Home / Browse projects / Palghar, Maharashtra / Dwarka Apartment
Dwarka Apartment
RG-MH-44940 · RERA P99000047876 · Last updated on MahaRERA portal: 15 Nov 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dwarka Apartment is a Residential / Group Housing project by AMARJEET PANCHAM YADAV in Palghar, Maharashtra, registered with MahaRERA as P99000047876 on 1 Dec 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date.
At a glance
Project
- NameDwarka Apartment
- TypeResidential / Group Housing
- Location
- Padghe
- Palghar
- 401404
- Pincode401404
- RERA no.P99000047876
- ReraGenie IDRG-MH-44940
Builder
- NameAMARJEET PANCHAM YADAV
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Dec 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed27 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Dwarka Apartment | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Dwarka Apartment: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership9
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Shaligram Builders and Developers | Vasai-Virar City (M Corp) | Palghar |
| Umabai Yashawant Patil | BHAYANDAR | Thane |
| ARUN YASHWANT PATIL | BHAYANDAR | Thane |
| MALTI MADHUKAR PATIL | BHAYANDAR | Thane |
| CHANDRAPRABHA CHINTAMAN PATIL | BHAYANDAR | Thane |
| CHANDRAKALA CHINTAMAN PATIL | BHAYANDAR | Thane |
| PARSHURAM YASHWANT PATIL | BHAYANDAR | Thane |
| SANJAY R PATHAK | BHAYANDAR | Thane |
| SADHANA DABRE | BHAYANDAR | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rajesh Y Satghare |
| Engineer | Mehram |
| Chartered Accountant | Dharmendra Lunawat |
| Partner | Role in project |
|---|---|
| AMARJEET PANCHAM YADAV | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed27
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: LOE LEGAL.pdf | 15 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: LOE FINANCE.pdf | 15 Nov 2022 |
| Details of encumbrances concerned to LegalFile: LOE LEGAL.pdf | 15 Nov 2022 |
| Details of encumbrances concerned to LegalFile: LOE FINANCE.pdf | 15 Nov 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER_compressed.pdf | 15 Nov 2022 |
| Proforma of Agreement for saleFile: AFS.pdf | 15 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: deviation report wrt allotment letter.pdf | 15 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: deviation report wrt model copy of agreement.pdf | 15 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 marin enterprises_compressed.pdf | 18 Oct 2022 |
| Details of encumbrances concerned to LegalFile: loe-legal (1).pdf | 11 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a bank ac.pdf | 11 Oct 2022 |
| Declaration about Commencement CertificateFile: letter.pdf | 12 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner 30 Apr 2022 15-21_compressed.pdf | 30 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC CLARIFICATION.pdf | 15 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Binder1_compressed_compressed.pdf | 11 Mar 2022 |
| Declaration about Commencement CertificateFile: FORM D.pdf | 9 Mar 2022 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 2 Mar 2022 |
| Building plan approvalFile: Layout Building Plan_compressed.pdf | 24 Feb 2022 |
| Layout approvalFile: Layout Plan_compressed-compressed.pdf | 24 Feb 2022 |
| PAN CardFile: Amarjeet Yadav Pan.pdf | 24 Feb 2022 |
| Details of encumbrancesFile: Encumbrances letter with letter head.pdf | 24 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: Layout Plan_compressed-compressed.pdf | 24 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout Building Plan_compressed.pdf | 24 Feb 2022 |
| Declaration in FORM BFile: Form b Amarjeet Yadav.pdf | 24 Feb 2022 |
| Declaration in FORM BFile: Form B Awadhesh_compressed.pdf | 24 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf | 24 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200230783675_For_Asset_Based_Search_21_02_2022_18_21_51_345.pdf | 24 Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 27 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Dwarka Apartment on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Padghe3,200+ in Palghar
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: AMARJEET PANCHAM YADAV
AMARJEET PANCHAM YADAV has 1 registration on MahaRERA, including Dwarka Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that Dwarka Apartment shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Dwarka Apartment is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dwarka Apartment?
The registered promoter entity is AMARJEET PANCHAM YADAV, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dwarka Apartment?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Dwarka Apartment?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dwarka Apartment?
The professionals named in the filing: Architect: Rajesh Y Satghare; Engineer: Mehram; Chartered Accountant: Dharmendra Lunawat. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dwarka Apartment?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback