ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / FAIR TOWNSHIP BUILDING NO 1

Registered No litigation declared Others project

FAIR TOWNSHIP BUILDING NO 1

By OM VALUE HOMES

RG-MH-07502 · RERA P99000055618 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
10 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 50%
119 of 129Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

FAIR TOWNSHIP BUILDING NO 1 is a Others project by OM VALUE HOMES in Palghar, Maharashtra, registered with MahaRERA as P99000055618 on 4 Apr 2024. Possession is promised by 31 Dec 2026. 10 of the 129 units on this registration are recorded sold or booked, and 10 of 33 construction stages are filed complete.

At a glance

Project

  • NameFAIR TOWNSHIP BUILDING NO 1
  • TypeOthers
  • Location
    • DHANSAR
    • PALGHAR WEST
    • Palghar
    • 401404
  • Pincode401404
  • RERA no.P99000055618
  • ReraGenie IDRG-MH-07502

Builder

  • NameOM VALUE HOMES
  • Entity typePartnership
  • PartnersSURJIT KUMAR SURYRAJ SINGH, RAMESH MANIKRAO NANDGAWLE, AJIT KUMAR SURYRAJ SINGH, AJAY KUMAR SURYRAJ SINGH, NIKHIL RAMESH NANDGAWLE, SWAPNIL RAMESH NANDGAWLE

Key dates

this monthRegisteredApr 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed66 files

Current status

8%10 of 129 units booked

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FAIRE TOEWNSHI BUILDING 1 A WINGNA77491261
FAIR TOWNSHIP BUILDING NO 1 B WINGNA7728634
FAIR TOWNSHIP BUILDING 1 C WINGNA7728634

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

FAIRE TOEWNSHI BUILDING 1 A WING42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
FAIR TOWNSHIP BUILDING NO 1 B WING27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
FAIR TOWNSHIP BUILDING 1 C WING27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered12
Open Space84
BuildingClosed/CoveredOpen SpaceTotal
FAIRE TOEWNSHI BUILDING 1 A WING42832
FAIR TOWNSHIP BUILDING NO 1 B WING42832
FAIR TOWNSHIP BUILDING 1 C WING42832

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,986 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHREE DAYARAM HOMESVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI5562.26
Proposed, not sanctioned5,562 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1,2,3,4,5 SHREE RAM SANKUL, ACHOLE ROAD, NALLASOPARA EAST, PIN-401209

