred
BUILDING - A3NARs 49.31 crRs 44.73 cr
BUILDING - A1NARs 39.50 crRs 39.50 cr
BULIDING - A2NARs 38.31 crRs 38.31 cr
-NARs 17.33 crRs 16.71 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX Architects Associates
EngineerSiddharth N Shitole
EngineerSUHAS ASHOK PATIL
Chartered AccountantDipali Shelar & company
Chartered AccountantPatel and Sharma
Chartered AccountantCA Atul Salgia
Chartered AccountantASAK & Co
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates
PartnerRole in project
Gini Citicorp Realty LLP-

Litigation declared12

CaseCourtStatus
829/2015Pune District CourtClosed
984/2015Pune District CourtClosed
472/2016Pune District CourtClosed
492/2017Pune District CourtClosed
503/2016High Court MumbaiClosed
1729/2021Pune District CourtClosed
636/2021Pune District CourtOngoing
1020/2017Sub divisional MaigistrateClosed
720/2014Pune District CourtClosed
320/2022Pune District CourtClosed
726/2022Pune Civil CourtClosed
726/2022Pune Civil CourtClosed

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000340684Gautam HarlalkaMrs. Deepika Kumari Choudhary11/04/2024
CC005000000340763Gautam HarlalkaMrs.Sonali Santosh Vispute12/04/2024
CC005000000340764Gautam HarlalkaMr. Mahendra Singh12/04/2024
CC005000000340765Gautam HarlalkaMr. Mahendra Singh12/04/2024
CC005000000340778Gautam HarlalkaDr. Shankar Sudhir Dakua13/06/2024
CC005000000411089VIJAY NARAYAN GAIKWADM/S. WINDSAR TOWN & COUNTRY INDIA PVT. LTD THROUGH IT'S DIRECTOR MRS. VIBHA VIKARAM BOKE07/06/2024
CC12600785Gini Citicorp Realty LLPMr Umesh Hanumant Pawar11/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed225

