ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / DNV ARCELIA PH 2

Completed No litigation declared Residential / Group Housing project

DNV ARCELIA PH 2

By DNV REALTY

RG-MH-73566 · RERA P52100003478 · Last updated on MahaRERA portal: 22 Jun 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2018Possession promisedregistration recorded completed
12 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 90%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

DNV ARCELIA PH 2 is a Residential / Group Housing project by DNV REALTY in Pune, Maharashtra, registered with MahaRERA as P52100003478 on 5 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2018.

At a glance

Project

  • NameDNV ARCELIA PH 2
  • TypeResidential / Group Housing
  • Location
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003478
  • ReraGenie IDRG-MH-73566

Builder

  • NameDNV REALTY
  • Entity typePartnership
  • PartnerTrupti Parag Patil
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017PromisedDec 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion31 Dec 2018
  • Revised completionNone
  • Buildings2 building records
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Arcelia ANA120000
Arcelia DNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

Arcelia A58%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Arcelia D77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 22 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes40%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Gates and Compound Wall common for whole complexYes80%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered2
Open Space42
BuildingClosed/CoveredOpen SpaceTotal
Arcelia A11516
Arcelia D12728

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,680 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Jyoti Jayesh RathoreBanerPune

Approvals and building plan

Permissible FSI4983.83
Proposed, not sanctioned4,984 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1st floor plot 421 A CTS No 1071 Gokhale Road Near Symbiosis ATUR Centre Ashoknagar Pune 411016

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLaxman Thite
EngineerG. A. Bhilare Consultants Pvt. Ltd.
PartnerRole in project
DNV REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Aug 2019

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: DNVA Eng Quality Assurance Certificate Ph-2_0001.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: DNVA Eng Quality Assurance Certificate Ph-2_0001.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5)File: DNVA Form 5 Phase II.pdf28 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Phase 2 OC.pdf28 Aug 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: D SOCIETY REGISTRATION CERTIFICATE.pdf19 Jul 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERTIFICATE NO DC-16173-2018.pdf19 Jul 2019
OtherFile: COMPLETION CERTIFCATE A AND D WING.pdf16 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate 3318.pdf31 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II Q1 Engineering Certificate 101017.pdf31 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg 8118.pdf31 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg 3318.pdf31 Mar 2018
Certificates of CA (Form 3)File: CA 3318.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE PHASE II Q1.pdf28 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Phase II Q1.pdf28 Oct 2017
Certificates of Architect (Form 4)File: ARCHITECT CERTIFICATE PHASE II Q1.pdf28 Oct 2017
Building plan approvalFile: A building 1.pdf27 Jul 2017
Building plan approvalFile: A building 2.pdf27 Jul 2017
Building plan approvalFile: A building 3.pdf27 Jul 2017
Building plan approvalFile: A building.pdf27 Jul 2017
Building plan approvalFile: D building 1.pdf27 Jul 2017
Building plan approvalFile: D building 2.pdf27 Jul 2017
Building plan approvalFile: D building.pdf27 Jul 2017
Layout approvalFile: Layout.pdf27 Jul 2017
PAN CardFile: PAN Card.pdf27 Jul 2017
Copy of the legal title reportFile: Legal Title Report.pdf27 Jul 2017
Details of encumbrancesFile: SELF DECLARATION.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf27 Jul 2017
Building Plan Approval (IOD)File: A building 1.pdf27 Jul 2017
Building Plan Approval (IOD)File: A building 2.pdf27 Jul 2017
Building Plan Approval (IOD)File: A building 3.pdf27 Jul 2017
Building Plan Approval (IOD)File: A building.pdf27 Jul 2017
Building Plan Approval (IOD)File: D building 1.pdf27 Jul 2017
Building Plan Approval (IOD)File: D building 2.pdf27 Jul 2017
Building Plan Approval (IOD)File: D building.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFCATES 2017.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICAT 2014.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFCATES 2015.pdf27 Jul 2017
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA A WING ARHITCT S CERTIFICATE.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate.pdf27 Jul 2017
Certificates of CA (Form 3)File: PHASE II CA CERTIFICATE.pdf27 Jul 2017
Proforma of Allotment letterFile: phase ii allotment letter.pdf27 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Elite HomesELITE HOMES NEAR AKSHARA INTERNATIONAL SCHOOL SR.NO 98 TATHAWADE PUNE-411033248CompletedNov 2013Nov 2013
Elite HomeELITE HOMES NEAR AKSHARA INTERNATIONAL SCHOOL SR.NO 98 TATHAWADE PUNE-411033248CompletedNov 2013Nov 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DNV ARCELIA PH 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune

2 kmDNV ARCELIA PH 2Completed 106Lapsed / revoked 56Other 114Dot size: filed unitsN

Filed coordinates, straight-line distance. 276 registered projects within 2 km.

Builder: DNV REALTY

DNV REALTY has 6 registrations on MahaRERA, including DNV ELVIRA A and DNV ARCELIA PH 2. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if DNV ARCELIA PH 2 is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DNV ARCELIA PH 2?

The registered promoter entity is DNV REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DNV ARCELIA PH 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DNV ARCELIA PH 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DNV ARCELIA PH 2?

The professionals named in the filing: Architect: Laxman Thite; Engineer: G. A. Bhilare Consultants Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DNV ARCELIA PH 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DNV ARCELIA PH 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DNV ARCELIA PH 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.