Home / Browse projects / Pune, Maharashtra / GINI ARIA - PHASE 2

Completed No litigation declared Residential / Group Housing project

GINI ARIA - PHASE 2

By Gini Construction Pvt Ltd

RG-MH-98061 · RERA P52100054760 · Last updated on MahaRERA portal: 24 Jan 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Basement (if any), 0%
23 of 65Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

GINI ARIA - PHASE 2 is a Residential / Group Housing project by Gini Construction Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100054760 on 12 Feb 2024. The registration is recorded completed; possession was promised by 30 Jun 2026. 42 of the 65 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameGINI ARIA - PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Survey No.16
    • Hissa No.2/2A/1(P)
    • Yevlewadi
    • YAWALEWADI
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054760
  • ReraGenie IDRG-MH-98061

Builder

  • NameGini Construction Pvt Ltd
  • Entity typeCompany
  • Managing DirectorsDeeapk Vishwanath Harlalka, Manish Vinod Harlalka, Gautam Vinod Harlalka
  • Other registrations4 more →
  • Completed5 of 5
  • Declared earlier projects6 →

Key dates

this monthRegisteredFeb 2024PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Feb 2024
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed88 files

Current status

65%42 of 65 units booked
100.0%Work done, per cost certificate

Figures as on 24 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GINI ARIA - PHASE 2 B BUILDING, Wing BNA111165065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

GINI ARIA - PHASE 2 B BUILDING, Wing B: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered65

Land and ownership11

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,461 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jul 2025
LandownerVillageDistrict
DATTOBA VITHOBA PADWALYAWALEWADIPune
YAMUNA DATTU PADWALYAWALEWADIPune
SUREKHA RAJENDRA WALHEKARYAWALEWADIPune
BABLU RAJENDRA WALHEKARYAWALEWADIPune
AKSHAY RAJENDRA WALHEKARYAWALEWADIPune
DEWIDAS DATTU PADWALYAWALEWADIPune
BALASAHEB DATTOBA PADWALYAWALEWADIPune
PRAMILA BALASAHEB PADWALYAWALEWADIPune
SHITAL SHITAL JAINPune (M Corp.)Pune
AMIT MAHENDRA SHAHPune (M Corp.)Pune
VAISHALI DEVIDAS PADWALYAWALEWADIPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI5365.6
Proposed, not sanctioned4,896 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5 C/ II Mittal Court, 224, Nariman Point, Mumbai, Maharashtra-400021
Estimated costRs 9.32 cr
Cost incurredRs 9.32 cr
Work done100.0%
BuildingWingEstimatedIncurred
GINI ARIA - PHASE 2 B BUILDING, Wing BNARs 8.20 crRs 8.20 cr
-NARs 1.12 crRs 1.12 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX Architects Associates
EngineerSiddharth N Shitole
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates
Chartered AccountantPatel and Sharma
PartnerRole in project
Gini Construction Pvt Ltd-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARIA FORM 1 DEC.pdf24 Jan 2026
Withdrawal Update Form 2File: Gini Aria Ph 02 _ Form 2_ Sep 25.pdf24 Jan 2026
Withdrawal Update Form 3File: ARIA FORM 3 DEC.pdf24 Jan 2026
Form 2A (FY 2023-2024)File: Form II A - Aria-Phase 2-B-Wing 31032024.pdf26 Dec 2025
Form 2A (FY 2024-2025)File: GA 02 FORM 2A 24-25.pdf26 Nov 2025
Withdrawal Update Form 1File: Gini Aria Ph 02 _ Form 1 _ Sep 25.pdf4 Nov 2025
Withdrawal Update Form 2File: Gini Aria Ph 02 _ Form 2_ Sep 25.pdf4 Nov 2025
Withdrawal Update Form 3File: Gini Aria Ph 02 _ Form 3 _ Sep 25 mERGED.pdf4 Nov 2025
Form 5 (FY 2023-2024)File: GA02 FORM 5 23-24.pdf6 Oct 2025
Form 5 (FY 2024-2025)File: ARIA 2 FORM 5 24-25.pdf30 Sep 2025
Form 1File: G Ar 02 FOrm 1 June 25.pdf22 Jul 2025
Form 2File: G Ar 02 FOrm 2 June 25.pdf22 Jul 2025
Form 3File: G Ar 02 FOrm 3 June 25_compressed.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: G Ar 02 Inventory June 25.pdf22 Jul 2025
Form 1File: AM Q4 23-24 ARCH.pdf22 Jul 2025
Form 2File: AM 02 Q4 23-24 ENG.pdf22 Jul 2025
Form 3File: AM 02 Q4 23-24 CA.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: AM Q4 23-24 SOLD-UNSOLD.pdf22 Jul 2025
Form 1File: Gini aria phase 2.pdf22 Jul 2025
Form 2File: gini aria phase 2.pdf22 Jul 2025
Form 3File: GA02 Form 3 JUNE 24-Signed.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf22 Jul 2025
Form 1File: GA 02 Form 1 Sep 24.pdf22 Jul 2025
Form 2File: GA 02 Form 2 sep 2024.pdf22 Jul 2025
Form 3File: GA 02 Form 3 Sep 2024.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: GA 02 Sold Usold Sep 24.pdf22 Jul 2025
Form 1File: 01 Form 1 Dec 24_0001.pdf22 Jul 2025
Form 2File: 02 GA 02 FORM 2 DEC 24.pdf22 Jul 2025
Form 3File: 03 GA 02 FORM 3 DEC 24- Final.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: 04 GA 02 SOLD UNSOLD DEC 24.pdf22 Jul 2025
Form 1File: A2 FORM 1 310325.pdf22 Jul 2025
Form 2File: A2 FORM 2 310325.pdf22 Jul 2025
Form 3File: A2 FORM 3 310325.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: A2 SOLD UNSOLD 310325.pdf22 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sign A2 FORM 3 310325_compressed.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A2 FORM 1 310325.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: A2 FORM 3 310325_compressed.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: A2 FORM 2 310325.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: A2 SOLD UNSOLD 310325.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 Form 1 Dec 24_0001.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 GA 02 FORM 3 DEC 24- Final.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 GA 02 FORM 2 DEC 24.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: 04 GA 02 SOLD UNSOLD DEC 24.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GA 02 Form 1 Sep 24.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GA 02 Form 3 Sep 2024.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GA 02 Form 2 sep 2024.pdf13 Nov 2024
Disclosure of sold/ booked inventoryFile: GA 02 Sold Usold Sep 24.pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: GA02 FORM 5 23-24.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gini aria phase 2.pdf9 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: gini aria phase 2.pdf9 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aria Phase 2 Final.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: GA 02 SOLD UNSOLD.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GA 02 Q4 23-24 ENG.pdf10 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GA 02 Q4 23-24 ARCH.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: GA 02 Q4 23-24 SOLD-UNSOLD.pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GA 02 Q4 23-24 CA_compressed.pdf10 May 2024
Copy of the legal title reportFile: GA PH-02 LEGAL TITLE REPORT - Final - 4.pdf29 Jan 2024
Proforma of Agreement for saleFile: Draft Agreement - Gini Aria Phase 02 - RERA (03012024).pdf4 Jan 2024
Other - LegalFile: GA PH-02 Clarification_regarding_Land_Area[1].pdf4 Jan 2024
Other - LegalFile: GA PH-02 Declaration_regarding_Landowner[1].pdf4 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK AC FOR REAL ESTATE PROJECTS (GA-PH-02).pdf3 Jan 2024
Other - TechnicalFile: SS of Mail_CC Authentication.pdf27 Dec 2023
Layout approvalFile: 01-07 Layout_Highlighted_changes.pdf29 Nov 2023
Building plan approvalFile: 02-07 Parking .pdf29 Nov 2023
Building plan approvalFile: 03-07 Floors 03-05-07-09-11 and 02-04-06-10 .pdf29 Nov 2023
Building plan approvalFile: 04-07 Floors 01 and 08 .pdf29 Nov 2023
Building plan approvalFile: 05-07 Section AA.pdf29 Nov 2023
Copy of Layout Approval (in case of layout)File: 01-07 Layout_Highlighted_changes.pdf29 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 02-07 Parking .pdf29 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 03-07 Floors 03-05-07-09-11 and 02-04-06-10 .pdf29 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 04-07 Floors 01 and 08 .pdf29 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 05-07 Section AA.pdf29 Nov 2023
Declaration in FORM BFile: GA-PH-02 FORM-B AFFIDAVIT CUM DECLARATION.pdf29 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_GINI ARIA PHASE 02_Reg_Signed_11zon.pdf29 Nov 2023
Proforma of Allotment letterFile: Model_Form_of_Allotment_Letter_(2)[1].pdf28 Nov 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ALLOTMENT LETTER.pdf27 Nov 2023
Deviation Report with respect to model copy of AgreementFile: GA PH-02 DEVIATION FROM MODEL AGREEMENT_11zon.pdf27 Nov 2023
Details of encumbrances concerned to FinanceFile: Declaration of Encumbrances concerned to Finance.pdf22 Nov 2023
Details of encumbrances concerned to FinanceFile: Declaration of Encumbrances concerned to Legal.pdf22 Nov 2023
Details of encumbrances concerned to LegalFile: Declaration of Encumbrances concerned to Finance.pdf22 Nov 2023

