ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / EL REGALO

Registered No litigation declared Others project

EL REGALO

By MAHESH REALTORS

RG-MH-50749 · RERA P52100015370 · Last updated on MahaRERA portal: 19 Jun 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
17 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 90%
2Complaints at MahaRERAon this registration
Jump to the 212 documents Report an error

EL REGALO is a Others project by MAHESH REALTORS in Pune, Maharashtra, registered with MahaRERA as P52100015370 on 20 Feb 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameEL REGALO
  • TypeOthers
  • Location
    • SURVEY NO 15/27A/1
    • 15/27A/2
    • 15/27D
    • UNDRI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015370
  • ReraGenie IDRG-MH-50749

Builder

  • NameMAHESH REALTORS
  • Entity typePartnership
  • PartnerRJENDRA RAMBHAU CHINCHOLE

Key dates

this monthRegisteredFeb 2018First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Feb 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed212 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA130000
B BUILDINGNA140000
AMENITYNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 90%.

A BUILDING72%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B BUILDING89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
AMENITY9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed372

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots372
Closed/Covered95
Open Space277
BuildingClosed/CoveredOpen SpaceTotal
A BUILDING20230250
B BUILDING52052
AMENITY234770

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
VASANT RAGHUNATH KADUNDRIPune
HIRABAI RAGHUNATH KADUNDRIPune
VISHAL ARUN KADUNDRIPune
ALKA PRAKASH KAKADEWadgaon-shindePune
ASHOK RAGHUNATH KADUNDRIPune
TANAJI LAXMAN KADUNDRIPune

Approvals and building plan

Permissible FSI7618.99
Proposed, not sanctioned5,999 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKarve Nagar, Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMAN INAMDAR
EngineerBHANUVILASPUNDLIKBHAVSAR
PartnerRole in project
MAHESH REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018428Dec 2023 → Dec 2026

Reason as filed by the promoterWe have finalized lift elevator contract with M/s T K Elevators Pvt ltd and mechanical parking contract with the M/s Klaus mechanical parking Pvt Ltd . According to information provided by the said vendors, critical components of their equipment’s have been manufactured in China. Government of China have implemented strict zero covid policy As per the said policy, manufacturing plants have been shut down for many months at a stretch. Thus, our vendors have invoked “force de majeure” clause in the agreement and expressed their inability to provide material as per the agreed timeline. As a resul

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12602642Vickysteven Martin StevenMAHESH REALTORS07/05/2026
CC12603655Vicky Martin StevenMAHESH REALTORS13/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jun 2025

Documents filed212

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 212 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MR form 1.pdf19 Jun 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: El Regalo Completion Certificate.pdf19 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 june 2024_compressed.pdf18 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sup 2024_compressed.pdf18 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dce 2024_compressed.pdf18 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 mar 2025_compressed.pdf18 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 March 2024_compressed.pdf18 Jun 2025
Certificates of CA (Form 3)File: M R March 2025_compressed.pdf18 Jun 2025
Certificates of CA (Form 3)File: M R Dec 2024_compressed.pdf18 Jun 2025
Certificates of CA (Form 3)File: M R Sept 2024_compressed.pdf18 Jun 2025
Certificates of CA (Form 3)File: M R June 2024_compressed (1).pdf18 Jun 2025
Certificates of CA (Form 3)File: M R March 2024_compressed.pdf18 Jun 2025
Certificates of CA (Form 3)File: M R Dec 2023_compressed.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec2023.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Mar2024.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F 2 june2024.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Sep2024.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec2024.pdf18 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Mar2025.pdf18 Jun 2025
Disclosure of sold/ booked inventoryFile: Mr inventory A_merged_compressed.pdf18 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F 2A 2023-24.pdf18 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Mr form 5.pdf18 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: COMENCEMENT CERTIFICATE -2021.pdf7 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: El Regalo CC 2022.pdf7 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MR F1 june.pdf7 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MR F1 March.pdf7 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 sup.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2021(3)Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(1)Form 2 - Copy.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(2)Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(3)Form 2 -.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(4)Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(1) Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(2) Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(3) Form 2.pdf7 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(3) Form 2.pdf7 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RE F2A 2019-20.pdf7 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RE F2A 2020-21.pdf7 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RE F2A 2021-22.pdf7 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RE F2A 2022-23.pdf7 Jan 2024
Disclosure of sold/ booked inventoryFile: RE Disclosure of sold_ booked inventory_page-0001 (1).pdf7 Jan 2024
Certificates of CA (Form 3)File: RE F3 June 2023.pdf7 Jan 2024
Certificates of CA (Form 3)File: RE F3 March2023.pdf7 Jan 2024
Certificates of CA (Form 3)File: RE F3 sup 2023.pdf7 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Signed.pdf7 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RE F 1 Mar 2023.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RE F 1 June 2023.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RE F 1 June 2023.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RE F 1 Sup 2023.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2018 Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2019 Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2020 Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2021(1)Form 2 -.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2021(2)Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2021(2)Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2021(3 )Form 2 -.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(1)Form 2 - Copy.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(2)Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(3)Form 2 -.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(4)Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2022(4)Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(1) Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(2) Form 2.pdf25 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE_2023(3) Form 2.pdf25 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RE F2A 2019-20.pdf25 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RE F2A 2021-22.pdf25 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RE F2A 2022-23.pdf25 Dec 2023
Disclosure of sold/ booked inventoryFile: SoldUnsold inventory Wing AB andAmenity.pdf25 Dec 2023
Certificates of CA (Form 3)File: RE F3 March2023.pdf25 Dec 2023
Certificates of CA (Form 3)File: RE F3 June 2023.pdf25 Dec 2023
Certificates of CA (Form 3)File: RE F3 sup 2023.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2018_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2019_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2020_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 1 2021_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2 2021_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2022 1_compressed.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mr F1 2022 2_compressed.pdf27 Nov 2023
Certificates of CA (Form 3)File: MR F3 2018.pdf27 Nov 2023
Certificates of CA (Form 3)File: Mr F3 2019.pdf27 Nov 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EL REGALO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near UNDRI13,700+ in Pune

2 kmEL REGALOCompleted 97Lapsed / revoked 30Other 97Dot size: filed unitsN

Filed coordinates, straight-line distance. 224 registered projects within 2 km.

Builder: MAHESH REALTORS

MAHESH REALTORS has 1 registration on MahaRERA, including EL REGALO. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EL REGALO is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EL REGALO?

The registered promoter entity is MAHESH REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EL REGALO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EL REGALO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EL REGALO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EL REGALO?

The professionals named in the filing: Architect: AMAN INAMDAR; Engineer: BHANUVILASPUNDLIKBHAVSAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EL REGALO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EL REGALO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EL REGALO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.