Red flags
- Litigation declared, 1 case
- 8 complaints at MahaRERA
- Completion date moved by 90 months
- 5 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EKTA GREENVILLE PHASE 2 WING O , P , Q AND R is a Residential / Group Housing project by EKTA HOUSING PRIVATE LIMITED in Nashik, Maharashtra, registered with MahaRERA as P51600000685 on 20 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 90 months from the original filing. 104 of the 128 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameEKTA GREENVILLE PHASE 2 WING O , P , Q AND R
- TypeResidential / Group Housing
- Location
- PATHARDI
- Nashik
- 422010
- Pincode422010
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600000685
- ReraGenie IDRG-MH-00743
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Jul 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2019)
- Buildings4 building records
- Documents filed102 files
Current status
Figures as on 5 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING O | NA | 10 | 0 | 32 | 0 | 32 |
| WING P | NA | 10 | 0 | 32 | 0 | 32 |
| WING Q | NA | 10 | 0 | 32 | 0 | 32 |
| WING R | NA | 10 | 0 | 32 | 0 | 32 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 95%.
WING O90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING P90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING Q80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 55% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
WING R60%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
Progress on shared amenities33
As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 86% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | Yes | 80% |
| Gazebo with size 8 feet x 8 feet for people to sit and relax | Yes | 65% |
| Children Play Area with playing equipments | Yes | 100% |
| CHESS and CARDS area will be in CLUB HOUSE | Yes | 100% |
| PAVED SITTING AREA | Yes | 85% |
| CLUB HOUSE with gymnasium and games room with squash court and steam facility | Yes | 100% |
| GUARD HOUSE with separate Entry and Exit | Yes | 100% |
| GYMNASIUM with area of approx 62 sqm with fitness equipment will be in CLUB HOUSE | Yes | 100% |
| KIDS POOL of size 4 m x 4m | Yes | 77% |
| MUTIPURPOSE COURT to play Basketball and Badminton | Yes | 100% |
| NET CRICKET with cricket pitch enclosed with net around | Yes | 100% |
| PARTY LAWN with lush green grass for party functions get together | Yes | 100% |
| PATHWAY of 5 feet in width for jogging and walking through the landscape area | Yes | 91% |
| SNOOKER TABLE area will be in Club House | Yes | 100% |
| SQUASH COURT will be in CLUB HOUSE | Yes | 100% |
| SWIMMING POOL of size 11 m x 5 m | Yes | 67% |
| TABLE TENNIS area will be in Club House | Yes | 100% |
| TEMPLE with size of 8 feet x 8 feet | Yes | 100% |
| TREE PITS WITH SEATS AROUND | Yes | 90% |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING O | 1 | 8 | 9 |
| WING P | 1 | 7 | 8 |
| WING Q | 1 | 10 | 11 |
| WING R | 1 | 0 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UMESH BAGUL |
| Architect | Samir Desai |
| Engineer | JW CONSULTANTS LLP |
| Engineer | Amit Parshuram Kamble |
| Engineer | SACHIN S KARAWADE |
| Chartered Accountant | Vikas Mangal |
| Chartered Accountant | Manoj Chaturvedi |
| Partner | Role in project |
|---|---|
| EKTA HOUSING PRIVATE LIMITED | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn the above said project, there are 4 wings O,P, Q & R and we have obtained Occupation Certificate for Wing O & P. Now we are applying for extension date for Q & R wing. In the Q & R Wing there are 24 Registered flats and we have obtained consent of 51% allottee i.e. 13 allottees. Due to non availability of material and labour for the constructions of the Project and outbreak of novel Corona Virus Pandemic and imposition of the Lock down in entire State of Maharashtra which caused delay in Project. Due to non availability of material and labour for the constructions of the Project and outbrea
Reason as filed by the promoterDue to scarcity of availability of the resources and also some technical reasons.
Reason as filed by the promoterReply Annexed.
