Home / Browse projects / Pune, Maharashtra / ELINA LITE

Completed Litigation declared Others project

ELINA LITE

By CHAPHALKAR KARANDIKAR DEVELOPERS

RG-MH-60853 · RERA P52100035129 · Last updated on MahaRERA portal: 31 Oct 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2026Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
13 of 166Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

ELINA LITE is a Others project by CHAPHALKAR KARANDIKAR DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100035129 on 10 May 2022. The registration is recorded completed; possession was promised by 31 Jan 2026. The completion date has moved by 7 months from the original filing. 153 of the 166 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameELINA LITE
  • TypeOthers
  • Location
    • S M Ghule Road
    • Off NIBM
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035129
  • ReraGenie IDRG-MH-60853

Builder

  • NameCHAPHALKAR KARANDIKAR DEVELOPERS
  • Entity typePartnership
  • PartnersVikaram Vilas Karandikar, Pushkaraj Arvind Chaphalkar
  • Other registrations9 more →
  • Completed2 of 10
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredMay 2022First promiseJun 2025Revised toJan 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 May 2022
  • Promised completion31 Jan 2026
  • Revised completionRevised to 31 Jan 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed94 files

Current status

92%153 of 166 units booked
100.0%Work done, per cost certificate

Figures as on 31 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A WING B WING CNA15141579166

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

WING A WING B WING C: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,488 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 May 2025
LandownerVillageDistrict
Subahu Kirit ShahPune (M Corp.)Pune
Ashit Vipin SanghaviPune (M Corp.)Pune
Brajesh Deo SInghPune (M Corp.)Pune
ACROPOLIS DESIGN PROMOTERS LLPPune (M Corp.)Pune
TRICON INFRA BUILDTECHPVT LTDPune (M Corp.)Pune
GENIE INFOTECH PVT LTDPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI15192.0
Proposed, not sanctioned4,743 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDeccan Gymkhana
Estimated costRs 44.92 cr
Cost incurredRs 44.92 cr
Work done100.0%
BuildingWingEstimatedIncurred
WING A WING B WING CNARs 44.92 crRs 44.92 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPINNAC AECL PVT LTD
EngineerPrashant Doke
Chartered AccountantP S Achaliya and Co
Chartered AccountantKhire Khandekar and Kirloskar
Chartered AccountantJPNR & ASSOCIATES
PartnerRole in project
CHAPHALKAR KARANDIKAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30062501876Jun 2025 → Jan 2026

Reason as filed by the promoterThe unforeseen reason i.e. we have applied for final Fire NOC for lift installation and final Fire work. But suddenly the change in authorities and the govt appointed local officer for the NOC of the LIFT the appointment is in the period of June 2025. And we are waiting for their NOC. After receipt of the NOC we can forward the process of Occupancy Certificate.so considering interest of allottee and work not to be get hampered we are requesting the extension.

Litigation declared2

CaseCourtStatus
1299/2022Honble Civil Judge Senior Division Court PuneAppearance and filing of reply
577/2021Honble Add Collector Punefinal order passed appeal rejected

