DOSHI TARACHAND VALAMJI VANIK NIWAS
By SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI
RG-MH-84698 · RERA P51800045888 · Last updated on MahaRERA portal: 24 Dec 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DOSHI TARACHAND VALAMJI VANIK NIWAS is a Residential / Group Housing project by SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800045888 on 15 Jun 2022. The registration is recorded completed; possession was promised by 30 Dec 2024. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameDOSHI TARACHAND VALAMJI VANIK NIWAS
- TypeResidential / Group Housing
- Location
- 7th cross road near Diamond Garden
- Chembur
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800045888
- ReraGenie IDRG-MH-84698
Builder
- NameSHREE CUTCHI DASHA SHRIMALI VANIK GNYATI
- Entity typeTrust
- TrusteesSHRI MANOJ NAVIN PAREKH, SHRI KIRTIBHAI AMRITLAL MAUN, SHRI KISHORBHAI DHARAMSHI MEHTA, SHRI CHETAN SHANTILAL DHILA, SHRI MAHENDRA KANTILAL MEHTA, SHRI MAHENDRAKUMAR KANJI MEHTA, DR SHRI KIRTIKUMAR BHAILAL DOSHI, SHRI LALITKUMAR VANECHAND MEHTA, SHRI KIRITKUMAR LALCHAND MEHTA
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jun 2022
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2023)
- Buildings1 building record
- Documents filed65 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DOSHI TARACHAND VALAMJI VANIK NIWAS | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
DOSHI TARACHAND VALAMJI VANIK NIWAS: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 24 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Others | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Aakar Architects & Consultanta |
| Engineer | Frames |
| Chartered Accountant | Todi Tulsyan & Co |
| Partner | Role in project |
|---|---|
| SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe were expecting to complete the project by December 2023 but due to delay in getting various approvals and technicalities thereof, our project is yet to get complete with OC for which we need one year extension till 30.12.2024. Keeping in view of the above genuine hardship and difficulties, the project is delayed. We need extension for completing the project by one year under section 6 of RERA till 30.12.2024.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 14 Oct 2024
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_23-24_signed.pdf | 24 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 as on 31_3_24.pdf | 30 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 as on 30_6_24.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dasha Trust 01_01_2024 to 31_03_2024.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dasha Trust 01_04_2024 to 30_06_2024.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on_31_3_24.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 30_6_24.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A as on 31_3_24.pdf | 30 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate - VANIK NIWAS - 20240814.pdf | 28 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate - VANIK NIWAS - 20240814.pdf | 22 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC_24_08_2024.pdf | 14 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 31_12_23_with correction.pdf | 3 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 AS ON 30_06_2023.pdf | 23 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 30_09_2023.pdf | 23 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 31_12_2023.pdf | 23 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Quarter 1 30 JUNE 23.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Quarter 2 30 SEPTEMBER 23.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Quarter 3 31 DECEMBER 23.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30 JUNE 23.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_30 SEPTEMBER 23.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30 DECEMBER 23.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 AS ON 30_06_2023.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 30_09_2023.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 31_12_2023.pdf | 9 May 2024 |
| Declaration in FORM BFile: formB.pdf | 31 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold and booked inventory as on 31_3_23.pdf | 31 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form _5 final.pdf | 31 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on 31_3_23.pdf | 23 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A_as on 31_3_23.pdf | 23 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 31_03_2023_compressed.pdf | 23 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 31_12_2022_compressed.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CERTIFICATE 27_02_2023.pdf | 9 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CERTIFICATE 20_04_23.pdf | 9 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan_0576_merged (1)_compressed.pdf | 29 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_Final signed_compressed.pdf | 14 Mar 2023 |
| Proforma of Allotment letterFile: Proforma Allotment Letter_Dasha Trust.pdf | 8 Jun 2022 |
| Copy of the legal title reportFile: Legal Title Report_format A (1).pdf | 31 May 2022 |
| Layout approvalFile: Approved Layout-Drawing-1.pdf | 12 May 2022 |
| Layout approvalFile: Approved Layout-Drawing_compressed-2.pdf | 12 May 2022 |
| Layout approvalFile: Approved Layout-Drawing_compressed-3.pdf | 12 May 2022 |
| Layout approvalFile: Approved Layout-Drawing-1 sign.pdf | 12 May 2022 |
| Copy of Layout Approval (in case of layout)File: Approved Layout-Drawing-1.pdf | 12 May 2022 |
| Copy of Layout Approval (in case of layout)File: Approved Layout-Drawing_compressed-2.pdf | 12 May 2022 |
| Copy of Layout Approval (in case of layout)File: Approved Layout-Drawing_compressed-3.pdf | 12 May 2022 |
| Copy of Layout Approval (in case of layout)File: Approved Layout-Drawing-1 sign.pdf | 12 May 2022 |
| Building plan approvalFile: Amended Plan Report (1).pdf | 2 May 2022 |
| Details of encumbrancesFile: DECLARATION NON ENCUMBRANCES (1).pdf | 2 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Plan Report (1).pdf | 2 May 2022 |
| Declaration in FORM BFile: Authority letter.pdf | 2 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A QUALITY ASSURANCE CERTIFICATE BY ENG.pdf | 2 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_TRUST 200236507646_For_Debtor_Based_Search_02_05_2022_16_38_19_832.pd | 2 May 2022 |
| Disclosure of sold/ booked inventoryFile: rera.pdf | 2 May 2022 |
| Disclosure of sold/ booked inventoryFile: rera page 2.pdf | 2 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFI 1 .pdf | 2 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFI 2 .pdf | 2 May 2022 |
| Proforma of Allotment letterFile: DASHA AGREEMENT FOR SALE.pdf | 2 May 2022 |
| OtherFile: MOU_compressed.pdf | 2 May 2022 |
| Building plan approvalFile: IOD FOR BULD PLAN_compressed.pdf | 30 Apr 2022 |
| PAN CardFile: PANCARD OF TRUST.pdf | 30 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD FOR BULD PLAN_compressed.pdf | 30 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC .pdf | 30 Apr 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 30 Apr 2022 |
| Declaration in FORM BFile: Form B Affidevit for RERA.pdf | 30 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 .pdf | 30 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 dated 22-4-22.pdf | 30 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
Keep DOSHI TARACHAND VALAMJI VANIK NIWAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI
SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI has 1 registration on MahaRERA, including DOSHI TARACHAND VALAMJI VANIK NIWAS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if DOSHI TARACHAND VALAMJI VANIK NIWAS is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DOSHI TARACHAND VALAMJI VANIK NIWAS?
The registered promoter entity is SHREE CUTCHI DASHA SHRIMALI VANIK GNYATI, a trust as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DOSHI TARACHAND VALAMJI VANIK NIWAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DOSHI TARACHAND VALAMJI VANIK NIWAS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DOSHI TARACHAND VALAMJI VANIK NIWAS?
The professionals named in the filing: Architect: Aakar Architects & Consultanta; Engineer: Frames; Chartered Accountant: Todi Tulsyan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DOSHI TARACHAND VALAMJI VANIK NIWAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.