GALAXY APARTMENTS CDF WINGS

By HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD

RG-MH-10822 · RERA P51800010758 · Last updated on MahaRERA portal: 11 Apr 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 69 months past the filed date
  • 19 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2021Possession promised69 months past this date
14 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 75%
19Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

GALAXY APARTMENTS CDF WINGS is a Others project by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010758 on 31 Aug 2017. Possession was promised by 31 Jan 2021 and is now 69 months past that date. 19 complaints are on record with the regulator.

At a glance

Project

  • NameGALAXY APARTMENTS CDF WINGS
  • TypeOthers
  • Location
    • Near Bunder Bhavan
    • Kurla East
    • Kurla
    • Mumbai Suburban
    • 400070
  • Pincode400070
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010758
  • ReraGenie IDRG-MH-10822

Builder

  • NameHOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
  • Entity typeCompany
  • Managing DirectorSARANG WADHAWAN
  • Other registrations13 more →
  • No longer live14 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

69 months past promisethis monthRegisteredAug 2017PromisedJan 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 Jan 2021
  • Revised completionNone
  • Buildings3 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING CNA210000
WING - DNA210000
WING - FNA210000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 75%.

WING C68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING - D54%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING - F27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed93

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots93
Closed/Covered93
BuildingClosed/CoveredTotal
WING C2323
WING - D3939
WING - F3131

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,014 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI18955.42
Proposed, not sanctioned18,955 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANDRA WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIndrajeet S. Deshmukh
EngineerH M RAJE STRUCTURAL CONSULTANTS PVT LTD
PartnerRole in project
HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD-

Complaints filed with MahaRERA19

Case no.ComplainantRespondentFiled
CC006000000001292Moushumi Rohan GalaMahindra Happinest Developers Ltd07/04/2024
CC006000000001570Melbourne B. TrinidadeHousing Development And Infrastructure Ltd07/07/2018
CC006000000078891Leeladevi HundiaHousing Development And Infrastructure Ltd.22/04/2019
CC006000000089910Galaxy Apartment C Wing Purchasers AssociationHousing Development Infrastructure Limited05/08/2019
CC006000000054859Manjhusha ChauguleHousing Development and Infrastructure Ltd.01/09/2018
CC006000000054862Sayed Akhlaque AhmedHousing Development and Infrastructure Ltd.01/09/2018
CC006000000054863Deepak Shankar KamatHousing Development and Infrastructure Ltd.01/09/2018
CC006000000054865Dawood Abdullah ShahHousing Development and Infrastructure Ltd01/09/2018
CC006000000054988Agnel Antonio Marian PereiraM/s. Housing Development and Infrastructure Ltd.06/09/2018
CC006000000056977Suresh WaghmareHousing Development and Infrastructure Limited19/11/2018
CC006000000057998Satish Suresh AdsulHDIL08/02/2019
CC006000000089749HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDShaila Alwin Raja19/06/2019
CC006000000089750HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDSHAILA ALWIN RAJA19/06/2019
CC006000000089752HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMrs Shaila Alwin Raja19/06/2019
CC006000000089753HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMrs Shaila Alwin Raja19/06/2019
CC006000000089755HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMrs. Shaila Alwin Raja19/06/2019
CC006000000089756HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMrs Shaila Alwin Raja19/06/2019
CC006000000089757HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMRS SHAILA ALWIN RAJA19/06/2019
CC006000000089758HOUSING DEVELOPMENT AND INFRASTRUCTURE LTDMRS SHAILA ALWIN RAJA19/06/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Galaxy, CDF Wings - Form 5.pdf11 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Galaxy.pdf13 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Sale Building C C.pdf27 Nov 2017
Layout approvalFile: 22 Wing F Terrace.pdf29 Jul 2017
Layout approvalFile: 06 2nd Basement.pdf29 Jul 2017
Layout approvalFile: 05 1st Basement.pdf29 Jul 2017
Layout approvalFile: 12 Wing C Typical.pdf29 Jul 2017
Layout approvalFile: 13 Wing C Terrace.pdf29 Jul 2017
Layout approvalFile: 14 Terrace Section.pdf29 Jul 2017
Layout approvalFile: 07 Basemen Floor.pdf29 Jul 2017
Layout approvalFile: 17 Wing D Refuge.pdf29 Jul 2017
Layout approvalFile: 15 Wing D Typical.pdf29 Jul 2017
Layout approvalFile: 16 Wing-D Refuge.pdf29 Jul 2017
Layout approvalFile: 18 Wing D Section.pdf29 Jul 2017
Layout approvalFile: 21 WinG F Typical.pdf29 Jul 2017
Layout approvalFile: 03 Ground Floor.pdf29 Jul 2017
Layout approvalFile: 04 Ground Floor.pdf29 Jul 2017
Layout approvalFile: 01 Layout Block Plan.pdf29 Jul 2017
Layout approvalFile: 02 Plot area CAL.pdf29 Jul 2017
Details of encumbrancesFile: Charge on Project Galaxy.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 01 Layout Block Plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 02 Plot area CAL.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 03 Ground Floor.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 04 Ground Floor.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 05 1st Basement.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 06 2nd Basement.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 07 Basemen Floor.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 12 Wing C Typical.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 13 Wing C Terrace.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 14 Terrace Section.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 15 Wing D Typical.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 16 Wing-D Refuge.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 17 Wing D Refuge.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 18 Wing D Section.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 21 WinG F Typical.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 22 Wing F Terrace.pdf29 Jul 2017
Declaration in FORM BFile: Form B - Galaxy CDF 27072017.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Galaxy Architect Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certifi_Galaxy_CDF.pdf29 Jul 2017
Building plan approvalFile: 00 IOA.pdf28 Jul 2017
PAN CardFile: PANCARD.pdf28 Jul 2017
Copy of the legal title reportFile: TCGalaxy _1-20_Part-1.pdf28 Jul 2017
Copy of the legal title reportFile: TCGalaxy_21-35_Part-2.pdf28 Jul 2017
Copy of the legal title reportFile: TCGalaxy36-49_Part-3.pdf28 Jul 2017
Building Plan Approval (IOD)File: 00 IOA.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate (Galaxy Apartments).pdf28 Jul 2017
Proforma of Allotment letterFile: AL_AFS_Galaxy.pdf28 Jul 2017

