Home / Browse projects / Thane, Maharashtra / GALAXY WING 5

Registration lapsed No litigation declared Residential / Group Housing project

GALAXY WING 5

By BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED

RG-MH-25928 · RERA P51700009788 · Last updated on MahaRERA portal: 30 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 72 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
21 of 77Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

GALAXY WING 5 is a Residential / Group Housing project by BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700009788 on 22 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 56 of the 77 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameGALAXY WING 5
  • TypeResidential / Group Housing
  • Location
    • Kalyan Shil Road
    • Padale Village
    • Thane (M Corp.)
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700009788
  • ReraGenie IDRG-MH-25928

Builder

  • NameBRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorsAMARSINGH NARAYANSINGH THAKUR, SOHANSINGH AMARSINGH THAKUR, SHAKTI BHAGWANSINGH KUSHWA, DHAJI VELJI BAUVA, PREMJI LAKHAMSHI KARIA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed100 files

Current status

73%56 of 77 units booked
96.7%Work done, per cost certificate

Figures as on 30 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GALAXY WING 5NA222077077

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

GALAXY WING 5: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 30 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered24
Open Space27

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,383 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Nov 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation, Thane
Permissible FSI3638.44
Proposed, not sanctioned2,924 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMADHUMALTI, VEER SAVARKAR PATH, THANE WEST 400 601
Estimated costRs 17.34 cr
Cost incurredRs 16.77 cr
Work done96.73%
BuildingWingEstimatedIncurred
GALAXY WING 5NARs 15.82 crRs 15.28 cr
-NARs 1.52 crRs 1.49 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAAKAAR ARCHITECTS
EngineerRajan Chandrakant Tipnis
Chartered AccountantMAYANK KUMAR JAIN
Chartered AccountantVIPUL JAIN
PartnerRole in project
BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700005078Dec 2019 → Dec 2020

Reason as filed by the promoterPaucity of funds on account of lack of sales of unsold inventory owned by Company and delay in receipt of outstanding payments due and payable by purchasers towards at the time of handover of their alloted units in building no.1 & 2. Since July 2017, the Company has witnessed lack luster sales which has burdened the Company financial position. The said sub sequence of events had the Company in turbulent financial situation and on the verge of Bankruptcy. Nonetheless the Company in tireless working of the option to shore up funds to aid the completion of building no.5 , a fact established beyon

EXT51700010126Dec 2019 → Jun 2023

Reason as filed by the promoterWe sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. 3. Customers are also facing financial problems There are huge receivable from the customers but we are unable to receive the same, which in turn has affected our financial position as well. Customers and we both are highly affected in last 1 and half year. 4. Even there is a long delay from L

EXT51700017529Dec 2019 → Jun 2024

Reason as filed by the promoterThe project got delayed due to delay in collection of Sales receivable and delay in sales of unsold units. Due to this financial issues, vendor and supplier payments got delayed. Due to non-receipt of timely payments suppliers/vendors have also not completed the activities on time. Therefore, project could not be completed as planned. We have obtained consent from allottees for project extension. Requesting you to grant the extension. Thanking you

EXT51700025106Dec 2019 → Jun 2025

Reason as filed by the promoterWe are facing hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on 24.

EA30112518472Dec 2019 → Dec 2025

Reason as filed by the promoterWe had faced hindrance for construction work of Building 5 of project galaxy, due to various issues raised by landlords and legal proceedings in court of law from first notice served by their Advocate Mr. Nitin Mhatre on 28.11.2022. They instituted a Special Civil Suit against us in the month of August 2023 in the court of 3rd Joint Civil judge Senior Division Thane. Further They served Notice of demand for Rs. 15000000/- we moved to Mumbai High Court for appointment of arbitrator under section 9 and section 17. The Honorable High Court has passed an order for appointment of Arbitrator on 24.0

