Home / Browse projects / Gagan Avencia
Gagan Avencia
RG-MH-19856 · RERA P52100005102 · Last updated on MahaRERA portal: 28 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 13 months past the filed date
- Litigation declared, 2 cases
- 13 complaints at MahaRERA
- Completion date moved by 54 months
- 4 extensions taken
- Rs 70.00 crore secured on the land, in favour of Hero fincrop Limited
Clear
- Separate project account declared
- Allotment letter follows the model form
7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gagan Avencia is a Others project by Onyx Promoters LLP in KHARADI, PUNE, 411014, registered with MahaRERA as P52100005102 on 9 Aug 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 54 months from the original filing. 355 of the 362 units on this registration are recorded sold or booked, and 48 of 55 construction stages are filed complete. 13 complaints are on record with the regulator.
At a glance
Project
- NameGagan Avencia
- TypeOthers
- Location
- Grant Road
- KHARADI
- PUNE
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100005102
- ReraGenie IDRG-MH-19856
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion30 Sep 2025
- Revised completionRevised to 30 Sep 2025 (originally 31 Mar 2021)
- Buildings5 building records
- Documents filed241 files
Current status
Figures as on 28 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 21 | 18 | 68 | 0 | 68 |
| B | NA | 21 | 18 | 67 | 0 | 67 |
| Commercial and Mhada | NA | 17 | 14 | 37 | 55 | 92 |
| C | NA | 20 | 18 | 67 | 0 | 67 |
| D | NA | 20 | 18 | 68 | 0 | 68 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 28 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
48 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
A99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Commercial and Mhada97%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
C98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 28 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 98% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 90% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1116
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A | 69 | 207 | 276 |
| B | 33 | 165 | 198 |
| Commercial and Mhada | 61 | 172 | 233 |
| C | 36 | 170 | 206 |
| D | 31 | 172 | 203 |
Land and ownership5
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Gagan Landmarks LLP | - | Pune |
| Westfield Properties LLP | wanwadi | Pune |
| Gagan Spaces | wanwadi | Pune |
| Bay Point Realty LLP | wanwadi | Pune |
| Gagan Township LLP | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 17.37 cr | Rs 16.79 cr |
| B | NA | Rs 15.92 cr | Rs 15.38 cr |
| - | NA | Rs 14.71 cr | Rs 10.71 cr |
| C | NA | Rs 13.91 cr | Rs 13.36 cr |
| D | NA | Rs 13.88 cr | Rs 13.24 cr |
| Commercial and Mhada | NA | Rs 13.12 cr | Rs 12.96 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Jay Aeram and Associates |
| Architect | Mr Malwadkar |
| Engineer | VAIBHAV INGAVALE |
| Engineer | Mr.Rajesh Mankani |
| Chartered Accountant | K. G Jhamvar |
| Partner | Role in project |
|---|---|
| Onyx Promoters LLP | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Our Project was originally proposed to be implemented on a portion admeasuring 10,724.80 sq.mtrs out of land admeasuring Hectares 01=20 Ares bearing Survey No.63 Hissa No.1/1, Village Kharadi, Pune. 2) Accordingly, the Maharashtra Real Estate Regulatory Authority has granted Registration. 3) We are in the process of acquiring some additional adjoining land out of land bearing Survey No.63 Hissa No.2, Kharadi and we propose to amalgamate such additional land with our existing Layout and develop a separate Project known as “GAGAN AVENCIA PHASE II”. The Building to be constructed by us for Mah
Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN AVENCIA” under implementation by us on land out of Survey No. 63 Hissa No. 1/1 situate, lying and being at Village Kharadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100005102 dated 09/08/2017. 2) In anticipation that we would complete the said Project on or before 30/03/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/03/2023. However,
Reason as filed by the promotera. Onyx Promoters LLP is developing a project registered with the MahaRERA under Project Registration No. P52100005102. The Promoter had mentioned the original date of completion as 30th March 2023 and had commenced the construction and development of project accordingly. b. However, on account of COVID-19 outbreak, the development activities at the project were halted. c. Later, during the part-normalcy period of the COVID-19 outbreak, there was acute shortage of skilled and unskilled labours in the Pune region. Due to above reason, the project could not be completed within the specified time
Reason as filed by the promoter1. As per the latest QPR the Construction of the project GAGAN AVENCIA is approximately 90% completed. 2. The proposed completion date for the project was 30/09/2024 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 680/2018 | Civil Court Senior Division Pune | Awaiting Summons |
| 680/2018 | Civil Court | Ongoing |
Complaints filed with MahaRERA13
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471232 | Pranay Ramesh Motghare | Onyx Promoters LLP | 30/07/2024 |
| CC005000000471613 | ATUL JAIN | ONYX PROMOTERS LLP | 19/08/2024 |
| CC12400018 | RAHUL VERMA | Onyx Promoters LLP | 04/09/2024 |
| CC12400221 | Vishal Shukla | Onyx Promoters LLP | 25/09/2024 |
| CC12400642 | ALOK KUMAR CHHATRY | Onyx Promoters LLP | 04/11/2024 |
| CC12400598 | Noor Alam Shaikh | Onyx Promoters LLP | 28/10/2024 |
| CC12400725 | Ajay Singh | Onyx Promoters LLP | 10/11/2024 |
| CC12500394 | Sameer Ashok Sawale | Onyx Promoters LLP | 05/02/2025 |
| CC12500469 | Sahil Sandip Shaha | Onyx Promoters LLP | 12/02/2025 |
| CC12503629 | Akhila Madhukar Mangalvedhekar | Onyx Promoters LLP | 12/10/2025 |
| CC12504298 | Stanny Michael Kedari | Onyx Promoters LLP | 05/12/2025 |