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered late
ProjectLocationFlatsStatusPromisedDelivered
HDIL INDUSTRIAL PARKBESIDES LAXMI MARBLES CHANDANSAR ROAD VILLAGE CHANDANSAR VIRAR EAST627CompletedApr 2017Late, Jul 2017
PREMIER EXOTICA IIPREMIER AUTO KIROL ROAD KURLA WEST MUMBAI 40007083CompletedJun 2013Late, Jun 2017
HARMONYNEW LINK ROAD GOREGAON WEST MUMBAI 400104221CompletedJun 2013Late, Jul 2017
PREMIER RESIDENCESPREMIER AUTO KURLA WEST MUMBAI - 4000701,087CompletedDec 2012Late, Mar 2017
GALAXY APARTMENTS WING ABEBHANDARY ESTATE KURLA EAST MUMBAI 400024314CompletedDec 2011Late, Jun 2017
HDIL RESIDENCY PARKOPP YAZOO PARK NARANGI BYPASS ROAD VILLAGE DONGRE VIRAR WEST1,199CompletedAug 2011Late, Oct 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GALAXY APARTMENTS CDF WINGS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla East6,700+ in Mumbai Suburban

2 kmGALAXY APARTMENTS CDF WICompleted 96Lapsed / revoked 74Other 123Dot size: filed unitsN

Filed coordinates, straight-line distance. 293 registered projects within 2 km.

Builder: HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD

HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD has 14 registrations on MahaRERA, including THE NEST and PREMIER EXOTICA I. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that GALAXY APARTMENTS CDF WINGS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GALAXY APARTMENTS CDF WINGS is delayed beyond 31 Jan 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GALAXY APARTMENTS CDF WINGS?

The registered promoter entity is HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GALAXY APARTMENTS CDF WINGS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GALAXY APARTMENTS CDF WINGS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GALAXY APARTMENTS CDF WINGS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GALAXY APARTMENTS CDF WINGS?

The professionals named in the filing: Architect: Indrajeet S. Deshmukh; Engineer: H M RAJE STRUCTURAL CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GALAXY APARTMENTS CDF WINGS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GALAXY APARTMENTS CDF WINGS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GALAXY APARTMENTS CDF WINGS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.