Completed No litigation declared Residential / Group Housing project

Geras Isle Royale Tower 2 and 3

By Gera Developments Private Limited

RG-MH-10628 · RERA P52100009870 · Last updated on MahaRERA portal: 30 Sep 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 24 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
9 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 98%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

Geras Isle Royale Tower 2 and 3 is a Residential / Group Housing project by Gera Developments Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100009870 on 22 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021.

At a glance

Project

  • NameGeras Isle Royale Tower 2 and 3
  • TypeResidential / Group Housing
  • Location
    • Bavdhan
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100009870
  • ReraGenie IDRG-MH-10628

Builder

  • NameGera Developments Private Limited
  • Entity typeCompany
  • Managing DirectorRohit Gera
  • Other registrations24 more →
  • Completed11 of 25
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects10 →

Key dates

this monthRegisteredAug 2017PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings2 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Geras Isle Royale Tower 2NA190000
Geras Isle Royale Tower 3NA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 98%.

Geras Isle Royale Tower 273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Geras Isle Royale Tower 383%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 30 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed210

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots210
Closed/Covered202
Open Space8
BuildingClosed/CoveredOpen SpaceTotal
Geras Isle Royale Tower 21128120
Geras Isle Royale Tower 390090

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,727 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13590.07
Proposed, not sanctioned13,590 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManekji wadia bldg nanek motwani marg fort 400001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGera Developments
EngineerSantosh Tiwatne
Chartered AccountantK Ray & Co
Chartered AccountantKhandelwal Jain & Associates
PartnerRole in project
Gera Developments Private Limited-

Litigation declared12

CaseCourtStatus
761/2004Civil Court PuneOngoing
1656/2009High Court BombayOngoing
1173/2010Civil Court PuneOngoing
493/2010Civil Court PuneOngoing
2027/2012Civil Court PuneOngoing
401/2012Civil Court PuneOngoing
1664/2014Civil Court PuneOngoing
1213/2017Civil Court PuneOngoing
1858/2019Civil Court PuneOngoing
797/2019Civil Court PuneOngoing
1879/2017Civil Court PuneOngoing
317/2011Civil Court PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jun 2021