Litigation declared1

CaseCourtStatus
RCA123/2016Thane Civil CourtAwaiting Summons

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000055911Rajendra Eknath PawarBright Sky Height Builder& Developer Private Limited23/08/2018
CC006000000193160Rajan G. RedkarMr. Sohansingh Amansing Thakur and Mr. Santosh B. Kushwah23/07/2020
CC006000000195959Mohini Milind KaleBright Sky Heights Builder and Developers Private Limited09/02/2021
CC12500065Mini Shivkumar PillaiBRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED07/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form No 1 Dtd 30062025.pdf30 Nov 2025
Withdrawal Update Form 2File: Form No 2 Dtd 30062025.pdf30 Nov 2025
Withdrawal Update Form 3File: Form No 3 Dtd 30062025.pdf30 Nov 2025
Disclosure of sold/ booked inventoryFile: RERA SOLD UNSOLD.pdf15 Mar 2025
Declaration in FORM BFile: FORM B UPDATED.pdf10 Mar 2025
Layout approvalFile: Layout 1.pdf14 Feb 2025
Layout approvalFile: Layout 2.pdf14 Feb 2025
Layout approvalFile: Layout 2.pdf14 Feb 2025
Building plan approvalFile: Bldg plan 1.pdf14 Feb 2025
Building plan approvalFile: Bldg plan 2.pdf14 Feb 2025
Building plan approvalFile: Bldg plan 3.pdf14 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout 2.pdf14 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout 2.pdf14 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout 1.pdf14 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf14 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Dec 24.pdf14 Feb 2025
Certificates of CA (Form 3)File: Signed Form 3 _ Sep 24.pdf14 Feb 2025
Certificates of CA (Form 3)File: Signed Form 3 _ Dec 24.pdf14 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf14 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Dec 24.pdf14 Feb 2025
Building Plan Approval (IOD)File: Bldg plan 1.pdf14 Feb 2025
Building Plan Approval (IOD)File: Bldg plan 3.pdf14 Feb 2025
Building Plan Approval (IOD)File: Bldg plan 2.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Sep.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Signed Form 3 _ Dec 24.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Sep.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec.pdf14 Feb 2025
CERSAI detailsFile: CERSAI.pdf14 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Declaration.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2a.pdf14 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2324.pdf14 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Nov 2024
Declaration in FORM BFile: Form B.pdf19 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf19 Nov 2024
Declaration in FORM BFile: Form B.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf19 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf19 Nov 2024
Declaration in FORM BFile: FORM B UPDATED.pdf1 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cert, Jan -Mar'23.pdf1 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cert, April-June'23.pdf1 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE FORM 2.pdf1 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 APR TO JUN.pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A Certficate.pdf1 Dec 2023
Certificates of CA (Form 3)File: Form - 3.pdf1 Dec 2023
Certificates of CA (Form 3)File: Form - 3 APR TO JUN.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form -5.pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: sold unsold details.pdf6 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31122021.pdf15 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30062021.pdf15 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30092021.pdf15 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31122021.pdf15 Jan 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Details 30-06-21.pdf15 Jan 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Details 30-09-21.pdf15 Jan 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Details 31-12-2021.pdf15 Jan 2022
CERSAI detailsFile: CERSAI Declaration.pdf15 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 of Bright March 2018.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 of Bright March 2019.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 of Bright March 2020.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 of Bright March 2021.pdf7 Jan 2022
Layout approvalFile: LAYOUT PLAN.pdf5 Jan 2022
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf5 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MAR 18 COMPRESSED.pdf5 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MAR 19 COMPRESSED.pdf5 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MAR 20 COMPRESSED.pdf5 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MAR 21 COMPRESSED.pdf5 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 JUN 21 COMPRESSED.pdf5 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 18.pdf5 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 19.pdf5 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 20.pdf5 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MAR 21.pdf5 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUN 21.pdf5 Jan 2022
Certificates of CA (Form 3)File: FORM 3_MARCH 18_compressed.pdf5 Jan 2022
Certificates of CA (Form 3)File: FORM 3_MAR 19_compressed.pdf5 Jan 2022

How this compares with Thane

73%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 72 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GALAXY WING 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Padale Village7,600+ in Thane

2 kmGALAXY WING 5Completed 14Lapsed / revoked 4Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED

BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED has 2 registrations on MahaRERA, including GALAXY BLDG 1 AND 2 and GALAXY WING 5. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that GALAXY WING 5 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GALAXY WING 5 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GALAXY WING 5?

The registered promoter entity is BRIGHT SKY HEIGHTS BUILDERS AND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GALAXY WING 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GALAXY WING 5?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GALAXY WING 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GALAXY WING 5?

The professionals named in the filing: Architect: SAAKAAR ARCHITECTS; Engineer: Rajan Chandrakant Tipnis; Chartered Accountant: MAYANK KUMAR JAIN; Chartered Accountant: VIPUL JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GALAXY WING 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GALAXY WING 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GALAXY WING 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.