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectODYSSEY ARCHITECTS & ASSOCIATES
EngineerJAY SHREE KRISHNA CONSULTANTS
EngineerNEE CONSULTANCY
Chartered AccountantS T R & ASSOCIATES
Chartered AccountantHARESH MEHTA AND ASSOCIATES
Chartered AccountantS.LAKDAWALA & ASSOCIATES
PartnerRole in project
OM VALUE HOMES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Jan to Mar 26.pdf26 May 2026
Form 2File: Form 2 Jan to Mar 26.pdf26 May 2026
Form 3File: Form 3 Jan to Mar 26.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Jan to Mar 2026.pdf26 May 2026
Form 2A (FY 2024-2025)File: FORM_2A.pdf20 Feb 2026
Form 1File: Form 1-Oct to Dec 25.pdf16 Feb 2026
Form 2File: Form 2 -Oct to Dec 25.pdf16 Feb 2026
Form 3File: Form 3 Oct to Dec 25.pdf16 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Oct to Dec 25.pdf16 Feb 2026
Form 1File: FORM-1 Jul to sep 25.pdf4 Nov 2025
Form 2File: FORM 2 Jul to Sep 25.pdf4 Nov 2025
Form 3File: Form 3-July to September 25_11zon.pdf4 Nov 2025
Disclosure of Sold and Booked InventoryFile: Inventory-July to September 25.pdf4 Nov 2025
Form 1File: FORM 1 Jan to Mar 25.pdf13 Aug 2025
Form 2File: FORM 2 Jan to Mar 25.pdf13 Aug 2025
Form 3File: Form 3 jan to March 2025_11zon.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold-Unsold Jan to March 2025.pdf13 Aug 2025
Form 1File: FORM_1 Apr to Jun 25.pdf13 Aug 2025
Form 2File: FORM_2 Apr to Jun 25.pdf13 Aug 2025
Form 3File: Form 3 April to june 2025_11zon.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold-Unsold April to jun 2025.pdf13 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon (1).pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_FAIRTOWN BLDG 1 SIGNED REV-1.pdf16 Mar 2024
Proforma of Allotment letterFile: AL revised.pdf16 Mar 2024
Proforma of Agreement for saleFile: SALE AGREEMENT REVISED 16 03 24.pdf16 Mar 2024
Other - TechnicalFile: ANNEXURE A.pdf16 Mar 2024
Other - TechnicalFile: LAYOUT PLAN SHEET 01 OPTI hl.pdf16 Mar 2024
Layout approvalFile: LAYOUT PLAN SHEET 01 OPTI.pdf8 Mar 2024
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN SHEET 01 OPTI.pdf8 Mar 2024
Other - TechnicalFile: Land Area Declaration FAIR TOWNSHIP BLDG 1.pdf8 Mar 2024
Other - LegalFile: partnership Deed Om value Homes - converted.pdf1 Feb 2024
Other - TechnicalFile: cc verification.pdf1 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Surjit Singh.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: SRN Home Value Homes.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: RMN Home Value Homes.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: NRN Om Value Homes.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Ajay Singh.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Ajit Singh.pdf8 Jan 2024
Deviation Report with respect to Allotment letterFile: Deviation report Allotment letter.pdf8 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report sale agreement.pdf8 Jan 2024
Building plan approvalFile: BUILDING NO 1A SHEET 02OPT.pdf7 Jan 2024
Building plan approvalFile: BUILDING NI 1A SHEET 03 OPT.pdf7 Jan 2024
Building plan approvalFile: BUILDING NO 1C SHEET 05 OPT.pdf7 Jan 2024
Building plan approvalFile: BUILDING NO 1B SHEET 04 OPT.pdf7 Jan 2024
Details of encumbrances concerned to FinanceFile: Declaration about finance encumbrances.pdf7 Jan 2024
Details of encumbrances concerned to FinanceFile: Declaration for legal encumrances.pdf7 Jan 2024
Details of encumbrances concerned to LegalFile: Declaration about finance encumbrances.pdf7 Jan 2024
Details of encumbrances concerned to LegalFile: Declaration for legal encumrances.pdf7 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING NO 1A SHEET 02OPT.pdf7 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING NI 1A SHEET 03 OPT.pdf7 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING NO 1C SHEET 05 OPT.pdf7 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING NO 1B SHEET 04 OPT.pdf7 Jan 2024
Declaration in FORM BFile: FORM B DEVELOPERS.pdf7 Jan 2024
CERSAI detailsFile: CERSAI DECLARATION.pdf7 Jan 2024
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf6 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for bank ac (rera).pdf6 Jan 2024
Copy of the legal title reportFile: Title Certificate opt.pdf5 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: CC SR-227 OPT.pdf5 Jan 2024
PAN CardFile: Pan Card of Om Values Homes_01062023_unlocked.pdf4 Jan 2024

How this compares with Palghar

8%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep FAIR TOWNSHIP BUILDING NO 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR WEST3,200+ in Palghar

Builder: OM VALUE HOMES

OM VALUE HOMES has 1 registration on MahaRERA, including FAIR TOWNSHIP BUILDING NO 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if FAIR TOWNSHIP BUILDING NO 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FAIR TOWNSHIP BUILDING NO 1?

The registered promoter entity is OM VALUE HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FAIR TOWNSHIP BUILDING NO 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for FAIR TOWNSHIP BUILDING NO 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at FAIR TOWNSHIP BUILDING NO 1?

The professionals named in the filing: Architect: ODYSSEY ARCHITECTS & ASSOCIATES; Engineer: JAY SHREE KRISHNA CONSULTANTS; Engineer: NEE CONSULTANCY; Chartered Accountant: S T R & ASSOCIATES; Chartered Accountant: HARESH MEHTA AND ASSOCIATES; Chartered Accountant: S.LAKDAWALA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FAIR TOWNSHIP BUILDING NO 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FAIR TOWNSHIP BUILDING NO 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FAIR TOWNSHIP BUILDING NO 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.