ReraGenieLog inGet a buyer report

Home / Developers / Pune Projects LLP

Pune Projects LLP: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Pune Projects LLP has 11 registrations in this build, including Purva Silversand and Purva Silversands Phase 2. Its filings disclose 8 earlier MahaRERA projects: 3 of 8 past projects completed on time. Litigation is declared on 5 of its registrations.

11Registrations in this build
8Past projects disclosed
+18 monthsMedian delivery slip
5Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Purva SilversandPune, Maharashtra--Completed
Purva Silversands Phase 2Pune, Maharashtra33691%Registered
Emerald Bay Building 2Pune, Maharashtra84100%Registered
Emerald Bay Building 3Pune, Maharashtra8498%Registered
Emerald Bay Building 11Pune, Maharashtra11255%Registered
Emerald Bay Building 10Pune, Maharashtra--Registered
Emerald Bay Building 12Pune, Maharashtra--Registered
Emerald Bay Building 13Pune, Maharashtra--Registered
Purva Atmosphere Tower 3Pune, Maharashtra--Registered
Purva Atmosphere Tower 2Pune, Maharashtra--Registered
Purva Atmosphere Tower 1Pune, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Purva Westend
31 Dec 201828 Dec 2018On time
Purva Silversands Phase 2
30 Nov 202028 Nov 2025+60 months
Emerald Bay Building 10
30 Jun 202531 Dec 2029+54 months
Emerald Bay Building 11
30 Jun 202530 Jun 2025On time
Emerald Bay Building 2
30 Jun 202531 Dec 2026+18 months
Emerald Bay Building 3
30 Jun 202530 Jun 2025On time
Emerald Bay Building 12
30 Jun 202831 Dec 2029+18 months
Emerald Bay Building 13
30 Jun 202831 Dec 2029+18 months

Frequently asked questions

How do I verify Pune Projects LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Pune Projects LLP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Pune Projects LLP unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.