Home / Browse projects / Gagan Avencia

Registration lapsed Litigation declared Others project

Gagan Avencia

By Onyx Promoters LLP

RG-MH-19856 · RERA P52100005102 · Last updated on MahaRERA portal: 28 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Litigation declared, 2 cases
  • 13 complaints at MahaRERA
  • Completion date moved by 54 months
  • 4 extensions taken
  • Rs 70.00 crore secured on the land, in favour of Hero fincrop Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Sep 2025Possession promised13 months past this date
48 of 55Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 95%
7 of 362Units unsoldnot recorded sold or booked
13Complaints at MahaRERAon this registration
Jump to the 241 documents Report an error

Gagan Avencia is a Others project by Onyx Promoters LLP in KHARADI, PUNE, 411014, registered with MahaRERA as P52100005102 on 9 Aug 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 54 months from the original filing. 355 of the 362 units on this registration are recorded sold or booked, and 48 of 55 construction stages are filed complete. 13 complaints are on record with the regulator.

At a glance

Project

  • NameGagan Avencia
  • TypeOthers
  • Location
    • Grant Road
    • KHARADI
    • PUNE
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005102
  • ReraGenie IDRG-MH-19856

Builder

  • NameOnyx Promoters LLP
  • Entity typePartnership
  • GSTIN27AAFFO0079E1ZE
  • PartnersPushparaj Krishan LAL Khanna, Rahul Sureshchand Garg
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

13 months past promisethis monthRegisteredAug 2017First promiseMar 2021Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Mar 2021)
  • Buildings5 building records
  • Documents filed241 files

Current status

98%355 of 362 units booked
92.7%Work done, per cost certificate

Figures as on 28 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA211868068
BNA211867067
Commercial and MhadaNA1714375592
CNA201867067
DNA201868068

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 28 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

A99%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B99%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Commercial and Mhada97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
C98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D99%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes98%
Street LightingYes100%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1116

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,116
Closed/Covered230
Open Space886
BuildingClosed/CoveredOpen SpaceTotal
A69207276
B33165198
Commercial and Mhada61172233
C36170206
D31172203

Land and ownership5

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area14,025 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared present
Charge in favour ofHero fincrop Limited
Secured amountRs 70.00 crore
Declared on27 May 2025
LandownerVillageDistrict
Gagan Landmarks LLP-Pune
Westfield Properties LLPwanwadiPune
Gagan SpaceswanwadiPune
Bay Point Realty LLPwanwadiPune
Gagan Township LLP-Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI30888.75
Proposed, not sanctioned30,889 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMahalunge , Pune-410501
Estimated costRs 88.91 cr
Cost incurredRs 82.44 cr
Work done92.72%
BuildingWingEstimatedIncurred
ANARs 17.37 crRs 16.79 cr
BNARs 15.92 crRs 15.38 cr
-NARs 14.71 crRs 10.71 cr
CNARs 13.91 crRs 13.36 cr
DNARs 13.88 crRs 13.24 cr
Commercial and MhadaNARs 13.12 crRs 12.96 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJay Aeram and Associates
ArchitectMr Malwadkar
EngineerVAIBHAV INGAVALE
EngineerMr.Rajesh Mankani
Chartered AccountantK. G Jhamvar
PartnerRole in project
Onyx Promoters LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001546Mar 2021 → Mar 2022

Reason as filed by the promoter1) Our Project was originally proposed to be implemented on a portion admeasuring 10,724.80 sq.mtrs out of land admeasuring Hectares 01=20 Ares bearing Survey No.63 Hissa No.1/1, Village Kharadi, Pune. 2) Accordingly, the Maharashtra Real Estate Regulatory Authority has granted Registration. 3) We are in the process of acquiring some additional adjoining land out of land bearing Survey No.63 Hissa No.2, Kharadi and we propose to amalgamate such additional land with our existing Layout and develop a separate Project known as “GAGAN AVENCIA PHASE II”. The Building to be constructed by us for Mah

EXT52100013987Mar 2021 → Sep 2023

Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN AVENCIA” under implementation by us on land out of Survey No. 63 Hissa No. 1/1 situate, lying and being at Village Kharadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100005102 dated 09/08/2017. 2) In anticipation that we would complete the said Project on or before 30/03/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/03/2023. However,

EXT52100017958Mar 2021 → Sep 2024

Reason as filed by the promotera. Onyx Promoters LLP is developing a project registered with the MahaRERA under Project Registration No. P52100005102. The Promoter had mentioned the original date of completion as 30th March 2023 and had commenced the construction and development of project accordingly. b. However, on account of COVID-19 outbreak, the development activities at the project were halted. c. Later, during the part-normalcy period of the COVID-19 outbreak, there was acute shortage of skilled and unskilled labours in the Pune region. Due to above reason, the project could not be completed within the specified time

EXT52100025432Mar 2021 → Sep 2025

Reason as filed by the promoter1. As per the latest QPR the Construction of the project GAGAN AVENCIA is approximately 90% completed. 2. The proposed completion date for the project was 30/09/2024 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.

Litigation declared2

CaseCourtStatus
680/2018Civil Court Senior Division PuneAwaiting Summons
680/2018Civil CourtOngoing

Complaints filed with MahaRERA13

Case no.ComplainantRespondentFiled
CC005000000471232Pranay Ramesh MotghareOnyx Promoters LLP30/07/2024
CC005000000471613ATUL JAINONYX PROMOTERS LLP19/08/2024
CC12400018RAHUL VERMAOnyx Promoters LLP04/09/2024
CC12400221Vishal ShuklaOnyx Promoters LLP25/09/2024
CC12400642ALOK KUMAR CHHATRYOnyx Promoters LLP04/11/2024
CC12400598Noor Alam ShaikhOnyx Promoters LLP28/10/2024
CC12400725Ajay SinghOnyx Promoters LLP10/11/2024
CC12500394Sameer Ashok SawaleOnyx Promoters LLP05/02/2025
CC12500469Sahil Sandip ShahaOnyx Promoters LLP12/02/2025
CC12503629Akhila Madhukar MangalvedhekarOnyx Promoters LLP12/10/2025
CC12504298Stanny Michael KedariOnyx Promoters LLP05/12/2025
CC12600856Sahil Sandip ShahaOnyx Promoters LLP16/02/2026
CC12603861Gaurav VaishnavaOnyx Promoters LLP22/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed241

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 241 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf28 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf28 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf28 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf28 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf28 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf28 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf30 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf30 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf30 Jul 2025
Certificates of CA (Form 3)File: Form 3.pdf25 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A gagan final.pdf17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Gagan Avencia 2023 2024.pdf15 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B(1).pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY_compressed.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY.pdf18 Jan 2025
Declaration in FORM BFile: From B_0001.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31 03 2024_0001_11zon (1).pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 33 06 2024_0001_11zon.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30 09 2024_0001_11zon (2).pdf6 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf4 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf4 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Avencia Form 5.pdf28 Oct 2024
Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory (1).pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf12 Jan 2024
Certificates of CA (Form 3)File: Form 3.pdf12 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 Jan 2024
Certificates of CA (Form 3)File: FORM 3.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance 2022.pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance 2023.pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf1 Dec 2023
Layout approvalFile: Layout.pdf8 Nov 2023
Building plan approvalFile: Parking.pdf8 Nov 2023
Building plan approvalFile: A and B Wing.pdf8 Nov 2023
Building plan approvalFile: C Wing.pdf8 Nov 2023
Building plan approvalFile: Wing D.pdf8 Nov 2023
Building plan approvalFile: MHADA.pdf8 Nov 2023
Building plan approvalFile: Commercial.pdf8 Nov 2023
Layout approvalFile: Layout.pdf8 Nov 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf8 Nov 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf8 Nov 2023
Building Plan Approval (IOD)File: Parking.pdf8 Nov 2023
Building Plan Approval (IOD)File: A and B Wing.pdf8 Nov 2023
Building Plan Approval (IOD)File: C Wing.pdf8 Nov 2023
Building Plan Approval (IOD)File: Wing D.pdf8 Nov 2023
Building Plan Approval (IOD)File: MHADA.pdf8 Nov 2023
Building Plan Approval (IOD)File: Commercial.pdf8 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC - 2865.pdf8 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf8 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC0829.pdf8 Nov 2023
Details of encumbrances concerned to FinanceFile: Encumbrance related to legal_0001.pdf6 Nov 2023
Details of encumbrances concerned to LegalFile: Encumbrance related to legal_0001.pdf6 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate Rahul Garg_0001.pdf6 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate Rohit Garg_0001.pdf6 Nov 2023
Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf6 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate Bank account_0001.pdf6 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Gagan Avencia.pdf22 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (2).pdf13 Sep 2023
Certificates of CA (Form 3)File: CA Certificate Original_compressed (1).pdf13 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Gagan Avencia_0001_compressed.pdf13 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf16 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf16 Aug 2023
Certificates of CA (Form 3)File: CA Certificate.pdf16 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf10 May 2023
Certificates of CA (Form 3)File: Form 3.pdf10 May 2023

Keep Gagan Avencia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHARADI, PUNE

2 kmGagan AvenciaCompleted 35Lapsed / revoked 15Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: Onyx Promoters LLP

Onyx Promoters LLP has 2 registrations on MahaRERA, including Gagan Avencia and Gagan Avencia Phase II. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that Gagan Avencia shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Gagan Avencia is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gagan Avencia?

The registered promoter entity is Onyx Promoters LLP, a partnership as per the filing. Its GSTIN 27AAFFO0079E1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gagan Avencia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gagan Avencia?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gagan Avencia?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gagan Avencia?

The professionals named in the filing: Architect: Jay Aeram and Associates; Architect: Mr Malwadkar; Engineer: VAIBHAV INGAVALE; Engineer: Mr.Rajesh Mankani; Chartered Accountant: K. G Jhamvar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gagan Avencia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gagan Avencia. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gagan Avencia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.