Red flags

  • Litigation declared, 5 cases
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2031Possession promisedmoved 36 months from the original
1 of 11Construction stages donefurthest along: Staircases, 20%
112 of 112Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Emerald Bay Building 12 is a Residential / Group Housing project by Pune Projects LLP in Pune, Maharashtra, registered with MahaRERA as P52100026132 on 21 Aug 2020. Possession is promised by 30 Jun 2031. The completion date has moved by 36 months from the original filing. 0 of the 112 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameEmerald Bay Building 12
  • TypeResidential / Group Housing
  • Location
    • NA
    • Mundhawa
    • Haveli
    • Pune
    • 411036
  • Pincode411036
  • RERA no.P52100026132
  • ReraGenie IDRG-MH-16496

Builder

  • NamePune Projects LLP
  • Entity typePartnership
  • PartnerAshish Puravankara
  • Other registrations10 more →
  • Completed1 of 11
  • Declared earlier projects8 →

Key dates

this monthRegisteredAug 2020First promiseJun 2028Revised toJun 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Aug 2020
  • Promised completion30 Jun 2031
  • Revised completionRevised to 30 Jun 2031 (originally 30 Jun 2028)
  • Buildings1 building record
  • Documents filed59 files

Current status

0%0 of 112 units booked
20.1%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 12NA32281120112

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 20%.

Building 12: 12% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)7%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes15%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes5%
Street LightingYes10%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes10%
Energy managemcntYes5%
Fire protection and fire safety requirementsYes15%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area703 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jul 2026
LandownerVillageDistrict
Oxford Shelters Private LimitedPune (M Corp.)Pune
Hritik Technologies and Realty Private LimitedMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI12127.43
Proposed, not sanctioned12,127 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Centenary Branch M G Road Bangalore
Estimated costRs 45.13 cr
Cost incurredRs 9.06 cr
Work done20.06%
BuildingWingEstimatedIncurred
Building 12NARs 41.05 crRs 5.83 cr
-NARs 4.08 crRs 3.22 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudio Thirty Architects
ArchitectCrystal Arch
EngineerJW Consultants LLp
EngineerShashank Tripathi
EngineerVijay B Dulange
Chartered AccountantVDSR & Co LLP
Chartered AccountantBhvana Bhat & Associates
PartnerRole in project
Pune Projects LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024356Jun 2028 → Dec 2029

Reason as filed by the promoterRespected Sir, I, the undersigned, authorised signatory of the Promoter M/S Pune projects LLP, (Purva Emerald Bay 13) hereby state that we have registered the project “Purva Emerald Bay 13” (hereinafter referred to as the said project) situated at survey no 9 to 14, Hissa No. 1/37 to 1/46 at Mundhwa Keshava Nagar Village Haveli District Pune 411036 with MahaRERA vide registration number P52100026099 (Purva Emerald Bay 13). We state that the registration validity of the said project is going to expire on June 30, 2028, and pursuant to the same we have filed an application seeking further extens

EA24072621861Jun 2028 → Jun 2031

Reason as filed by the promoterThe Promoter respectfully submits that the present application for extension has been filed to obtain approval of the revised project completion date as 30/06/2031. Although the existing project completion date is 31/12/2029, the extension has been sought at this stage as the revised completion date is required to be reflected in the Agreements for Sale to be executed with the allotees and other project-related documents. The Promoter seeks approval of the revised completion date prior to execution of such agreements to ensure that all contractual documents accurately reflect the anticipated t

Litigation declared5

CaseCourtStatus
2033/2011Civil CourtPending for evidence
1670/2013Civil CourtPending for issues
1268/2016Civil CourtPending for summons
1263/2006Civil CourtPending for evidence
125/2019Civil CourtPending for arguments on exhibit

