FLOWER VALLEY COMPLEX
RG-MH-64511 · RERA P99000017544 · Last updated on MahaRERA portal: 7 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
FLOWER VALLEY COMPLEX is a Commercial project by SHERU SHAMSHER KHAN in Palghar, Maharashtra, registered with MahaRERA as P99000017544 on 24 Aug 2018. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 40 of the 94 units on this registration are recorded sold or booked, and 1 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameFLOWER VALLEY COMPLEX
- TypeCommercial
- Location
- BOISAR ROAD
- UMROLI
- Birwadi
- Palghar
- 401404
- Pincode401404
- RERA no.P99000017544
- ReraGenie IDRG-MH-64511
Builder
- NameSHERU SHAMSHER KHAN
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Aug 2018
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 30 Dec 2022)
- Buildings3 building records
- Documents filed98 files
Current status
Figures as on 7 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 7 | NA | 3 | 3 | 12 | 0 | 12 |
| BUILDING NO 13 | NA | 3 | 3 | 15 | 11 | 26 |
| BUILDING NO 16 | NA | 4 | 4 | 56 | 0 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 7 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 30%.
BUILDING NO 70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 130%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1615%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 30% |
| Podiums (if any) | 0% |
| Plinth | 30% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 7 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NISHANT PATIL VASTU SHILP AND ASSOCIATES |
| Engineer | YOGESH VAJA DARSH CONSULT |
| Engineer | Vinay Singh |
| Chartered Accountant | Bharat Dhonde & Co. |
| Chartered Accountant | Mohammad Memon |
| Partner | Role in project |
|---|---|
| SHERU SHAMSHER KHAN | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOurs is a Residential cum Commercial Construction project located in rural area of Village Mahim, Taluka and District Palghar 401404. 1. Our projects validity has expired on 30.12.2022. 2. However, due to general recession in Real Estate Sector, lack of liquidity in NBFC and slow growth in economy, dried the resources with the customers, The new sale is also very slow. In spite, this we continued to pour in all the money for construction of project. 3. The Details of percentage of Completions as on today is around 90 %. 4. We are sure that we would be able to complete the project within extend
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000251625 | DATTA KISHAN RAMASNE | SHERU SHAMSHER KHAN | 25/06/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jun 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: 1 Form 1- Jun 23.pdf | 7 Jun 2025 |
| Form 2File: 1 Form 2- Jun 23.pdf | 7 Jun 2025 |
| Form 3File: 2 Form 3- June 23.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold June-23.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: June- 2023.pdf | 7 Jun 2025 |
| Form 1File: Form 1- Mar 23.pdf | 7 Jun 2025 |
| Form 2File: Form 2- Mar 23.pdf | 7 Jun 2025 |
| Form 3File: 1 Form 3- Mar 23.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold - Mar-2023.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: March-2023.pdf | 7 Jun 2025 |
| Form 1File: 2 Form 1- Sept 23.pdf | 7 Jun 2025 |
| Form 2File: 2 Form 2- Sept 23.pdf | 7 Jun 2025 |
| Form 3File: 3 Form 3- Sept 23.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold- Sep 23.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: September-2023.pdf | 7 Jun 2025 |
| Form 1File: 3 Form 1- Dec 23.pdf | 7 Jun 2025 |
| Form 2File: 3 Form 2- Dec 23.pdf | 7 Jun 2025 |
| Form 3File: 4 Form 3- Dec 23.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: December-2023.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold- Dec 23.pdf | 7 Jun 2025 |
| Form 1File: 4 Form 1- Mar 24.pdf | 7 Jun 2025 |
| Form 2File: 4 Form 2- March 24.pdf | 7 Jun 2025 |
| Form 3File: 5 Form 3- Mar 24.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: March-2024.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold- Mar 24.pdf | 7 Jun 2025 |
| Form 1File: 5 Form 1- Jun 24.pdf | 7 Jun 2025 |
| Form 2File: 5 Form 2- Jun 24.pdf | 7 Jun 2025 |
| Form 3File: 6 Form 3- June 24.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: June-2024.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold- June 24.pdf | 7 Jun 2025 |
| Form 1File: 6 Form 1- Sept 24.pdf | 7 Jun 2025 |
| Form 2File: 6 Form 2- Sept 24.pdf | 7 Jun 2025 |
| Form 3File: 7 Form 3- Sept 24.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: September-2024.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold- Sep 24.pdf | 7 Jun 2025 |
