ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GARDENIA CREST

Completed No litigation declared Residential / Group Housing project

GARDENIA CREST

By RUJUTA SHELTERS

RG-MH-09116 · RERA P52100001527 · Last updated on MahaRERA portal: 4 Jun 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 70 months
  • 6 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 157 documents Report an error

GARDENIA CREST is a Residential / Group Housing project by RUJUTA SHELTERS in Pune, Maharashtra, registered with MahaRERA as P52100001527 on 28 Jul 2017. The registration is recorded completed; possession was promised by 16 Apr 2025. The completion date has moved by 70 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGARDENIA CREST
  • TypeResidential / Group Housing
  • Location
    • sus
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001527
  • ReraGenie IDRG-MH-09116

Builder

  • NameRUJUTA SHELTERS
  • Entity typeOthers
  • PartnersMILIND MOHAN TALATHI, KUSH LANDMARK LLP THROUGH SUNIL JUGALKRISHOR BAHETI
  • Named personsKUSH LANDMARK LLP, BHIKAMCHAND RATHI, SUDHIR AGARWAL, MILIND MOHAN TALATHI, RAKESH KUMAR AGARWAL, NILESH MURLIDHAR BIHANI, SANJAY BAHETI

Key dates

this monthRegisteredJul 2017First promiseJun 2019Revised toApr 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Jul 2017
  • Promised completion16 Apr 2025
  • Revised completionRevised to 16 Apr 2025 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed157 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GARDENIA CRESTNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

GARDENIA CREST: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,850 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5206.91
Proposed, not sanctioned4,379 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCAMP, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAKASH KULKARNI ANKUR ASSOCIATES
EngineerG A BHILARE CONSULTANTS PVT LTD
Chartered AccountantSUNIL P SHAH
PartnerRole in project
RUJUTA SHELTERS-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002034Jun 2019 → Jun 2020

Reason as filed by the promoterADDITIONAL FSI IS STILL AWAITED TO CONSTRUCT THE FURTHER PROJECT AND COMPLETE THE AME.

EXT52100011762Jun 2019 → Dec 2022

Reason as filed by the promoterNon availbility of raw material and labor due to covid 19 pandemic

EXT52100008943Jun 2019 → Jun 2021

Reason as filed by the promoterNon availability of labours and construction material because of the pandemic of Covid-19.

EXT52100015345Jun 2019 → Dec 2023

Reason as filed by the promoterNON AVAILBILITY OF RAW MATERIAL AND LABOUR DUE TO COVID 19 PANDEMIC

EXT52100019202Jun 2019 → Dec 2024

Reason as filed by the promoterFINISHING WORK OF THE PROJECT IS REMAINING.

EXT52100028285Jun 2019 → Apr 2025

Reason as filed by the promoterThe project work is 100% completed. We have received Full Occupancy Certificate dated 16/04/2025. We want to apply for extension ispo facto till the date of Occupancy Certificate.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000085432Shriram Pandharinath ChaudhariM/S Rujuta Shelters Through its partner Milind M TalathIit20/04/2021
CC005000000106481Ravindra UdgiriMilind Talathi12/01/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Apr 2025

Documents filed157

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 157 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Gardenia Crest - OC.pdf4 Jun 2025
Occupational CertificateFile: Gardenia Crest - OC Verification.pdf4 Jun 2025
Declaration in FORM BFile: FORM B.pdf25 Apr 2025
Certificates of CA (Form 3)File: Form 3 31-03-2025.pdf25 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2025.pdf25 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Gardenia Crest Completion 2025-04-16 15-13.pdf18 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -31-03-2025.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory-31-03-2025.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 FY -2023-2024.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: disclosure of Sold Unsold Inventory.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory 31 03 2018.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory 31 03 2019.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory 31 03 2020.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory 30 09 2022.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Book Inventory 31 12 2022.pdf14 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1 31-12-2024 gardenia crest.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3 31-12-2024 gardenia crest.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-12-2024 gardenia crest.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Book Inventory 31-12-2024 gardenia crest.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf15 Oct 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf15 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Discloure Sold Unsold Inventory.pdf15 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1 Q-01 24-25.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form- 2 Q-01 24-25.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form- 2A Q-01 24-25.pdf5 Jul 2024
Disclosure of sold/ booked inventoryFile: Updated Sold - Unsold Inventory Q-01 24-25.pdf5 Jul 2024
Certificates of CA (Form 3)File: Form-3 Q-01 24-25.pdf5 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form-01 Q-04 23-24.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form-02 Q-04 23-24.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3 Form-02A Q-4 23-24.pdf20 Apr 2024
Certificates of CA (Form 3)File: 4 Form-03 Q-04 23-24.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-05 FY 2022-23.pdf18 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form -05 FY 2017-18.pdf8 Apr 2024
Certificates of CA (Form 3)File: Rera Form 3 March 2018 2024-03-24 14-06_compressed.pdf26 Mar 2024
Certificates of CA (Form 3)File: RERA Form 3 Dec 2017 2024-03-24 14-03_compressed.pdf26 Mar 2024
Certificates of CA (Form 3)File: Rera March 2019 2024-03-24 14-08.pdf25 Mar 2024
Certificates of CA (Form 3)File: Rera March 2020 2024-03-24 14-11.pdf25 Mar 2024
Certificates of CA (Form 3)File: Rera Sept 2022 2024-03-24 14-12.pdf25 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 31st December 2017.pdf19 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 31st Decemeber 2018.pdf19 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8 30th September 2022.pdf19 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 23 th December-2022 FORM 1.pdf18 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Form 2 31 St December-2017.pdf18 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 30 September-2022.pdf18 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 31 St Decemeber-2022.pdf18 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 Form 2A 31 March-2018.pdf18 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5 Form 2A 31st March 2022.pdf18 Mar 2024
Certificates of CA (Form 3)File: 5 Form 3 31st December-2022.pdf18 Mar 2024
Certificates of CA (Form 3)File: 6 Form 3 30 June -2023.pdf18 Mar 2024
Certificates of CA (Form 3)File: 7 Form 3 31st December-2023.pdf18 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form -1.pdf25 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM- 2.pdf25 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Form -2A.pdf25 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf26 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory (2).pdf26 Oct 2023
Certificates of CA (Form 3)File: FORM-3 (2).pdf26 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1.pdf24 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf24 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf10 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 30-06-2023.pdf11 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30-06-2023.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 30-06-2023.pdf11 Jul 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 30-06-2023.pdf11 Jul 2023
Layout approvalFile: HPSC5597_Layout.pdf27 Apr 2023
Building plan approvalFile: HPSC5598_compressed.pdf27 Apr 2023
Building plan approvalFile: HPSC5599_compressed.pdf27 Apr 2023
Building plan approvalFile: HPSC5600_compressed.pdf27 Apr 2023
Building plan approvalFile: HPSC5601_compressed.pdf27 Apr 2023
Building plan approvalFile: HPSC5602_compressed.pdf27 Apr 2023
Copy of Layout Approval (in case of layout)File: HPSC5597_Layout.pdf27 Apr 2023
Building Plan Approval (IOD)File: HPSC5598_compressed.pdf27 Apr 2023
Building Plan Approval (IOD)File: HPSC5599_compressed.pdf27 Apr 2023
Building Plan Approval (IOD)File: HPSC5600_compressed.pdf27 Apr 2023
Building Plan Approval (IOD)File: HPSC5601_compressed.pdf27 Apr 2023
Building Plan Approval (IOD)File: HPSC5602_compressed.pdf27 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter dated 02092022_compressed.pdf27 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf13 Apr 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 70 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GARDENIA CREST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near sus13,700+ in Pune

2 kmGARDENIA CRESTCompleted 28Lapsed / revoked 17Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: RUJUTA SHELTERS

RUJUTA SHELTERS has 1 registration on MahaRERA, including GARDENIA CREST. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GARDENIA CREST is delayed beyond 16 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GARDENIA CREST?

The registered promoter entity is RUJUTA SHELTERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GARDENIA CREST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GARDENIA CREST?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GARDENIA CREST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GARDENIA CREST?

The professionals named in the filing: Architect: PRAKASH KULKARNI ANKUR ASSOCIATES; Engineer: G A BHILARE CONSULTANTS PVT LTD; Chartered Accountant: SUNIL P SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GARDENIA CREST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GARDENIA CREST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GARDENIA CREST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.