Home / Browse projects / Pune, Maharashtra / GANGA AVANTA A1

Registered No litigation declared Others project

GANGA AVANTA A1

By SOHAM ASSOCIATES

RG-MH-22659 · RERA P52100047366 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken
  • Rs 125.00 crore secured on the land, in favour of PIRAMAL FINANCE LIMITED
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
51 of 151Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 137 documents Report an error

GANGA AVANTA A1 is a Others project by SOHAM ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100047366 on 27 Oct 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 100 of the 151 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameGANGA AVANTA A1
  • TypeOthers
  • Location
    • MUNDHWA S NO 47
    • MUNDHWA
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047366
  • ReraGenie IDRG-MH-22659

Builder

  • NameSOHAM ASSOCIATES
  • Entity typePartnership
  • GSTIN27ACLFS9011Q1ZD
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersSUBHASH SITARAM GOEL, SWARANSINGH GYANSINGH SOHAL, SARANJEETSINGH PUNJABSINGH BAGGA, ALPHA HOMES SPACES LLP Through Anurag S Goel
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2022First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Oct 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed137 files

Current status

66%100 of 151 units booked
57.9%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA29251447151

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

A1: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed605

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots605
Closed/Covered605

Land and ownership8

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,151 sq m
Land owned byNot the promoter
Named landowners8
Encumbrance on the landDeclared present
Charge in favour ofPIRAMAL FINANCE LIMITED
Secured amountRs 125.00 crore
CERSAI search filedYes
Declared on30 Apr 2026
LandownerVillageDistrict
RATAN INDRAKUMAR KACHIPune (M Corp.)Pune
MILIND INDRAKUMAR KACHIPune (M Corp.)Pune
PRITI HEMANT KACHIPune (M Corp.)Pune
SHRUTI HEMANT KACHIPune (M Corp.)Pune
SALONI HEMANT KACHIPune (M Corp.)Pune
ATHARVA HEMANT KACHIPune (M Corp.)Pune
SACHIN INDRAKUMAR KACHIPune (M Corp.)Pune
AMAR INDRAKUMAR KACHIPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune municipal corporation
Permissible FSI23104.47
Proposed, not sanctioned23,104 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Survey No. 46/6, Caprivilla, B T Kawade Road, Ghorpadi, Pune.411001
Estimated costRs 72.60 cr
Cost incurredRs 42.05 cr
Work done57.92%
BuildingWingEstimatedIncurred
A1NARs 58.08 crRs 33.64 cr
-NARs 14.52 crRs 8.41 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAMOD DESHPANDE
ArchitectCreative Designs
EngineerSANJAY KUMAR YADAV
EngineerChandrashekar Tendulkar
EngineerKiran Bardiya
EngineerSANDIP SHIVARKAR
Chartered AccountantCA MAHESH CHANDORKAR
Chartered AccountantAtul Hattarage
PartnerRole in project
SOHAM ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017541Dec 2025 → Dec 2027

Reason as filed by the promoterWe want to extend the project registration as the Revised Sanction from the competent authority was delayed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed137

