Gini Construction Pvt Ltd: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Gini Construction Pvt Ltd has 5 registrations in this build, including BELLINA PHASE 3 and BELLINA PHASE 2 - COMMERCIAL. Its filings disclose 6 earlier MahaRERA projects: 3 of 6 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| BELLINA PHASE 3 | Pune, Maharashtra | - | - | Completed |
| BELLINA PHASE 2 - COMMERCIAL | Pune, Maharashtra | - | - | Completed |
| GINI ARIA - PHASE I | Pune, Maharashtra | - | - | Completed |
| GINI ARIA MHADA WING | Pune, Maharashtra | - | - | Completed |
| GINI ARIA - PHASE 2 | Pune, Maharashtra | 65 | 65% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Gini Bellina Phase 1 | 31 Jan 2014 | 1 Mar 2015 | +13 months |
| Gini Viviana Phase 1 | 31 May 2016 | 3 May 2017 | +11 months |
| Harlalka Heights | 15 May 2017 | 6 Jun 2017 | +1 months |
| BELLINA PHASE 2 - COMMERCIAL | 30 Sep 2018 | 16 Feb 2018 | On time |
| Bellina Phase 3 | 30 Sep 2020 | 7 Aug 2020 | On time |
| GINI ARIA - PHASE I | 30 Sep 2022 | 29 Jun 2022 | On time |
Frequently asked questions
How do I verify Gini Construction Pvt Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Gini Construction Pvt Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.