ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ELATE

Registered No litigation declared Others project

ELATE

By M/s. Guddwill RVN Spaces LLP

RG-MH-19457 · RERA P52100077745 · Last updated on MahaRERA portal: 18 Apr 2026

Source: official MahaRERA filing

Red flags

  • Rs 10.00 crore secured on the land, in favour of STATE BANK OF INDIA

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Slabs of Super Structure, 70%
121 of 156Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 163 documents Report an error

ELATE is a Others project by M/s. Guddwill RVN Spaces LLP in Pune, Maharashtra, registered with MahaRERA as P52100077745 on 25 Oct 2024. Possession is promised by 31 Oct 2027. 35 of the 156 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameELATE
  • TypeOthers
  • Location
    • -
    • UNDRI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077745
  • ReraGenie IDRG-MH-19457

Builder

  • NameM/s. Guddwill RVN Spaces LLP
  • Entity typePartnership
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2024PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2024
  • Promised completion31 Oct 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed163 files

Current status

22%35 of 156 units booked
32.1%Work done, per cost certificate

Figures as on 18 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER ANA15141524156

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

TOWER A: 47% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed258

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots258
Closed/Covered258

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,121 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofSTATE BANK OF INDIA
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on5 Jan 2026
LandownerVillageDistrict
M/S. MALA ESTATES & INVESTMENTSkondhwa khurdPune
SAI DEVELOPMENTSkondhwa khurdPune
MAJOR MOHANLAL BAJAJkondhwa khurdPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI13798.06
Proposed, not sanctioned13,798 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, RAINBOW PLAZA, SHOP NO. 22, RAHATANI PIMPLE SAUDAGAR, PUNE, MAHARASHTRA, PIN 411017
Estimated costRs 42.74 cr
Cost incurredRs 13.74 cr
Work done32.14%
BuildingWingEstimatedIncurred
TOWER ANARs 38.47 crRs 13.74 cr
-NARs 4.27 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParvez jamadar & associates
EngineerMillind N Chaudhari
Chartered AccountantBhushan Kohinkar & Assocaiate
Chartered AccountantManoj R. Jain For SPCM & Associates
Chartered AccountantRohan R Nahar
PartnerRole in project
M/s. Guddwill RVN Spaces LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2027

Documents filed163

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 163 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Layout-1-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-2-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-3-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-4-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-5-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-6-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-7-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-8-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-9-12.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-10-12_compressed.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-11-12_compressed.pdf18 Apr 2026
Layout approvalFile: Sanctioned Plans-12-12.pdf18 Apr 2026
Withdrawal Update Form 1File: form 1- Architect Certificate - Guddwill.pdf17 Apr 2026
Withdrawal Update Form 2File: Form 2_final.pdf17 Apr 2026
Withdrawal Update Form 3File: Form 3 (6).pdf17 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A Elate 24-25.pdf25 Feb 2026
Withdrawal Update Form 1File: form 1- Architect Certificate - Guddwill.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Jan 2026
Withdrawal Update Form 3File: form-3 CA Certificate - Guddwill.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf18 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf18 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Elate 24-25.pdf11 Oct 2025
Withdrawal Update Form 1File: Form 1undri.pdf8 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf8 Oct 2025
Withdrawal Update Form 3File: Form 3 (1) (1).pdf8 Oct 2025
Form 1File: FORM 1 ELATE DEC 24.pdf13 Aug 2025
Form 2File: FORM 2 ELATE DEC 2024.pdf13 Aug 2025
Form 3File: FORM 3 DEC 24_compressed.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Elate Dec 24.pdf13 Aug 2025
Form 1File: Form 1 Elate.pdf13 Aug 2025
Form 2File: Form 2Elate.pdf13 Aug 2025
Form 3File: Form 3 Elate.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Inventory sold unsold_undri.pdf13 Aug 2025
Withdrawal Update Form 1File: Form 1undri.pdf13 Aug 2025
Withdrawal Update Form 1File: Form 1undri.pdf13 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf13 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf13 Aug 2025
Withdrawal Update Form 3File: Form 3 (1) (1).pdf13 Aug 2025
Withdrawal Update Form 3File: Form 3 (1) (1).pdf13 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1undri.pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1) (1)_compressed.pdf28 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (10).pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: Inventory details undri.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: ELATE Inventory sold unsold.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Elate.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Elate.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2Elate.pdf16 Apr 2025
Deviation Report with respect to model copy of AgreementFile: AFS Elate Deviation_11zon.pdf1 Mar 2025
Proforma of Agreement for saleFile: Final draft AFS revised ELATE_11zon.pdf1 Mar 2025
Layout approvalFile: 1-8.pdf5 Feb 2025
Building plan approvalFile: 2-8.pdf5 Feb 2025
Building plan approvalFile: 3-8.pdf5 Feb 2025
Building plan approvalFile: 4-8.pdf5 Feb 2025
Building plan approvalFile: 5-8.pdf5 Feb 2025
Building plan approvalFile: 6-8.pdf5 Feb 2025
Building plan approvalFile: 7-8.pdf5 Feb 2025
Building plan approvalFile: 8-8.pdf5 Feb 2025
Layout approvalFile: 1-8.pdf5 Feb 2025
Building plan approvalFile: 2-8.pdf5 Feb 2025
Building plan approvalFile: 3-8.pdf5 Feb 2025
Building plan approvalFile: 4-8.pdf5 Feb 2025
Building plan approvalFile: 5-8.pdf5 Feb 2025
Building plan approvalFile: 6-8.pdf5 Feb 2025
Building plan approvalFile: 7-8.pdf5 Feb 2025
Building plan approvalFile: 8-8.pdf5 Feb 2025
Copy of Layout Approval (in case of layout)File: 1-8.pdf5 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC (2).pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 2-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 3-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 4-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 5-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 6-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 7-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 8-8.pdf5 Feb 2025
Copy of Layout Approval (in case of layout)File: 1-8.pdf5 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC (2).pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 2-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 3-8.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 4-8.pdf5 Feb 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
WoodshireP52100055731Mouje Urse, Pune89Apr 2024OngoingDec 2025Not delivered

How this compares with Pune

22%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmELATECompleted 76Lapsed / revoked 30Other 56Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: M/s. Guddwill RVN Spaces LLP

M/s. Guddwill RVN Spaces LLP has 1 registration on MahaRERA, including ELATE. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ELATE is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELATE?

The registered promoter entity is M/s. Guddwill RVN Spaces LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELATE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELATE?

The professionals named in the filing: Architect: Parvez jamadar & associates; Engineer: Millind N Chaudhari; Chartered Accountant: Bhushan Kohinkar & Assocaiate; Chartered Accountant: Manoj R. Jain For SPCM & Associates; Chartered Accountant: Rohan R Nahar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELATE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.