Home / Browse projects / Pune, Maharashtra / Gagan Ela

Completed Litigation declared Others project

Gagan Ela

By Gagan Landmarks LLP

RG-MH-11124 · RERA P52100002439 · Last updated on MahaRERA portal: 2 Dec 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 5 complaints at MahaRERA
  • Completion date moved by 54 months
  • 4 extensions taken
  • Rs 6.00 crore secured on the land, in favour of Abhiyan Marchantts Pvt Ltd

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
20 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 98%
50 of 251Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 219 documents Report an error

Gagan Ela is a Others project by Gagan Landmarks LLP in Pune, Maharashtra, registered with MahaRERA as P52100002439 on 1 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 54 months from the original filing. 201 of the 251 units on this registration are recorded sold or booked, and 20 of 33 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameGagan Ela
  • TypeOthers
  • Location
    • NIBM Road
    • Mohammadwadi
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002439
  • ReraGenie IDRG-MH-11124

Builder

  • NameGagan Landmarks LLP
  • Entity typePartnership
  • PartnerRohit Sureshchand Garg
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2020)
  • Buildings3 building records
  • Documents filed219 files

Current status

80%201 of 251 units booked

Figures as on 2 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA20161280128
BNA201664064
Commercial and MHADANA105243559

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 2 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.

A76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises63%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.18%
B71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises34%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.42%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
Commercial and MHADA82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 2 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes85%
Landscaping & Tree PlantingYes5%
Street LightingYes0%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes5%
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed296

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots296
Closed/Covered296
BuildingClosed/CoveredTotal
A128128
B128128
Commercial and MHADA4040

Land and ownership6

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area9,098 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared present
Charge in favour ofAbhiyan Marchantts Pvt Ltd
Secured amountRs 6.00 crore
CERSAI search filedYes
Declared on30 Jun 2025
LandownerVillageDistrict
Rahul Mahajankondhwa khurdPune
Rohit Mahajankondhwa khurdPune
Sonam Mahajankondhwa BKPune
Interstellar Developers LLPkondhwa BKPune
Quadra InfraMOHAMMADWADIPune
Nirman Bharti Lifestyle HomesParvatiPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI15460.42
Proposed, not sanctioned4,928 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLane No 7, Koregaon Park, Pune-411001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr.Rahul Malvadkar
EngineerMr.Rajesh Mankani
Chartered AccountantV V UDGAVE & ASSOCIATES
Chartered AccountantK.G Jhamvar and Co
PartnerRole in project
Gagan Landmarks LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016960Dec 2020 → Mar 2024

Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No. 23 Hissa No. 7/1, 7/2 and 7/3, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 30/06/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/06/2023. However, due to unfore

EXT52100013155Dec 2020 → Jun 2023

Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No. 23 Hissa No. 7/1, 7/2 and 7/3, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 30/12/2022, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/12/2022. However, due to unfore

EXT52100002372Dec 2020 → Dec 2021

Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN ELA” under implementation by us on land out of Survey No.23, Village Mohammedwadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100002439 dated 01/08/2017. 2) In anticipation that we would complete the said Project on or before 31/12/2020, in our Application to you for Registration of our Project, we had mentioned the date of Completion as 31/12/2020. However, due to unforeseen and unexpected delays i

EXT52100019775Dec 2020 → Jun 2025

Reason as filed by the promoter1. As per the latest QPR the Construction of the project GAGAN ELA is approximately 90% completed. 2. The proposed completion date for the project was 30.12.2022 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.

Litigation declared3

CaseCourtStatus
RCS No 1945/2018Civil Judge Junior Division PuneAwaiting Summons
261/2019Civil Judge Senior Division PuneAwaiting Summons
RCS. No. 1945/2018Civil CourtOngoing

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000075187Makarand PatilGagan Developers09/06/2021
CC005000000238699Sameer Nasir MominGagan Landmark LLP08/05/2023
CC005000000269662DEEPA RAJESH MAKHIJARAHUL ASHOK MAHAJAN17/11/2023
CC12502119Mary Reena DsouzaGagan Landmarks LLP27/06/2025
CC12504574Taher Hatim LokhandwalaGagan Landmarks LLP22/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed219

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 219 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5.pdf2 Dec 2025
Occupational CertificateFile: Occupancy certificate verification.pdf10 Jul 2025
Occupational CertificateFile: Commencement Certificate.pdf10 Jul 2025
Occupational CertificateFile: Commencement Certificate verification.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7701.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7702.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7703.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7704.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7705.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7706.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7707.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7708.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7709.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7710.pdf10 Jul 2025
Occupational CertificateFile: HPSCANNER7711.pdf10 Jul 2025
Occupational CertificateFile: Gagan Ela Full Completion.pdf30 Jun 2025
Certificates of CA (Form 3)File: Form 3.pdf5 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf5 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Gagan Ela Form 2A Name added.pdf25 Mar 2025
Disclosure of sold/ booked inventoryFile: Form 3 gagan ela.pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Gagan Ela.pdf21 Mar 2025
Other - TechnicalFile: Pert chart gagan ela.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Gagan Ela 31 12 2024_compressed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Booked inventory 30 09 2023_0001_11zon.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked inventory 31 12 2023_0001_11zon.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked inventory 31 03 2024_0001_11zon.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked inventory 30 06 2024_0001_11zon.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Booked inventory 30 09 2024_0001_11zon.pdf29 Nov 2024
Declaration in FORM BFile: Form B_0001.pdf26 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf15 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf15 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf15 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ela Form 5.pdf28 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf12 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf12 Aug 2024
Certificates of CA (Form 3)File: Form 3.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Mar 2024
Certificates of CA (Form 3)File: Form 3.pdf18 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf22 Nov 2023
Certificates of CA (Form 3)File: Form 3.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Gagan Ela.pdf25 Oct 2023
Declaration about Commencement CertificateFile: Dclaration CC.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Certificate.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate.pdf19 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf19 Jul 2023
Details of encumbrancesFile: Encumbrance certificate.pdf11 Jul 2023
Declaration in FORM BFile: Form B.pdf11 Jul 2023
Declaration in FORM BFile: Form B.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf11 Jul 2023
Certificates of CA (Form 3)File: Form 3.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf9 May 2023
Certificates of CA (Form 3)File: Form 3.pdf9 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf10 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf10 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf16 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf16 Dec 2022
Certificates of CA (Form 3)File: Form 3.pdf16 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Gagan Ela.pdf6 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf11 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf11 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf11 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf11 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf11 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf11 Aug 2022

How this compares with Pune

80%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 54 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gagan Ela on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mohammadwadi13,700+ in Pune

2 kmGagan ElaCompleted 76Lapsed / revoked 26Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: Gagan Landmarks LLP

Gagan Landmarks LLP has 3 registrations on MahaRERA, including Gagan Ela and Gagan Aviva. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Gagan Ela is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gagan Ela?

The registered promoter entity is Gagan Landmarks LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gagan Ela?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gagan Ela?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gagan Ela?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gagan Ela?

The professionals named in the filing: Architect: Mr.Rahul Malvadkar; Engineer: Mr.Rajesh Mankani; Chartered Accountant: V V UDGAVE & ASSOCIATES; Chartered Accountant: K.G Jhamvar and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gagan Ela?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gagan Ela. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gagan Ela to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.