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000177889Smt. Shantabai Dattu TarwadeM/s. Chaphalkar Karandikar Developers Through its Partner Mr. Vikram Vilas Karandikar07/12/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1- Elina Lite Sep 2025.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2- Elina Lite Sep 2025.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3 Q1 2025-26_compressed.pdf31 Oct 2025
Occupational CertificateFile: Occupancy Certificate Elina Lite Plot D .pdf31 Oct 2025
Withdrawal Update Form 1File: Form 1 Q1 2025-26.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 Q1 2025-26_compressed.pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3 Q1 2025-26_compressed.pdf29 Oct 2025
Form 5 (FY 2024-2025)File: Form 5- Elina Lite24-25.pdf24 Oct 2025
Building plan approvalFile: PLAN 1_6.pdf4 Feb 2025
Building plan approvalFile: PLAN 2_6.pdf4 Feb 2025
Building plan approvalFile: PLAN 3_6.pdf4 Feb 2025
Building plan approvalFile: PLAN 4_6.pdf4 Feb 2025
Building plan approvalFile: PLAN 5_6.pdf4 Feb 2025
Building plan approvalFile: PLAN 6_6.pdf4 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1_6.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2_6.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3_6.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 4_6.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 5_6.pdf4 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 6_6.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Elina Lite Q3.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Elina Lite Q3.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Elina Lite Q3.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory Elina Lite Q3.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CKD - ELINA LITE RERA FORM 5 (2023-2024).pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ELINA LIVA Q2.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ELINA LITE Q2.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ELINA LITE Q2.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: CKD Elina Lite Disclosure of Inventory Q2 24-25.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 24-25.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 24-25.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 24-25.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2023-24.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 23- 24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 23-24.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Q 3.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2023-24.PDF1 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-12-2022.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-03-2023.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-092023.pdf6 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Elina Lite 22-23.pdf6 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory 3.pdf6 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Elina Lite.pdf22 Nov 2023
Building plan approvalFile: PLAN 01_06.pdf1 Sep 2023
Building plan approvalFile: PLAN 02_06.pdf1 Sep 2023
Building plan approvalFile: PLAN 03_06.pdf1 Sep 2023
Building plan approvalFile: PLAN 04_06.pdf1 Sep 2023
Building plan approvalFile: PLAN 05_06.pdf1 Sep 2023
Building plan approvalFile: PLAN 06_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 01_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 02_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 03_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 04_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 05_06.pdf1 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 06_06.pdf1 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: CC 01 SEPT 2023.pdf1 Sep 2023
Other - LegalFile: Self Declaration litigation - Elina Lite.pdf28 Jul 2023
Other - LegalFile: Add collector order-Appeal no 5772021 tarwade and others.pdf28 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Elina Lite 2.pdf10 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Elina Lite 21-22.pdf23 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Elina Lite.pdf20 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Declaration of Bank account Elina Lite.pdf20 Jan 2023
Other - LegalFile: SELF DECLARATION - ELINA LITE 'D'.pdf20 Dec 2022
Building plan approvalFile: 01-04-.pdf16 Nov 2022
Building plan approvalFile: 02-04-.pdf16 Nov 2022
Building plan approvalFile: 03-04-.pdf16 Nov 2022
Building plan approvalFile: 04-04-.pdf16 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: 01-04-.pdf16 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: 02-04-.pdf16 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: 03-04-.pdf16 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: 04-04-.pdf16 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: C C Rev1 .pdf16 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf6 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200236767543_For_Asset_Based_Search_06_05_2022_16_13_09_077.pdf6 May 2022
Copy of the legal title reportFile: Circular 28 _ FORM A.pdf2 May 2022
Declaration in FORM BFile: 1 Declaration FORM B - Revised.pdf2 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA FORM 3 REGISTRATION.pdf2 May 2022
Layout approvalFile: Layout_1 Plan.pdf29 Apr 2022
Layout approvalFile: Layout_2.pdf29 Apr 2022

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 7 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELINA LITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Off NIBM13,700+ in Pune

2 kmELINA LITECompleted 59Lapsed / revoked 23Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 147 registered projects within 2 km.

Builder: CHAPHALKAR KARANDIKAR DEVELOPERS

CHAPHALKAR KARANDIKAR DEVELOPERS has 10 registrations on MahaRERA, including ASHOKBAN and SHASHI APARTMENTS. Its filings disclose 14 earlier MahaRERA projects: declares 8 of 9 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ELINA LITE is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELINA LITE?

The registered promoter entity is CHAPHALKAR KARANDIKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELINA LITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ELINA LITE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ELINA LITE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELINA LITE?

The professionals named in the filing: Architect: PINNAC AECL PVT LTD; Engineer: Prashant Doke; Chartered Accountant: P S Achaliya and Co; Chartered Accountant: Khire Khandekar and Kirloskar; Chartered Accountant: JPNR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELINA LITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELINA LITE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELINA LITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.