Reason as filed by the promoterWe hereby apply for extension u/s 7(3) for the registered project naming Ekta Greenville Phase II bearing MahaRERA registration No. P51600000685 comprising of Four wings i.e. O,P,Q and R, out of the Two wings i.e. O and P have received O.C on 06th January, 2020. The O.C still pending for wings Q and R, and while the Buildings are almost complete, application for O.C is pending only for some technical issue. The current registration expired on 30.09.2022, and we are applying u/s 7(3) for the extension till 30.09.2023. As prescribed under circular No. 07/2019 dated 8th Feb, 2019 the details of c
Reason as filed by the promoterShortage of sand and skilled labour
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1197/2016 | State Commission Maharashtra Mumbai | PENDING |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC001000000000033 | BAHULA PARIKH | EKTA HOUSING PVT LTD | 20/12/2017 |
| CC001000000000012 | Sudesh Sharma | VIVEK MOHANANI | 24/10/2017 |
| CC001000000000110 | MOHINESH ADVANI | EKTA HOUSING PVT. LTD. | 26/07/2019 |
| CC001000000020214 | Ranjana Devraj Balisti | Ekta Housing Private Limited | 02/12/2021 |
| CC001000000020263 | ASHOK BANDU SALVE | EKTA HOUSING PVT LTD | 11/05/2022 |
| CC001000000060327 | Anoop Murildhar Katare | Ekta Housing Private Limited | 08/06/2023 |
| CC001000000080349 | Kailash Gupta | M/s. Ekta Housing Pvt. Ltd. Through its Promoter Mr. Vivek A. Mohanan | 11/09/2023 |
| CC12502203 | Sunil Vasant Shinde | EKTA HOUSING PRIVATE LIMITED | 02/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 6 Jan 2020
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: SIGNED GREENVILLE PHASE II FORM 1 WING Q R TILL 31-3-2026 NEW FORMAT.pdf | 5 May 2026 |
| Form 2File: SIGNED EKTA GREENVILLA PHASE II FORM 2 MARCH 26.pdf | 5 May 2026 |
| Form 3File: SIGNED FORM 3 Greenville Phase II 31_03_2026.pdf | 5 May 2026 |
| Disclosure of Sold and Booked InventoryFile: QUARTERLY SOLD AND UNSOLD 31_03_2026.pdf | 5 May 2026 |
| Form 1File: EW GREENVILLE PHASE II FORM 1 DEC 25.pdf | 20 Jan 2026 |
| Form 2File: Form 2EKTA GREENVILLE PHASE 2.pdf | 20 Jan 2026 |
| Form 3File: signed FORM 3 GV P II.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD EKTA GREENVILLE PHASE II.pdf | 20 Jan 2026 |
| Form 1File: EW GREENVILLE PHASE II FORM 1 WING Q& R TILL 30-09-2025.pdf | 17 Oct 2025 |
| Form 2File: greenville phase 2 form 2 Sep 2025.pdf | 17 Oct 2025 |
| Form 3File: signed FORM 3 GV P II.pdf | 17 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: EKTA GREENVILLE PHASE 2 SOLD UNSOLD.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 EKTA GREENVILLE PHASE II 31_03_25.pdf | 29 Sep 2025 |
| Form 1File: EKTA GREENVILLE PHASE II FORM 1 30-06-2025.pdf | 18 Jul 2025 |
| Form 2File: FORM 2 EKTA GREENVILEE PHASE 2.pdf | 18 Jul 2025 |
| Form 3File: signed FORM 3 GV P II 30_06_2025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD & UNSOLD Greenville phase 2.pdf | 18 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: EKTA GREENVILLE SOLD UNSOLD INVENTORY.pdf | 22 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II FORM 1 WING Q R 31_12_2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: GV P II_compressed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EKTA GREENVILLE II.PDF | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II FORM 1 WING Q R TILL 30_09_24.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II FORM 1 WING Q R TILL 30_09_24 R1.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30062024 EW GREENVILLE PHASE II Form 2 ENGINEER CERTIFICATE 30_09_24.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: GV P II SOLD UNSOLD.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta greenville phase 2.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 GV P II_30062024.pdf | 8 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: EKTA GREENVILLE- OPQR WINGS Quaterly Inventory Updates.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II FORM 1 WING Q R TILL 31-03-2024.pdf | 3 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II Form 2 ENGINEER CERTIFICATE 31032024.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: EW GREENVILLE Q R FORM 2A Quality Assurance Certificate 31-3-2024.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: SIGNED Form 3 GV P II 31-03-2024.pdf | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: EKTA GREENVILLE- OPQR WINGS Quaterly Inventory Updates.pdf | 16 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II FORM 1 WING Q and R TILL 31-12-2023.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: GREENVILLE-02012024.pdf | 17 Jan 2024 |
| OtherFile: construction schedule Qand R.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenville Phase II.pdf | 15 Dec 2023 |
| Proforma of Agreement for saleFile: AFS Ekta Greenville Phase 2 Wing OPQR.pdf | 8 Dec 2023 |
| Certificates of CA (Form 3)File: Signed Form 3 Greenville Phase 3 Sep 2023.pdf | 30 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: EKTA GREENVILLE- OPQR WINGS Quaterly Inventory Updates.pdf | 23 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II Form 1 ARCH CERTIFICATE 30-9-2023.pdf | 17 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II Form 2 ENGINEER CERTIFICATE 30-9-2023.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: greenville phase II.pdf | 6 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GREENVILLE PHASE II.pdf | 3 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: 01072023-GREENVILLE OPQR.pdf | 16 Jul 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: GREENVILLE Phase II O TO R.pdf | 12 Jun 2023 |