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2031

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf24 Jul 2026
Withdrawal Update Form 1File: 1.pdf24 Jul 2026
Withdrawal Update Form 1File: 3046_001.pdf24 Jul 2026
Withdrawal Update Form 2File: form 2.pdf24 Jul 2026
Withdrawal Update Form 2File: 2.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2 A _Emerald_B12_FY26-27_Q1.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 Dec.pdf24 Jul 2026
Withdrawal Update Form 3File: 3.pdf24 Jul 2026
Withdrawal Update Form 3File: Emerald Bay 12 Form 3_compressed.pdf24 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf24 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf24 Jul 2026
Form 1File: Form 1.pdf20 Jul 2026
Form 2File: Form 2.pdf20 Jul 2026
Form 3File: Form 3.pdf20 Jul 2026
Disclosure of Sold and Booked InventoryFile: NA.pdf20 Jul 2026
Form 1File: Architect Emerald Bay.pdf22 Sep 2025
Form 2File: Form 2 EB 12.pdf22 Sep 2025
Form 3File: EB 12 Form 3.pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: EB 12 Sold and Unsold.pdf22 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2 B3 and B10 to B13_30-Jun-24.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emerald_Bay_Building_12_RERA_compressed.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2 B3 and B10 to B13_31-Mar-24_.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emarlad Bay B 12 Form 3.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emerald_Bay_Building_12 CA.pdf20 Jul 2024
Other - FinanceFile: MODT Emerald_merged (10).pdf27 May 2024
Other - FinanceFile: MODT Emerald_merged (4).pdf16 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Emerald Bay-12_Form-5_FY22-23.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2 B3 and B10 to B13_30-June-23_.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2 B3 and B10 to B13_30-Sep-23_.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2, B3 and B10 to B13_31-Dec-22 .pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2 B3 and B10 to B13_30-Dec-23_.pdf14 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emaraland_Bay_Building 12.pdf14 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emerald Building 12 EMB.pdf14 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emerald Building 12.pdf15 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2, B3 and B10 to B13_31-Mar-23 .pdf5 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Emerald_Bye_Building_12_compressed.pdf5 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Emerald Bay B12 Form_5_FY21-22_sd.pdf5 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2, B3 and B10 to B13_31-Dec-22 .pdf18 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (RERA) - Architect Certificate for Emerald Bay B2, B3 and B10 to B13_30-Sep-22 .pdf7 Nov 2022
Details of encumbrancesFile: Index of charges_Pune Projects ABFL.pdf29 Aug 2022
Copy of the legal title reportFile: page-12-22.pdf16 Aug 2020
Copy of the legal title reportFile: page-23-30.pdf16 Aug 2020
Details of encumbrancesFile: PPLLP Charge Regn.pdf16 Aug 2020
Details of encumbrancesFile: Nil Encumbrance B12.pdf16 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: EB12 CA Cert.pdf14 Aug 2020
Layout approvalFile: LAYOUT PLAN.pdf13 Aug 2020
Building plan approvalFile: LAYOUT PLAN.pdf13 Aug 2020
PAN CardFile: PAN.pdf13 Aug 2020
Copy of the legal title reportFile: LSR.pdf13 Aug 2020
Details of encumbrancesFile: Mortgage Deed.pdf13 Aug 2020
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf13 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT PLAN.pdf13 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 1.pdf13 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 2.pdf13 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 3.pdf13 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 4.pdf13 Aug 2020
Declaration in FORM BFile: Affidavit - Pune Projects LLP.pdf13 Aug 2020
Proforma of Allotment letterFile: EB_Allotment Letter B12.pdf13 Aug 2020
Proforma of Allotment letterFile: ATS (EB) Draft v0.pdf13 Aug 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Purva WestendService Road Kudlu Gate Garebhavipalya Hosur Main Road Bangalore 560068815CompletedDec 2018Dec 2018

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Emerald Bay Building 12 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA13,700+ in Pune

Builder: Pune Projects LLP

Pune Projects LLP has 11 registrations on MahaRERA, including Purva Silversand and Purva Silversands Phase 2. Its filings disclose 8 earlier MahaRERA projects: declares 3 of 8 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Emerald Bay Building 12 is delayed beyond 30 Jun 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Emerald Bay Building 12?

The registered promoter entity is Pune Projects LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Emerald Bay Building 12?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Emerald Bay Building 12?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Emerald Bay Building 12?

The professionals named in the filing: Architect: Studio Thirty Architects; Architect: Crystal Arch; Engineer: JW Consultants LLp; Engineer: Shashank Tripathi; Engineer: Vijay B Dulange; Chartered Accountant: VDSR & Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Emerald Bay Building 12?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Emerald Bay Building 12. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Emerald Bay Building 12 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.