| Form 1File: 7 Form 1- Dec 24.pdf | 7 Jun 2025 |
| Form 2File: 7 Form 2- Dec 24.pdf | 7 Jun 2025 |
| Form 3File: 8 Form 3- Dec 24.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: December-2024.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold- Dec 24.pdf | 7 Jun 2025 |
| Form 1File: 8 Form 1- Mar 25.pdf | 7 Jun 2025 |
| Form 2File: 8 Form 2- March 25.pdf | 7 Jun 2025 |
| Form 3File: 9 Form 3- Mar 25.pdf | 7 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: March-2025.pdf | 7 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory- Mar 25.pdf | 7 Jun 2025 |
| Form 5 (FY 2022-2023)File: FORM 5 2022-23.pdf | 7 Jun 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 2023-24.pdf | 7 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked inventory.pdf | 27 May 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200269222195_For_Asset_Based_Search_20_05_2023_16_10_04_113.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 March 2019.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 March 2020_5_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 Dec2021 old_4_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 Dec2021_7_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 Dec2021 old_4_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 March 2022_6_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 30 June 2020_1_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 30 Sept 2022_2_11zon.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Form 3 As on 31 Dec2022_3_11zon.pdf | 20 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Annual Report Of Statement of account on1-4-2018.pdf | 20 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Report Of Statement of account on1-4-2018.pdf | 20 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Report Of Statement of account on 31-3-2020.pdf | 20 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 as on 31-3-2021.pdf | 20 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 as on 31-3-2022.pdf | 20 May 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Declaration.pdf | 29 Apr 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance Declaration.pdf | 29 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Designated bank account declaration.pdf | 29 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 28 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE 27-4-2023.pdf | 28 Apr 2023 |
| Proforma of Agreement for saleFile: AFS (2)-1-33_11zon.pdf | 27 Apr 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 27 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory.pdf | 27 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf | 27 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Report for Allotment Letter.pdf | 27 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report for Sale.pdf | 27 Mar 2023 |
| Details of encumbrancesFile: No Encumbrances.pdf | 1 Aug 2018 |
| Declaration in FORM BFile: Affidavit Cum Declaration.pdf | 1 Aug 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate- 2.pdf | 1 Aug 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 1 Aug 2018 |
| Building plan approvalFile: Building no 7.pdf | 28 Jun 2018 |
| Building plan approvalFile: Building no 13.pdf | 28 Jun 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep FLOWER VALLEY COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near UMROLI3,200+ in Palghar
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: SHERU SHAMSHER KHAN
SHERU SHAMSHER KHAN has 1 registration on MahaRERA, including FLOWER VALLEY COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that FLOWER VALLEY COMPLEX shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if FLOWER VALLEY COMPLEX is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of FLOWER VALLEY COMPLEX?
The registered promoter entity is SHERU SHAMSHER KHAN, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in FLOWER VALLEY COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against FLOWER VALLEY COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for FLOWER VALLEY COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at FLOWER VALLEY COMPLEX?
The professionals named in the filing: Architect: NISHANT PATIL VASTU SHILP AND ASSOCIATES; Engineer: YOGESH VAJA DARSH CONSULT; Engineer: Vinay Singh; Chartered Accountant: Bharat Dhonde & Co.; Chartered Accountant: Mohammad Memon. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in FLOWER VALLEY COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback