ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Dosti West County - Dosti Nest - Phase 4

Registered No litigation declared Residential / Group Housing project

Dosti West County - Dosti Nest - Phase 4

By DOSTI ENTERPRISES

RG-MH-90953 · RERA P51700050253 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 14 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
187 of 639Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 198 documents Report an error

Dosti West County - Dosti Nest - Phase 4 is a Residential / Group Housing project by DOSTI ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700050253 on 27 Mar 2023. Possession is promised by 31 Dec 2027. 452 of the 639 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameDosti West County - Dosti Nest - Phase 4
  • TypeResidential / Group Housing
  • Location
    • Thane Bhiwandi Wadpa Road
    • Balkum
    • Thane (West)
    • Thane (M Corp.)
    • Thane
    • 400608
  • Pincode400608
  • RERA no.P51700050253
  • ReraGenie IDRG-MH-90953

Builder

  • NameDOSTI ENTERPRISES
  • Entity typeOthers
  • Named personsDosti Realty Limited, Suraksha Realty Limited, MACKINON ENTERPRISES PVT LTD
  • Other registrations14 more →
  • Completed2 of 15
  • Declared earlier projects16 →

Key dates

this monthRegisteredMar 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Mar 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed198 files

Current status

71%452 of 639 units booked
46.4%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dosti Heron Wing A, Wing B, Wing C / Building No 2 Wing A, Wing B, Wing CNA35336390639

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

Dosti Heron Wing A, Wing B, Wing C / Building No 2 Wing A, Wing B, Wing C: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes7%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1813

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,813
Closed/Covered852
Open Space961

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,340 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Sep 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI61240.56
Proposed, not sanctioned50,212 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort, Mumbai
Estimated costRs 266.67 cr
Cost incurredRs 123.80 cr
Work done46.42%
BuildingWingEstimatedIncurred
Dosti Heron Wing A, Wing B, Wing C / Building No 2 Wing A, Wing B, Wing CNARs 250.68 crRs 123.80 cr
-NARs 15.99 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNEERJA PURANDARE
ArchitectJAY R VORA
ArchitectTen Folds Architects & Consultants
EngineerVaibhav Raghunath Kalambate
EngineerSWAPNIL LONDHE
EngineerParas R Vishwakarma
Chartered AccountantBAGADE AND ASSOCIATES
Chartered AccountantManish Bardia & Co
PartnerRole in project
DOSTI ENTERPRISES-

Litigation declared13

CaseCourtStatus
16/2013Civil Judge Senior Division ThaneFor Exhibiting documents in the Evidence of Defendant no three to thirty
586/2011Civil Judge Senior Division ThaneFor Evidence of Plantiff
149/2010Civil Judge Junior Division ThaneFor order on Evidence discard application of plaintiff
1/2015Civil Judge Junior Division Thanefor list of witness of plaintiff
23/2021District Judge ThaneFor final arguements on Appeal
687/2010Civil Judge Junior Division ThaneFor evidence of defence part heard
38/2012Civil Judge Junior Division ThaneFor order on intervention application of Dosti
308/2014Civil Judge Junior Division ThaneFor Evidence of Plantiff
31/2018District Judge ThaneFor steps by applicants for securing presence of unserved respondents
313/2018Civil Judge Junior Division ThaneFor hearing on deficit court fee application of defendant number twelve dosti
389/2017Civil Judge Senior Division ThaneFor reply of defendant number ten on delay condonation application of plaintiff
35/2017Civil Judge Senior Division ThaneFor say of plaintiff on amendment application of defendant number forty four Dosti
400/2022Civil Judge Senior Division ThaneFor reports of respondents