| OtherFile: Ekta Greenville phase2.pdf | 2 May 2023 |
| Disclosure of sold/ booked inventoryFile: GREEN VILLE PHASE II.pdf | 6 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH GREENVILLE PHASE II.pdf | 4 Mar 2023 |
| OtherFile: Greenville Phase 2.pdf | 11 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 EKTA GREENVILLE PHASE II.pdf | 10 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 EKTA GREENVILLE PHASE II.pdf | 10 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW GREENVILLE PHASE II Form 2 ENGINEER CERTIFICATE 31-12-22.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Greenville Phase 2.pdf | 4 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Greenville Phase 2.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A QUALITY ASSURANCE GREENVILLE PHASE II 1-01-2022.pdf | 4 Feb 2023 |
| CERSAI detailsFile: Housing.pdf | 4 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Housing.pdf | 4 Feb 2023 |
| Proforma of Agreement for saleFile: Allottment Letter and Agreement - Greenville Ph II.pdf | 4 Feb 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: GREENVILLE PHASE II.pdf | 23 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: GREENVILEE O P Q R.pdf | 15 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Greenville Phase 2.pdf | 1 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: GREEN VILLE PHASE II.pdf | 9 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: GREENVILLE PHASE II OPQR.pdf | 6 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: greenville Phase II.pdf | 5 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: OPQR GREENVILLE PHASE II.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GREENVILLE PHASE II.pdf | 30 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: ekta green ville phase II.pdf | 9 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Disclouser of sold inventory of Oand P wing.pdf | 25 Aug 2021 |
| OtherFile: Nashik Club OC.pdf | 25 Aug 2021 |
| Declaration about Commencement CertificateFile: Declaration of Commencement certificate.pdf | 3 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certifcate for 2020-2021.pdf | 27 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: DIsclosure of Sold Inventory.pdf | 27 Jul 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 22 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certifcate for 2020-2021.pdf | 22 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Greenville Phase-2.pdf | 10 Feb 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Nasik OC.pdf | 6 Jan 2020 |
| Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf | 3 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Greenville Phase II.pdf | 16 Nov 2019 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| EKTA GREENVILLE WING F,G,H,L,M,N | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 192 | Completed | Mar 2017 | Late, Jul 2017 |
| EKTA CALIFORNIA WING A,B,C,D,E | Survey No 9 Hissa No 1 Part Undri Pune | 120 | Completed | Mar 2015 | Late, Jul 2015 |
| EKTA GREENVILLE ROW HOUSES AND VILLAS | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 20 | Completed | May 2014 | Late, Jul 2017 |
| EKTA GREENVILLE ROW HOUSE NO 29 AND 30 | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 2 | Completed | Jul 2012 | Jul 2012 |
| EKTA GREENVILLE WING A, B, C, D, E, K | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 192 | Completed | Apr 2012 | Late, Jul 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep EKTA GREENVILLE PHASE 2 WING O , P , Q AND R on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik4,100+ in Nashik
Filed coordinates, straight-line distance. 137 registered projects within 2 km.
SHREE SATYANARAYAN ROONGTA FORUM
ROONGTA HOMES LLP
LIFE 360
VELOCITY INFRA PROJECTS
ARYAN'S LIFEONE
SHREE ARYAN BUILDERS AND DEVELOPERS
SUNFLOWER CITY
DEEPAK KALYANJI CHANDE
Laxminarayan Heaven
Sahajanand Builders And Developers
SWASTIK MANGAL APARTMENT
SHREEMANGAL CONSTRUCTION
See every Nashik project, with the district possession charts
Builder: EKTA HOUSING PRIVATE LIMITED
EKTA HOUSING PRIVATE LIMITED has 9 registrations on MahaRERA, including EKTA GREENVILLE PHASE 1 WING I AND J and EKTA GREENVILLE PHASE 2 WING O , P , Q AND R. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if EKTA GREENVILLE PHASE 2 WING O , P , Q AND R is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
The registered promoter entity is EKTA HOUSING PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1990PTC058279 and GSTIN 27AAACE2460K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
The professionals named in the filing: Architect: UMESH BAGUL; Architect: Samir Desai; Engineer: JW CONSULTANTS LLP; Engineer: Amit Parshuram Kamble; Engineer: SACHIN S KARAWADE; Chartered Accountant: Vikas Mangal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EKTA GREENVILLE PHASE 2 WING O , P , Q AND R?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.