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_IR Tower 2-3.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Notes to Form 5_IR Tower 2-3.pdf30 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: IR Bavdhan OC of T2 T3.pdf18 Jun 2021
Disclosure of sold/ booked inventoryFile: IR 2-3 inventory.pdf1 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: IR Bavdhan OC of T2 - T3_1.pdf1 Jun 2021
Declaration in FORM BFile: Form B- IR 2-3_Oct-20.pdf23 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Arch CERTIFICATE-TOWER T-2 T-3.pdf23 Nov 2020
Proforma of Allotment letterFile: Post-OC-IR-II III Agreement-Ver 6B- 27-Oct-20.pdf23 Nov 2020
Building plan approvalFile: 1-22.pdf2 Nov 2020
Building plan approvalFile: 14-22.pdf2 Nov 2020
Building plan approvalFile: 15-22.pdf2 Nov 2020
Building plan approvalFile: 16-22.pdf2 Nov 2020
Building plan approvalFile: 17-22.pdf2 Nov 2020
Building plan approvalFile: 18-22.pdf2 Nov 2020
Building plan approvalFile: 19-22.PDF2 Nov 2020
Building Plan Approval (IOD)File: 1-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 14-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 15-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 16-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 17-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 18-22.pdf2 Nov 2020
Building Plan Approval (IOD)File: 19-22.PDF2 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: IR 2-3-2019.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: IR 2 -3-Audit.pdf30 Sep 2020
Details of Restarting of Construction work post lockdownFile: IR 2-3.pdf20 Jun 2020
Certificates of CA (Form 5)File: IR 2-3-2019.pdf30 Sep 2019
Proforma of Allotment letterFile: Gera's IR-2 Application Form -V3.pdf7 Feb 2019
Proforma of Allotment letterFile: Post-OC-IR-II -III Agreement-Ver 6B.pdf7 Feb 2019
Certificates of Architect (Form 4)File: Form4- IR 70 unit completion.pdf7 Feb 2019
OtherFile: OC IR T 2 T 3 -24jan-19.PDF7 Feb 2019
OtherFile: IR EC Expansion 163 tenements.pdf7 Feb 2019
OtherFile: C to E ammendment IR 163 tenements.pdf7 Feb 2019
OtherFile: IR-II- III Agreement-Ver-6A.pdf7 Feb 2019
Certificates of Architect (Form 4)File: T2 T3 - completion certificate.pdf22 Nov 2018
OtherFile: IR OC T 2 -T 3 OCC 0925-18.PDF22 Nov 2018
Details of encumbrancesFile: Encum-IR-2-2.pdf1 Nov 2018
Declaration in FORM BFile: Form B-IR 2-3.pdf1 Nov 2018
Certificates of CA (Form 5)File: GDPL IR 2 -3.pdf30 Sep 2018
Proforma of Allotment letterFile: IR-II- III Agreement-Ver5.pdf9 Aug 2018
Proforma of Allotment letterFile: IR-2-3AgreementVer4.pdf23 May 2018
Proforma of Allotment letterFile: IR-II-III Agreement-Ver3.pdf2 May 2018
Proforma of Allotment letterFile: Gera's IR-2 Application Form Ver 2.pdf8 Sep 2017
Proforma of Allotment letterFile: Gera's IR-3 Application Form ver 2.pdf8 Sep 2017
Building plan approvalFile: (15-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building plan approvalFile: (16-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building plan approvalFile: (17-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building plan approvalFile: (18-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building plan approvalFile: (19-19 ) CC No 2978-16 dated 23Dec2016( Basement Parking Plans).PDF29 Jul 2017
Building plan approvalFile: (1-19 ) CC No 2978-16 dated 23Dec2016 (Building Lay Out).pdf29 Jul 2017
Building plan approvalFile: (14-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Layout approvalFile: ( 3-3 ) Amalgamation commencement certificate no 3379-15 dated 31Dec2015.pdf29 Jul 2017
PAN CardFile: GDPL PAN.pdf29 Jul 2017
Copy of the legal title reportFile: Title Opinion 24-7-17- Isle Royalecompressed.pdf29 Jul 2017
Details of encumbrancesFile: Details of encumbrances.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: ( 3-3 ) Amalgamation commencement certificate no 3379-15 dated 31Dec2015.pdf29 Jul 2017
Building Plan Approval (IOD)File: (1-19 ) CC No 2978-16 dated 23Dec2016 (Building Lay Out).pdf29 Jul 2017
Building Plan Approval (IOD)File: (14-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building Plan Approval (IOD)File: (15-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building Plan Approval (IOD)File: (16-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building Plan Approval (IOD)File: (17-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building Plan Approval (IOD)File: (18-19 ) CC No 2978-16 dated 23Dec2016.pdf29 Jul 2017
Building Plan Approval (IOD)File: (19-19 ) CC No 2978-16 dated 23Dec2016( Basement Parking Plans).PDF29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate number CC-2978-16 Dated 23Dec2016.PDF29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate -NoCC-4449-15 dated 31Dec2016.PDF29 Jul 2017
Declaration in FORM BFile: Form B IR 2-3compress.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch-IR2-3.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-Certificate IR-T2and3.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: IR 2 3Agreement 29072017.pdf29 Jul 2017
Proforma of Allotment letterFile: IR 2 3Combined Application form 29072017.pdf29 Jul 2017

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Geras Imperium GreenChalta No 13 Part of PT Sheet No 73 Plot No A X Neogi nagar Rua de Ourem Road Panji Goa61CompletedApr 2019May 2015
Geras Greenville Song of Joy A1 A2Survey No 64 Hissa No 1 to 6120CompletedApr 2017Oct 2016
A1 A2 Song of Joy Geras GreenvilleS No 64 Hissa No 1to 6 Kharadi Pune 14120CompletedApr 2017Oct 2016
Geras Greensville Trinity TowersSurvey No 64 Hissa No 1 to 6 Kharadi Pune 411 014248CompletedNov 2015Oct 2015
Geras Regent TowerSurvey No 33 Hissa No 2 2 Village Baner Pune9CompletedNov 2014Sep 2014
Geras Parkview ISurvey No 73 Hissa No 1 Kharadi Pune 411014227CompletedApr 2014Late, Mar 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Geras Isle Royale Tower 2 and 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavdhan13,700+ in Pune

2 kmGeras Isle Royale Tower Completed 68Lapsed / revoked 40Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 171 registered projects within 2 km.

Builder: Gera Developments Private Limited

Gera Developments Private Limited has 25 registrations on MahaRERA, including A3, Song of Joy, Geras Greensville2 and Geras Misty Waters. Its filings disclose 10 earlier MahaRERA projects: declares 8 of 10 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Geras Isle Royale Tower 2 and 3 is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Geras Isle Royale Tower 2 and 3?

The registered promoter entity is Gera Developments Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Geras Isle Royale Tower 2 and 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Geras Isle Royale Tower 2 and 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Geras Isle Royale Tower 2 and 3?

The professionals named in the filing: Architect: Gera Developments; Engineer: Santosh Tiwatne; Chartered Accountant: K Ray & Co; Chartered Accountant: Khandelwal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Geras Isle Royale Tower 2 and 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Geras Isle Royale Tower 2 and 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Geras Isle Royale Tower 2 and 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.