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
GINI ARIA - PHASE IYAWALEWADI PUNE-41104865CompletedSep 2022Jun 2022
Bellina Phase 3Lohgaon Pune-41104749CompletedSep 2020Aug 2020
BELLINA PHASE 2 - COMMERCIALLohgaon Pune-41104731CompletedSep 2018Feb 2018
Harlalka HeightsSitaram Poddar Marg Kalbadevi36CompletedMay 2017Late, Jun 2017
Gini Viviana Phase 1Survey No 38-1 Balewadi191CompletedMay 2016Late, May 2017
Gini Bellina Phase 1off Porwal Road Lohegaon140CompletedJan 2014Late, Mar 2015

How this compares with Pune

65%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GINI ARIA - PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yevlewadi13,700+ in Pune

2 kmGINI ARIA - PHASE 2Completed 49Lapsed / revoked 27Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: Gini Construction Pvt Ltd

Gini Construction Pvt Ltd has 5 registrations on MahaRERA, including BELLINA PHASE 3 and BELLINA PHASE 2 - COMMERCIAL. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GINI ARIA - PHASE 2 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GINI ARIA - PHASE 2?

The registered promoter entity is Gini Construction Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GINI ARIA - PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GINI ARIA - PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GINI ARIA - PHASE 2?

The professionals named in the filing: Architect: CUBIX Architects Associates; Engineer: Siddharth N Shitole; Chartered Accountant: Patel & Sharma; Chartered Accountant: Agarwal Sarawgi and Associates; Chartered Accountant: Patel and Sharma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GINI ARIA - PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GINI ARIA - PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GINI ARIA - PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.