Eklavya Skylark
By Eklavya Builders Private Limited
RG-MH-01465 · RERA P52100002715 · Last updated on MahaRERA portal: 14 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 114 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Eklavya Skylark is a Residential / Group Housing project by Eklavya Builders Private Limited in Rajaram Patil Nagar, 411014, registered with MahaRERA as P52100002715 on 4 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 114 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameEklavya Skylark
- TypeResidential / Group Housing
- Location
- Grant Road
- Rajaram Patil Nagar
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100002715
- ReraGenie IDRG-MH-01465
Builder
- NameEklavya Builders Private Limited
- Entity typeCompany
- Managing DirectorSantosh Dilip Ustoorikar
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2018)
- Buildings1 building record
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Skylark | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Skylark: 95% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 14 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Siddharth Subhash Harishchandrakar |
| Partner | Role in project |
|---|---|
| Eklavya Builders Private Limited | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRevised Sanction received for 6th Floor on 28/06/2019 CC/0692/19, Project was delayed due to unavailability of construction material and construction workers initially and then by Global Pandemic. However now things are recovered and construction is going on in full swing. Customers well informed and required consent sought.
Reason as filed by the promoterReceived Commencement dated 19/05/2018 for 5th & 6th floor on 13/06/2018. Decision regarding loading of TDR on projects adjoining 6m & 9m roads pending at Municipal corporation.
Reason as filed by the promoterWe have completed 98% of Project. Only Finishing work is pending. We require some time for completion of pending work , form Association and complete Handover as well as Conveyance procedures
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000053916 | Pooja Rajkumar Sheti | Eklavya Builders Pvt. Ltd. | 24/01/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH Q4 24-25.pdf | 14 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer FORM 2 Q4 24-25.pdf | 14 Apr 2025 |
| Building plan approvalFile: 1 SKYLARK_compressed.pdf | 8 Nov 2024 |
| Building plan approvalFile: 2 SKYLARK_compressed.pdf | 8 Nov 2024 |
| Building plan approvalFile: 3 SKYLARK (1)_compressed.pdf | 8 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Annexure B.pdf | 8 Nov 2024 |
| Building Plan Approval (IOD)File: 1 SKYLARK_compressed.pdf | 8 Nov 2024 |
| Building Plan Approval (IOD)File: 2 SKYLARK_compressed.pdf | 8 Nov 2024 |
| Building Plan Approval (IOD)File: 3 SKYLARK (1)_compressed.pdf | 8 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Form 2A_compressed.pdf | 8 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5.pdf | 8 Nov 2024 |
| Declaration in FORM BFile: Form B Eklavya Skylark.pdf | 7 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Bank format A.pdf | 7 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of Interest Anup Joshi.pdf | 7 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of Interest Nikhil Botre.pdf | 7 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of Interest Santosh Ustoorikar.pdf | 7 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5.pdf | 7 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate FY 24-25 Q-1.pdf | 9 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexture.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold.pdf | 9 Oct 2024 |
| Declaration about Commencement CertificateFile: Form D Declaration about Comm Cert.pdf | 23 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Cert Form 1 Q-2 FY 23-24.pdf | 23 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Cert Form 1 Q-3 FY 23-24.pdf | 23 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Cert Form 1 Q-4 FY 23-24.pdf | 23 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate FY 23-24 Q-1.pdf | 23 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexture.pdf | 23 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Engineer.pdf | 23 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold.pdf | 23 May 2024 |
| Certificates of CA (Form 3)File: CA Form 3A Eklavya.pdf | 23 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022 Eklavya.pdf | 23 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023 Eklavya.pdf | 23 May 2024 |
| Declaration about Commencement CertificateFile: Declaration Format D .pdf | 1 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Architects Certificate.pdf | 1 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 5 FORM 2A ENGINEER .pdf | 1 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Declaration Sol and Unsold Inventory.pdf | 1 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200229288987_For_Asset_Based_Search_01_02_2022_17_49_07_229.pdf | 1 Feb 2022 |
| Certificates of CA (Form 3)File: Rera certificate-Eklavya Builders_compressed.pdf | 1 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - FY 18-19 final with sign.pdf | 1 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - FY 19-20 final with sign.pdf | 1 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - FY 20-21 final with sign.pdf | 1 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Certificate Small size form 1.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate - RERA.pdf | 26 Jul 2017 |
| Building plan approvalFile: IOC Letter.pdf | 25 Jul 2017 |
| Layout approvalFile: Layout Sanction.pdf | 25 Jul 2017 |
| Details of encumbrancesFile: Details of Encumbrances.pdf | 25 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Sanction.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOC Letter.pdf | 25 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf | 25 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter Draft.pdf | 25 Jul 2017 |
| Proforma of Allotment letterFile: Draft Agreement.pdf | 25 Jul 2017 |
| PAN CardFile: Eklavy Builders Pancard.pdf | 24 Jul 2017 |
| Copy of the legal title reportFile: Search Report.pdf | 24 Jul 2017 |
| Declaration in FORM BFile: Form B Affidavit.pdf | 24 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc4.pdf | 12 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc3.pdf | 12 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Eklavya Prayag Dham | Gat No 1103 wagholi Pune | 48 | Completed | Feb 2013 | Late, Mar 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Eklavya Skylark on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Rajaram Patil Nagar
Filed coordinates, straight-line distance. 68 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: Eklavya Builders Private Limited
Eklavya Builders Private Limited has 1 registration on MahaRERA, including Eklavya Skylark. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What are my rights if Eklavya Skylark is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Eklavya Skylark?
The registered promoter entity is Eklavya Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Eklavya Skylark?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Eklavya Skylark?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Eklavya Skylark?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Eklavya Skylark?
The professionals named in the filing: Architect: Siddharth Subhash Harishchandrakar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Eklavya Skylark?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.