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA A1 JUN 26.pdf4 Jul 2026
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA A1 JUN 26.pdf4 Jul 2026
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA A1 JUN 26.pdf4 Jul 2026
Layout approvalFile: Plot Marking-1.pdf12 Jun 2026
Layout approvalFile: SANCTION PLAN 1.pdf22 May 2026
Layout approvalFile: SANCTION PLAN 2.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 3.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 4.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 5.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 6.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 7.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 8.pdf22 May 2026
Building plan approvalFile: SANCTION PLAN 9.pdf22 May 2026
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA MAR 26.pdf30 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA A1 MAR 26.pdf30 Apr 2026
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA A1 MAR 26.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA A1 MAR 26.pdf6 Apr 2026
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA A1 MAR 26.pdf6 Apr 2026
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA A1 DEC 25.pdf12 Jan 2026
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA DEC 25.pdf12 Jan 2026
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA DEC 25.pdf12 Jan 2026
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Withdrawal Update Form 1File: FORM 1 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Withdrawal Update Form 2File: FORM 2 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Withdrawal Update Form 3File: FORM 3 GANGA AVANTA A1 SEP 25.pdf10 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 GANGA AVANTA AI 2024-25.pdf30 Sep 2025
Withdrawal Update Form 1File: Form 1 Ganga Avanta A1 June 2025.pdf25 Sep 2025
Withdrawal Update Form 2File: Form 2 Ganga Avanta A1 June 2025.pdf25 Sep 2025
Withdrawal Update Form 3File: Form 3 Ganga Avanta A1 June 2025.pdf25 Sep 2025
Withdrawal Update Form 1File: Form 1 Ganga Avanta A1 June 2025.pdf17 Sep 2025
Withdrawal Update Form 2File: Form 2 Ganga Avanta A1 June 2025.pdf17 Sep 2025
Withdrawal Update Form 3File: Form 3 Ganga Avanta A1 June 2025.pdf17 Sep 2025
Form 2A (FY 2023-2024)File: FORM 2A Ganga Avanta A1 2023-2024.pdf17 Sep 2025
Form 2A (FY 2024-2025)File: FORM 2A GANGA AVANTA 2024-25.pdf17 Sep 2025
Form 5 (FY 2023-2024)File: Form 5 Ganga Avanta A1 2023 to 24.pdf16 Sep 2025
Form 5 (FY 2022-2023)File: Form 5 Ganga Avanta 2022 to 23.pdf16 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 March 2023.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 March 2023.pdf13 Sep 2025
Form 3File: FORM 3 Ganga Avanta A1 March 2023.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 March 2023.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 June 2023.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 June 2023.pdf13 Sep 2025
Form 3File: FORM 3 Ganga Avanta A1 June 2023.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 June 2023.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 September 2023.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 September 2023.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 September 2023.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 September 2023.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 December 2023.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 December 2023.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 December 2023 (2).pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 December 2023.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 March 2024.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 March 2024.pdf13 Sep 2025
Form 3File: Form 3Ganga Avanta A1 March 2024.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 March 2024.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 June 2024.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 June 2024 (1).pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 June 2024.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 June 2024.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 September 2024.pdf13 Sep 2025
Form 2File: Form 2 Gang Avanta A1 Sept 2024.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 September 2024.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 September 2024.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 December 2024.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 Dec 2024.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 December 2024.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Avanta A1 December 2024.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 March 2025.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 March 2025.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 March 2025.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 March 2025.pdf13 Sep 2025
Form 1File: Form 1 Ganga Avanta A1 June 2025.pdf13 Sep 2025
Form 2File: Form 2 Ganga Avanta A1 June 2025.pdf13 Sep 2025
Form 3File: Form 3 Ganga Avanta A1 June 2025.pdf13 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ganga Avanta A1 June 2025.pdf13 Sep 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ganga Avanta A1 Dec 2022.pdf20 May 2025

How this compares with Pune

66%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGA AVANTA A1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUNDHWA13,700+ in Pune

2 kmGANGA AVANTA A1Completed 68Lapsed / revoked 25Other 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 203 registered projects within 2 km.

Builder: SOHAM ASSOCIATES

SOHAM ASSOCIATES has 5 registrations on MahaRERA, including VASANT VIHAR and Rajhans Ville. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANGA AVANTA A1 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGA AVANTA A1?

The registered promoter entity is SOHAM ASSOCIATES, a partnership as per the filing. Its GSTIN 27ACLFS9011Q1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGA AVANTA A1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANGA AVANTA A1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGA AVANTA A1?

The professionals named in the filing: Architect: PRAMOD DESHPANDE; Architect: Creative Designs; Engineer: SANJAY KUMAR YADAV; Engineer: Chandrashekar Tendulkar; Engineer: Kiran Bardiya; Engineer: SANDIP SHIVARKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGA AVANTA A1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGA AVANTA A1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGA AVANTA A1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.