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed198

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 198 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A - DWC Dosti Nest Ph 4.pdf23 Jun 2026
Withdrawal Update Form 1File: Dosti Enterprises DWC Nest Ph 4 Form 1 Mar26.pdf28 Apr 2026
Withdrawal Update Form 2File: Dosti Enterprises DWC Nest Ph 4 Form 2 Mar26.pdf28 Apr 2026
Withdrawal Update Form 3File: Dosti Enterprises DWC Nest Ph 4 Form 3 Mar26_compressed.pdf28 Apr 2026
Withdrawal Update Form 1File: Dosti Enterprises DWC Nest Ph 4 Form 1 Dec25.pdf27 Jan 2026
Withdrawal Update Form 2File: Dosti Enterprises DWC Nest Ph 4 Form 2 Dec25.pdf27 Jan 2026
Withdrawal Update Form 3File: Dosti Enterprises DWC Nest Ph 4 Form 3 Dec25compressed.pdf27 Jan 2026
Withdrawal Update Form 1File: DWC Nest PH4 Heron ARCH Certificate Sept 25.pdf27 Nov 2025
Withdrawal Update Form 2File: DWC Nest PH4 Heron Engg Certificate Sept 25.pdf27 Nov 2025
Withdrawal Update Form 3File: DWC Nest PH4 Heron CA Certificate Sept 25.pdf27 Nov 2025
Form 5 (FY 2024-2025)File: DE DWC Nest Phase 4.pdf12 Nov 2025
Form 1File: DWC Nest PH4 Heron Arch Certificate July2025.pdf27 Jul 2025
Form 2File: DWC Nest PH4 Heron Engg Certificate July2025.pdf27 Jul 2025
Form 3File: DWC Nest PH4 Heron CA Certificate July2025.pdf27 Jul 2025
Disclosure of Sold and Booked InventoryFile: DWC Nest PH4 June 2025.pdf27 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DWC Nest PH4 Architect's Certificate.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DWC Nest PH4 CA Certificate.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DWC Nest PH4 Engg Certificate.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: DWC Dosti Nest PH4 Dosti Heron A B C PH 4.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: DWC Nest PH4 Quality Certificate.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DWC Dosti Nest Phase-4 CA Certificate.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DWC Dosti Nest Phase-4 Engineer Certificate.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DWC Dosti Nest Phase-4 Arch certificate 30Dec 2024.pdf10 Jan 2025
Disclosure of sold/ booked inventoryFile: DWC Nest PH4 Dosti Heron Wing A B C.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: DWC Nest PH4.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DWC Nest PH4 Form1 Sep24.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DWC Nest PH4 Form3 Sep24.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DWC Nest PH4 Form2 Sep24.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DWC Dosti Nest Phase-4.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: 11-4 DWC Nest PH4.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DWC Dosti Nest Phase-4 Form1 Arch Cert June 2024.pdf29 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DWC Dosti Nest Phase-4 Form2 Engg Cert June 2024.pdf29 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DWC Dosti Nest Phase-4 Form3 CA Cert June 2024.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: Dosti Nest Phase-4 Heron.pdf14 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DWC Dosti Nest Phase 4-compressed.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate Dosti nest Phase4.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate DWC Dosti Nest Phase 4 Heron.pdf25 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Dosti Nest Phase-4.pdf24 Apr 2024
Disclosure of sold/ booked inventoryFile: Dosti Heron A B C.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate DWC Dosti Nest Phase 4.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate DWC Dosti Nest Phase 4.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Dosti West County Phase 4 Dosti Nest.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Dosti West County Dosti Nest Phase 4.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg-Form-2-DWC-Nest-PH-IV.pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA certificate Dosti West county Dosti Nest Phase 4.pdf11 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dosti West County Dosti Nest Phase 4.pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: Dosti Heron Phase 4 A B C Wing.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dosti Nest Phase 4.pdf12 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dosti Nest Phase 4.pdf17 Jul 2023
Disclosure of sold/ booked inventoryFile: Heron A,B,C.pdf10 Jul 2023
Layout approvalFile: 1) Amended Permission Plans date -8-5-23 comp_Part1_compressed.pdf10 May 2023
Layout approvalFile: 2) Amended Permission Plans date -8-5-23 comp_Part2_compressed.pdf10 May 2023
Layout approvalFile: 3) Amended Permission Plans date -8-5-23 comp_Part3_compressed.pdf10 May 2023
Layout approvalFile: 4) Amended Permission Plans date -8-5-23 comp_Part4_compressed.pdf10 May 2023
Layout approvalFile: 5) Amended Permission Plans date -8-5-23 comp_Part5_compressed.pdf10 May 2023
Layout approvalFile: 6) Amended Permission Plans date -8-5-23 comp_Part6_compressed.pdf10 May 2023
Layout approvalFile: 7) Amended Permission Plans date -8-5-23 comp_Part7_compressed.pdf10 May 2023
Layout approvalFile: 8) Amended Permission Plans date -8-5-23 comp_Part8_compressed.pdf10 May 2023
Layout approvalFile: 9) Amended Permission Plans date -8-5-23 comp_Part9_compressed.pdf10 May 2023
Layout approvalFile: 10) Amended Permission Plans date -8-5-23 comp_Part10_compressed.pdf10 May 2023
Layout approvalFile: 11) Amended Permission Plans date -8-5-23 comp_Part11_compressed.pdf10 May 2023
Layout approvalFile: 12) Amended Permission Plans date -8-5-23 comp_Part12_compressed.pdf10 May 2023
Layout approvalFile: 13) Amended Permission Plans date -8-5-23 comp_Part13_compressed.pdf10 May 2023
Layout approvalFile: 14) Amended Permission Plans date -8-5-23 comp_Part14_compressed.pdf10 May 2023
Layout approvalFile: 15) Amended Permission Plans date -8-5-23 comp_Part15_compressed.pdf10 May 2023
Layout approvalFile: 16) Amended Permission Plans date -8-5-23 comp_Part16_compressed.pdf10 May 2023
Layout approvalFile: 17) Amended Permission Plans date -8-5-23 comp_Part17_compressed.pdf10 May 2023
Layout approvalFile: 18) Amended Permission Plans date -8-5-23 comp_Part18_compressed.pdf10 May 2023
Layout approvalFile: 19) Amended Permission Plans date -8-5-23 comp_Part19_compressed.pdf10 May 2023
Layout approvalFile: 20) Amended Permission Plans date -8-5-23 comp_Part20_compressed.pdf10 May 2023
Layout approvalFile: 21) Amended Permission Plans date -8-5-23 comp_Part21_compressed.pdf10 May 2023
Layout approvalFile: 22) Amended Permission Plans date -8-5-23 comp_Part22_compressed.pdf10 May 2023
Layout approvalFile: 23) Amended Permission Plans date -8-5-23 comp_Part23_compressed.pdf10 May 2023
Layout approvalFile: 24) Amended Permission Plans date -8-5-23 comp_Part24_compressed.pdf10 May 2023
Layout approvalFile: 25) Amended Permission Plans date -8-5-23 comp_Part25_compressed.pdf10 May 2023
Layout approvalFile: 26) Amended Permission Plans date -8-5-23 comp_Part26_compressed.pdf10 May 2023
Layout approvalFile: 27) Amended Permission Plans date -8-5-23 comp_Part27_compressed.pdf10 May 2023
Layout approvalFile: 28) Amended Permission Plans date -8-5-23 comp_Part28_compressed.pdf10 May 2023
Layout approvalFile: 29) Amended Permission Plans date -8-5-23 comp_Part29_compressed.pdf10 May 2023
Layout approvalFile: 30) Amended Permission Plans date -8-5-23 comp_Part30_compressed.pdf10 May 2023

How this compares with Thane

71%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dosti West County - Dosti Nest - Phase 4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Balkum, Thane (West)7,600+ in Thane

Builder: DOSTI ENTERPRISES

DOSTI ENTERPRISES has 15 registrations on MahaRERA, including DOSTI WEST COUNTY - DOSTI OAK and DOSTI WESTCOUNTY- PHASE 2- DOSTI CEDAR. Its filings disclose 16 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Dosti West County - Dosti Nest - Phase 4 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dosti West County - Dosti Nest - Phase 4?

The registered promoter entity is DOSTI ENTERPRISES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dosti West County - Dosti Nest - Phase 4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Dosti West County - Dosti Nest - Phase 4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dosti West County - Dosti Nest - Phase 4?

The professionals named in the filing: Architect: NEERJA PURANDARE; Architect: JAY R VORA; Architect: Ten Folds Architects & Consultants; Engineer: Vaibhav Raghunath Kalambate; Engineer: SWAPNIL LONDHE; Engineer: Paras R Vishwakarma. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dosti West County - Dosti Nest - Phase 4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dosti West County - Dosti Nest - Phase 4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dosti West County - Dosti Nest - Phase 4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.