| CC12600856 | Sahil Sandip Shaha | Onyx Promoters LLP | 16/02/2026 |
| CC12603861 | Gaurav Vaishnava | Onyx Promoters LLP | 22/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Nov 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed241
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 241 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 28 Nov 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Nov 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 30 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 30 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 30 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 25 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 17 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 17 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A gagan final.pdf | 17 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Gagan Avencia 2023 2024.pdf | 15 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B(1).pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY_compressed.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY.pdf | 18 Jan 2025 |
| Declaration in FORM BFile: From B_0001.pdf | 6 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31 03 2024_0001_11zon (1).pdf | 6 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 33 06 2024_0001_11zon.pdf | 6 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30 09 2024_0001_11zon (2).pdf | 6 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 4 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 4 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 4 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 4 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 4 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 4 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 4 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Avencia Form 5.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory (1).pdf | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 12 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf | 10 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 10 Jan 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 10 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance 2022.pdf | 1 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance 2023.pdf | 1 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf | 1 Dec 2023 |
| Layout approvalFile: Layout.pdf | 8 Nov 2023 |
| Building plan approvalFile: Parking.pdf | 8 Nov 2023 |
| Building plan approvalFile: A and B Wing.pdf | 8 Nov 2023 |
| Building plan approvalFile: C Wing.pdf | 8 Nov 2023 |
| Building plan approvalFile: Wing D.pdf | 8 Nov 2023 |
| Building plan approvalFile: MHADA.pdf | 8 Nov 2023 |
| Building plan approvalFile: Commercial.pdf | 8 Nov 2023 |
| Layout approvalFile: Layout.pdf | 8 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 8 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: Parking.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: A and B Wing.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: C Wing.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: Wing D.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: MHADA.pdf | 8 Nov 2023 |
| Building Plan Approval (IOD)File: Commercial.pdf | 8 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - 2865.pdf | 8 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 8 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC0829.pdf | 8 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance related to legal_0001.pdf | 6 Nov 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance related to legal_0001.pdf | 6 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate Rahul Garg_0001.pdf | 6 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate Rohit Garg_0001.pdf | 6 Nov 2023 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf | 6 Nov 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate Bank account_0001.pdf | 6 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Gagan Avencia.pdf | 22 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (2).pdf | 13 Sep 2023 |
| Certificates of CA (Form 3)File: CA Certificate Original_compressed (1).pdf | 13 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Gagan Avencia_0001_compressed.pdf | 13 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 16 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 16 Aug 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 16 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 10 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 10 May 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 10 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 7 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 241 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Gagan Avencia on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHARADI, PUNE
Filed coordinates, straight-line distance. 68 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: Onyx Promoters LLP
Onyx Promoters LLP has 2 registrations on MahaRERA, including Gagan Avencia and Gagan Avencia Phase II. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What does it mean that Gagan Avencia shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Gagan Avencia is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gagan Avencia?
The registered promoter entity is Onyx Promoters LLP, a partnership as per the filing. Its GSTIN 27AAFFO0079E1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gagan Avencia?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Gagan Avencia?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Gagan Avencia?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gagan Avencia?
The professionals named in the filing: Architect: Jay Aeram and Associates; Architect: Mr Malwadkar; Engineer: VAIBHAV INGAVALE; Engineer: Mr.Rajesh Mankani; Chartered Accountant: K. G Jhamvar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gagan Avencia?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback