Home / Browse projects / Pune, Maharashtra / Elina Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Elina Phase 2

By Trimurti Development Company

RG-MH-91674 · RERA P52100018875 · Last updated on MahaRERA portal: 17 Feb 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
30 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

Elina Phase 2 is a Residential / Group Housing project by Trimurti Development Company in Pune, Maharashtra, registered with MahaRERA as P52100018875 on 10 Dec 2018. Possession was promised by 30 Dec 2022 and is now 46 months past that date.

At a glance

Project

  • NameElina Phase 2
  • TypeResidential / Group Housing
  • Location
    • SUS Road
    • Next to VIBGYOR School
    • Sus
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018875
  • ReraGenie IDRG-MH-91674

Builder

  • NameTrimurti Development Company
  • Entity typePartnership
  • PartnersRajkumar Vishandas Nandwani, Padma Vinod Talreja, Amar Vinod Talreja, Atmaram Budhomal Talreja, Tejpal Bhagatsingh Ailsinghani, Haina Rajkumar Nandwani, Vinod Atmaram Talreja
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

46 months past promisethis monthRegisteredDec 2018PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Dec 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed25 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building DNA130000
Building ENA120000
Building ANA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 17 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Building D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed125

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots125
Closed/Covered74
Open Space51
BuildingClosed/CoveredOpen SpaceTotal
Building D221739
Building E221739
Building A301747

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13408.0
Proposed, not sanctioned13,408 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRajiv gandhi infoctech park hinjewadi pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnil S. Saykar
EngineerM/s. G. A. Bhilare Consultants Pvt. Ltd.
PartnerRole in project
Trimurti Development Company-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Jan 2023

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: A Bldg Society Formation.pdf17 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DocScanner 20-Jan-2023 10-42 am.pdf20 Jan 2023
Form 2AFile: RERA 2A.pdf6 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA 2A.pdf6 May 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: D BUILDING COMPLETION_compressed.pdf6 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: E BUILD-converted.pdf6 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: D BUILD-converted.pdf6 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA PHASE 2-compressed.pdf28 Aug 2019
Certificates of CA (Form 5)File: RERA Certificate (1).pdf28 Aug 2019
Form 2AFile: Form 2A Rera 1.pdf9 Apr 2019
Certificates of CA (Form 5)File: Form 5_Phase 2 TDC Certificate.pdf9 Apr 2019
Building plan approvalFile: IOD Rera.pdf4 Dec 2018
Building Plan Approval (IOD)File: IOD Rera.pdf4 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Letter.pdf4 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: TRIMURTI_ARCHITECT CERTIFICATE_FORM 1.pdf1 Dec 2018
Certificates of CA (Form 3)File: Rera Certificate.pdf1 Dec 2018
Declaration in FORM BFile: Declaration B.pdf26 Nov 2018
Proforma of Allotment letterFile: Agreement.pdf21 Nov 2018
Layout approvalFile: Layout trim.pdf17 Nov 2018
PAN CardFile: TDC PAN.pdf17 Nov 2018
Copy of the legal title reportFile: Title trimurti.pdf17 Nov 2018
Details of encumbrancesFile: TDC DOC.pdf17 Nov 2018
Copy of Layout Approval (in case of layout)File: Layout trim.pdf17 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: NA order trim.pdf17 Nov 2018
OtherFile: EC trim.pdf17 Nov 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Elina Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Next to VIBGYOR School13,700+ in Pune

2 kmElina Phase 2Completed 152Lapsed / revoked 47Other 112Dot size: filed unitsN

Filed coordinates, straight-line distance. 311 registered projects within 2 km.

Builder: Trimurti Development Company

Trimurti Development Company has 2 registrations on MahaRERA, including Elina Phase 1 and Elina Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Elina Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Elina Phase 2 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Elina Phase 2?

The registered promoter entity is Trimurti Development Company, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Elina Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Elina Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Elina Phase 2?

The professionals named in the filing: Architect: Anil S. Saykar; Engineer: M/s. G. A. Bhilare Consultants Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Elina Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Elina Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Elina Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.