Home / Browse projects / Palghar, Maharashtra / DEEP SKY C AND G WING

Registered No litigation declared Others project

DEEP SKY C AND G WING

By DEEP BUILDER AND DEVELOPERS

RG-MH-06239 · RERA P99000054150 · Last updated on MahaRERA portal: 26 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 25.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedno revision filed
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 88%
0Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

DEEP SKY C AND G WING is a Others project by DEEP BUILDER AND DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000054150 on 29 Dec 2023. Possession is promised by 30 Jun 2028.

At a glance

Project

  • NameDEEP SKY C AND G WING
  • TypeOthers
  • Location
    • GOKHIWARE
    • VASAI EAST
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000054150
  • ReraGenie IDRG-MH-06239

Builder

  • NameDEEP BUILDER AND DEVELOPERS
  • Entity typePartnership
  • PartnersSUSHILA SANJAY YADAV, SANJAY KERDARNATH YADAV

Key dates

this monthRegisteredDec 2023PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Dec 2023
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed121 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DEEP SKY C WINGNA2524000
DEEP SKY G WINGNA2524000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 26 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 88%.

DEEP SKY C WING54%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises42%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks61%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
DEEP SKY G WING47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises6%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered120
Open Space8
BuildingClosed/CoveredOpen SpaceTotal
DEEP SKY C WING61869
DEEP SKY G WING59059

Land and ownership5

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,065 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 25.00 crore
CERSAI search filedYes
Declared on9 Jun 2026
LandownerVillageDistrict
RASHMI AMEYA DEVELOPERS HOUSING & ESTATE REALTORSVasai-Virar City (M Corp)Palghar
SAI RYDAM REALTORS PRIVATE LIMITEDVasai-Virar City (M Corp)Palghar
SAI ASHISH DEVELOPERSVasai-Virar City (M Corp)Palghar
DEVENDRA RAJNIKANT LADHANIVasai-Virar City (M Corp)Palghar
ANIL RAMCHANDRA GUPTAVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPRATION
Permissible FSI20092.2
Proposed, not sanctioned20,092 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNALLASOPARA EAST

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANAT MEHTA
EngineerABHISHEK LENGARE
EngineerBHAVIN SHAH
Chartered AccountantSTR AND ASSOCIATES
Chartered AccountantHARESH MEHTA AND ASSOCIATES
Chartered AccountantRAKESH SAMARJEET TIWARI
PartnerRole in project
DEEP BUILDER AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2023-2024)File: FORM 5 FY_2023-24.pdf26 Jun 2026
Form 5 (FY 2024-2025)File: FORM 5 FY_2024-25.pdf18 Jun 2026
Form 2A (FY 2024-2025)File: FORM 2A DEEP SKY C G WING FY_2024-25.pdf17 Jun 2026
Form 2A (FY 2025-2026)File: FORM 2A DEEP SKY C G WING FY_2025-26.pdf17 Jun 2026
Form 1File: FORM 1 C AND G WING - MAR 2026.pdf20 May 2026
Form 2File: FORM 2 C AND G WING - MAR 2026.pdf20 May 2026
Form 3File: FORM 3_C AND G WING_MAR 2026-SIGNED.pdf20 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY C AND G WING - MAR 2026.pdf20 May 2026
Form 1File: FORM 1 C and G WING - DEC 2025.pdf28 Feb 2026
Form 2File: FORM 2 C and G WING - DEC 2025.pdf28 Feb 2026
Form 3File: FORM 3_C and G WING_DEC 2025-SIGNED.pdf28 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY C and G WING - DEC 2025.pdf28 Feb 2026
Form 1File: FORM 1 C & G WING - SEP 2025.pdf10 Nov 2025
Form 2File: FORM 2 C & G WING - SEP 2025.pdf10 Nov 2025
Form 3File: FORM 3_C & G WING_SEP 2025-SIGNED.pdf10 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY C & G WING - SEP 2025.pdf10 Nov 2025
Form 1File: FORM 1_Q1 APR - JUNE 2025 C & G Wing.pdf22 Aug 2025
Form 2File: FORM 2_Q1 APR - JUNE 2025 C & G Wing.pdf22 Aug 2025
Form 3File: FORM 3_C & G WING_APR - JUNE 2025-SIGNED.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY_Q1 APR - JUNE 2025.pdf22 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-C WING.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-G WING.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-C WING.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-G WING.pdf12 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 FY 2023-2024.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: Deep Sky C And G Wing-SOLD BOOKED INVENTORY - converted.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Deep Builder And Developers-C G WING SIGNED-compressed.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - C Wing.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- G WIng.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- C WIng.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- G WIng.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Deep Builder And Developers- G Wing (1).pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Deep Sky C Wing - 22022024 REVISED.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Deep Sky G Wing 220224.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Deep Sky C Wing - 22022024 REVISED.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Deep Sky G Wing 220224.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Deep Sky C Wing- 190724.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Deep Sky G Wing- 190724.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- C Wing.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- G Wing.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_DEEPSKYCG_MAR 24 SIGNED1.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_JUNE 24 SIGNED1.pdf13 Aug 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A UPDATED.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 C WING.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 G WINGS.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Deep Sky C Wing 220224.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Deep Sky G Wing 220224.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 C WING.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 G WING.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Deep Sky C Wing 220224.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Deep Sky G Wing 220224.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - converted.pdf22 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT FORMAT A.pdf12 Jun 2024
Details of encumbrances concerned to FinanceFile: FIANANCIAL ENCUMBRANCES G WING.pdf22 Apr 2024
Details of encumbrances concerned to LegalFile: FIANANCIAL ENCUMBRANCES G WING.pdf22 Apr 2024
Details of encumbrances concerned to FinanceFile: FIANANCIAL ENCUMBRANCES.pdf11 Jan 2024
Details of encumbrances concerned to LegalFile: FIANANCIAL ENCUMBRANCES.pdf11 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 signed opt revised.pdf22 Dec 2023
Other - LegalFile: Deed Exchange_Gokhivare SNO891 FULL_1.pdf18 Dec 2023
Other - LegalFile: Deed Exchange_Gokhivare SNO 891A FULL_2.pdf18 Dec 2023
Other - LegalFile: Deed Exchange_Gokhivare SNO 891A FULL_3.pdf18 Dec 2023
Other - LegalFile: Deed Exchange_GokhivareSNO 891A FULL_4.pdf18 Dec 2023
Other - LegalFile: PAO DEEP BD FULL_1.pdf18 Dec 2023
Other - LegalFile: PAO DEEP BD FULL_2.pdf18 Dec 2023
Other - LegalFile: PAO DEEP BD FULL_3.pdf18 Dec 2023
Other - LegalFile: Index 2 And Ferfar R.pdf18 Dec 2023
Other - FinanceFile: Request letter for tab opening Finance.pdf18 Dec 2023
Other - TechnicalFile: Request letter for tab opening Finance.pdf18 Dec 2023
Layout approvalFile: RDP DATED 03012022(NO 772) OURS_opt hl RR.pdf14 Dec 2023
Copy of Layout Approval (in case of layout)File: RDP DATED 03012022(NO 772) OURS_opt hl RR.pdf14 Dec 2023
Layout approvalFile: block layout No 772 opt HL RR.pdf13 Dec 2023
Copy of Layout Approval (in case of layout)File: block layout No 772 opt HL RR.pdf13 Dec 2023
Declaration about Commencement CertificateFile: 1 CC DECLARATION FINAL.pdf13 Dec 2023
Other - TechnicalFile: RDP DATED 03012022(NO 772) OURS_opt hl RR.pdf13 Dec 2023
Building plan approvalFile: block layout No 772 opt HL.pdf22 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: block layout No 772 opt HL.pdf22 Nov 2023
Copy of the legal title reportFile: legal title report REVISED 20112023_1 WITH INDEX.pdf20 Nov 2023
Copy of the legal title reportFile: legal title report REVISED 20112023_2.pdf20 Nov 2023
Copy of the legal title reportFile: legal title report REVISED 20112023_3.pdf20 Nov 2023
Copy of the legal title reportFile: legal title report REVISED 20112023_4.pdf20 Nov 2023

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DEEP SKY C AND G WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI EAST3,200+ in Palghar

2 kmDEEP SKY C AND G WINGCompleted 52Lapsed / revoked 30Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: DEEP BUILDER AND DEVELOPERS

DEEP BUILDER AND DEVELOPERS has 1 registration on MahaRERA, including DEEP SKY C AND G WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if DEEP SKY C AND G WING is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DEEP SKY C AND G WING?

The registered promoter entity is DEEP BUILDER AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DEEP SKY C AND G WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DEEP SKY C AND G WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DEEP SKY C AND G WING?

The professionals named in the filing: Architect: SANAT MEHTA; Engineer: ABHISHEK LENGARE; Engineer: BHAVIN SHAH; Chartered Accountant: STR AND ASSOCIATES; Chartered Accountant: HARESH MEHTA AND ASSOCIATES; Chartered Accountant: RAKESH SAMARJEET TIWARI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DEEP SKY C AND G WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DEEP SKY C AND G WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DEEP SKY C AND G WING to a free account