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 225 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: GV01 Form 1 Mar 26.pdf24 Apr 2026
Withdrawal Update Form 2File: GV01 FORM 2 MAR 26.pdf24 Apr 2026
Withdrawal Update Form 3File: FINAL FORM 3 Mar 26_compressed.pdf24 Apr 2026
Withdrawal Update Form 1File: GV01 FORM 1 DEC.pdf30 Jan 2026
Withdrawal Update Form 2File: GV01 FORM 2 DEC.pdf30 Jan 2026
Withdrawal Update Form 3File: GV01 FORM 3 DEC_compressed.pdf30 Jan 2026
Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) (1).pdf26 Nov 2025
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf26 Nov 2025
Form 2A (FY 2024-2025)File: GV 01 FORM 2A 24-25.pdf26 Nov 2025
Form 3File: form 3 scanned Signed Final.pdf7 Nov 2025
Form 1File: GV01 Form 1 June 24.pdf7 Nov 2025
Form 2File: GV01 Form 2 June 24.pdf7 Nov 2025
Disclosure of Sold and Booked InventoryFile: GV01 SOLD UNSOLD JUNE 24 signed.pdf7 Nov 2025
Form 3File: GV01 Form 3 Sep 2024.pdf7 Nov 2025
Form 2File: GV01 Form 2 Sep 24.pdf7 Nov 2025
Form 1File: GV01 Form 1 Sep 2024.pdf7 Nov 2025
Disclosure of Sold and Booked InventoryFile: GV 01 Sold Unsold Sep 24.pdf7 Nov 2025
Form 3File: 02GV 01 FORM 3 DEC 24_11zon (1).pdf7 Nov 2025
Form 2File: GV 01 FORM 2 DEC 24.pdf7 Nov 2025
Form 1File: GV 01 FORM 1 DEC 24.pdf7 Nov 2025
Disclosure of Sold and Booked InventoryFile: GV 01 SOLD UNSOLD DEC 24.pdf7 Nov 2025
Form 3File: Sign Gini vivante phase 1 FORM 3 310325_compressed_11zon.pdf7 Nov 2025
Form 2File: Gini vivante phase 1 FORM 2 .pdf7 Nov 2025
Form 1File: Gini vivante phase 1 FORM 1 310325.pdf7 Nov 2025
Disclosure of Sold and Booked InventoryFile: Gini vovante phase 1 SOLD UNSOLD 31325.pdf7 Nov 2025
Withdrawal Update Form 1File: Gini Vivante 01 Form 1 Sep 25.pdf7 Nov 2025
Withdrawal Update Form 1File: Gini Vivante 01 Form 1 Sep 25.pdf7 Nov 2025
Withdrawal Update Form 2File: Gini Vivante 01 Form 2 Sep 25.pdf7 Nov 2025
Withdrawal Update Form 2File: Gini Vivante 01 Form 2 Sep 25.pdf7 Nov 2025
Withdrawal Update Form 3File: Gini Vivante 01 Form 3 Sep 25_with sold unsold.pdf7 Nov 2025
Withdrawal Update Form 3File: Gini Vivante 01 Form 3 Sep 25_with sold unsold.pdf7 Nov 2025
Form 5 (FY 2022-2023)File: FORM 5 22-23 (GV-PH-01).pdf6 Oct 2025
Form 5 (FY 2023-2024)File: GV01 FORM 5 23-24.pdf6 Oct 2025
Form 5 (FY 2024-2025)File: GV 01 FORM 5 24-25.pdf30 Sep 2025
Building plan approvalFile: Part6 - A4.pdf18 Aug 2025
Building plan approvalFile: Part7 - A4.pdf18 Aug 2025
Building plan approvalFile: Part8 - A4.pdf18 Aug 2025
Building plan approvalFile: Part9 - A5.pdf18 Aug 2025
Building plan approvalFile: Part10 - A3.pdf18 Aug 2025
Building plan approvalFile: Part11 - A3.pdf18 Aug 2025
Building plan approvalFile: Part12 - A3.pdf18 Aug 2025
Building plan approvalFile: Part13 - A3.pdf18 Aug 2025
Building plan approvalFile: Part14 - A3.pdf18 Aug 2025
Building plan approvalFile: Part15 - B1 Mhada.pdf18 Aug 2025
Building plan approvalFile: Part16 - B1 Mhada.pdf18 Aug 2025
Building plan approvalFile: Part19- A4 Wing 1st Floor Plan.pdf18 Aug 2025
Building plan approvalFile: Part22- A5 Wing.pdf18 Aug 2025
Building plan approvalFile: Part29 - A5 Wing.pdf18 Aug 2025
Building plan approvalFile: Part30 - A7 Wing.pdf18 Aug 2025
Building plan approvalFile: Part31 - A7 Wing.pdf18 Aug 2025
Building plan approvalFile: Part32 - A7 Wing.pdf18 Aug 2025
Building plan approvalFile: Part33 - A7 Wing.pdf18 Aug 2025
Building plan approvalFile: Part34 - A11 Wing.pdf18 Aug 2025
Building plan approvalFile: Part35 - A11 Wing.pdf18 Aug 2025
Building plan approvalFile: Part36 - A11 Wing.pdf18 Aug 2025
Building plan approvalFile: Part37 - A12 Wing.pdf18 Aug 2025
Building plan approvalFile: Part38 - A12 Wing.pdf18 Aug 2025
Building plan approvalFile: Part39 - A12 Wing.pdf18 Aug 2025
Withdrawal Update Form 1File: G V01 Form 1 June 25.pdf30 Jul 2025
Withdrawal Update Form 1File: G V01 Form 1 June 25.pdf30 Jul 2025
Withdrawal Update Form 2File: G V01 Form 2 June 25.pdf30 Jul 2025
Withdrawal Update Form 2File: G V01 Form 2 June 25.pdf30 Jul 2025
Withdrawal Update Form 3File: G V01 Form 3 June 25_11zon (1).pdf30 Jul 2025
Withdrawal Update Form 3File: G V01 Form 3 June 25_11zon (1).pdf30 Jul 2025
Layout approvalFile: 1-40 Layout .pdf18 Jul 2025
Building plan approvalFile: Part2 - Lower ground Floor.pdf18 Jul 2025
Building plan approvalFile: Part3 - Ground Floor.pdf18 Jul 2025
Building plan approvalFile: Part4 - UG.pdf18 Jul 2025
Building plan approvalFile: Part5 -A 1.pdf18 Jul 2025
Building plan approvalFile: Part6 - A4.pdf18 Jul 2025
Building plan approvalFile: Part7 - A4.pdf18 Jul 2025
Building plan approvalFile: Part8 - A4.pdf18 Jul 2025
Building plan approvalFile: Part9 - A5.pdf18 Jul 2025
Building plan approvalFile: Part10 - A3.pdf18 Jul 2025
Building plan approvalFile: Part11 - A3.pdf18 Jul 2025
Building plan approvalFile: Part12 - A3.pdf18 Jul 2025
Building plan approvalFile: Part13 - A3.pdf18 Jul 2025
Building plan approvalFile: Part14 - A3.pdf18 Jul 2025
Building plan approvalFile: Part15 - B1 Mhada.pdf18 Jul 2025
Building plan approvalFile: Part16 - B1 Mhada.pdf18 Jul 2025

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
GINI VIVANTE PHASE 02P52100050601KIWALE, Pune621Apr 2023OngoingDec 2027Not due yet
Harlalka HeightsSitaram Poddar Marg Fanaswadi36-CompletedMay 2017Late, Jun 2017
Gini Viviana Phase 1Survey No 38-1 Balewadi191-CompletedMay 2016Late, May 2017
Gini Bellina Phase 1off Porwal Road Lohegaon140-CompletedJan 2014Late, Mar 2015

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GINI VIVANTE PHASE 01 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILLAGE KIWALE13,700+ in Pune

2 kmGINI VIVANTE PHASE 01Completed 51Lapsed / revoked 36Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: Gini Citicorp Realty LLP

Gini Citicorp Realty LLP has 8 registrations on MahaRERA, including Gini Viviana F Bldg Phase 2 and GINI BELVISTA - PHASE I. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GINI VIVANTE PHASE 01 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GINI VIVANTE PHASE 01?

The registered promoter entity is Gini Citicorp Realty LLP, a partnership as per the filing. Its GSTIN 27AAJFG4973H1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GINI VIVANTE PHASE 01?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GINI VIVANTE PHASE 01?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GINI VIVANTE PHASE 01?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GINI VIVANTE PHASE 01?

The professionals named in the filing: Architect: CUBIX Architects Associates; Engineer: Siddharth N Shitole; Engineer: SUHAS ASHOK PATIL; Chartered Accountant: Dipali Shelar & company; Chartered Accountant: Patel and Sharma; Chartered Accountant: CA Atul Salgia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GINI VIVANTE PHASE 01?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GINI VIVANTE PHASE 01. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GINI VIVANTE PHASE 01 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.