Home / Browse projects / Kolhapur, Maharashtra / DATTATIRTH

Registration lapsed No litigation declared Residential / Group Housing project

DATTATIRTH

By GAJRAJ BUILDERS

RG-MH-07692 · RERA P52100003610 · Last updated on MahaRERA portal: 11 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 26 months past the filed date
  • Completion date moved by 73 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Aug 2024Possession promised26 months past this date
25 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 75%
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

DATTATIRTH is a Residential / Group Housing project by GAJRAJ BUILDERS in Kolhapur, Maharashtra, registered with MahaRERA as P52100003610 on 6 Aug 2017. Possession was promised by 28 Aug 2024 and is now 26 months past that date. The completion date has moved by 73 months from the original filing.

At a glance

Project

  • NameDATTATIRTH
  • TypeResidential / Group Housing
  • Location
    • Nrusinhawadi
    • Shirol
    • Kolhapur
    • 416106
  • Pincode416106
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003610
  • ReraGenie IDRG-MH-07692

Builder

  • NameGAJRAJ BUILDERS
  • Entity typePartnership
  • PartnersPrakash Vilasrao Budhavnt, Kaveri Prakash Budhavant

Key dates

26 months past promisethis monthRegisteredAug 2017First promiseJul 2018Revised toAug 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion28 Aug 2024
  • Revised completionRevised to 28 Aug 2024 (originally 31 Jul 2018)
  • Buildings3 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA50000
BNA60000
CNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 75%.

A79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes45%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes40%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
A11
B11
C11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3982.5
Proposed, not sanctioned3,941 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1369, SIDDHI PLATINUM, SADASHIV PETH, PUNE-411030

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHALCHANDRA S PATIL
EngineerPARIKH & ASSOCIATES
PartnerRole in project
GAJRAJ BUILDERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000012027Jul 2018 → Jun 2023

Reason as filed by the promoterRevise sanction for Additional FSI from government authority and Covid - 19 Situation as well as fund shortage.

EXT53000008705Jul 2018 → Dec 2021

Reason as filed by the promoterObtained occupancy certificate(Partial) on 15/05/2019. Due to heavy rain in Kolhapur district government authorities given stay for occupancy and sale on 19/08/2019. The stay has been withdrawn by government authorities on 13/10/2020. Due to stay issued by department we not able complete the project so need the extension.

EXT53000016857Jul 2018 → Aug 2024

Reason as filed by the promoterWe have already completed the project. The completion file is pending with the concerned authority. Once the completion certificate has been received we will process the formation of Society and conveyance deed accordingly. Hence need extension of one year.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Apr 2025

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: GB Form3 CA Certificate.pdf11 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Maharera Occupancy Certificate_12-09-2024.pdf4 Apr 2025
Declaration in FORM BFile: Gb-Maharera Form B Notary Copy.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 01_Gajraj Builders_ITR_23-24.pdf2 Apr 2025
Declaration in FORM BFile: MAHARera Form B.pdf26 Sep 2023
Declaration in FORM BFile: MAHARera FormB.pdf13 Sep 2023
Declaration in FORM BFile: MAHARera_FormB_Affidavit Cum Declaration.pdf24 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHARera Form 03_1.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: MAHARERA_Form02A_Quality Assurance Certificate.pdf23 Aug 2023
OtherFile: Task Activity Parking.pdf23 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MAHARERA_Form02_Engineers Certificate.pdf21 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: MAHARERA_Form02A_Quality Assurance Certificate.pdf21 Aug 2023
Certificates of CA (Form 3)File: MAHARERA_FORM03_CA Certificate.pdf21 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MAHARERA_FORM05_22-23.pdf21 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MAHARera_Form_05_Balance Sheet_22-23.pdf14 Aug 2023
Declaration in FORM BFile: FORMB_Maharera Affidavit.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MahaRERA_FORM_01_Architect Certificate.pdf24 Jul 2023
Disclosure of sold/ booked inventoryFile: MahaRERA_SOLD UNSOLD Flats.pdf24 Jul 2023
Certificates of CA (Form 3)File: MAHARERA_Form 3_CA_Certificate.pdf24 Jul 2023
OtherFile: Maharera Affidavit.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_15-05-23.pdf21 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Certiicate of Engineer.pdf21 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Maharera_Form 2A_ Certificate of Quality Assurance.pdf21 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Balance Sheets_Gajraj_FY_21-22.pdf21 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Invetory_01-03-23.pdf4 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Status of Formation Legal Entity.pdf4 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf7 Jul 2022
Certificates of CA (Form 3)File: CA Certificate Revised.pdf7 Jul 2022
OtherFile: Sold Unsold and Completion details.pdf7 Jul 2022
OtherFile: Sold Unsold Completion details.pdf25 Jun 2022
Declaration about Commencement CertificateFile: Declaration about commencement certificate (1).pdf24 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 03_MAHARERA_FORM2A_Quality Assurance_03-06-2022.pdf24 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_Asset_Id_Based_Search_23_06_2022_19_48_33_747.pdf24 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: GB_BS_17-18.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: GB_Audit Report_18-19.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: GB_Balance Sheet_18-19.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GB_Balane Sheet_2019-20.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GB_Balance Sheet_Audit Report_2020-2021.pdf24 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf16 Jun 2022
Certificates of CA (Form 3)File: CA Certificate Revised.pdf16 Jun 2022
Building plan approvalFile: 06a_Approved Drawing.pdf14 Jun 2022
Building plan approvalFile: 06a_Approved Drawing.pdf14 Jun 2022
Building Plan Approval (IOD)File: 06a_Approved Drawing.pdf14 Jun 2022
Building Plan Approval (IOD)File: 06a_Approved Drawing.pdf14 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: 06_New Commencement_11-08-2017.pdf14 Jun 2022
Declaration about Commencement CertificateFile: 06_New Commencement_11-08-2017.pdf14 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01_MAHARERA_Architect Certificate_05-06-2022.pdf14 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 02_MAHARERA_FORM2_ENGINEERS CERTIFICATE_03-06-2022 (1).pdf14 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 03_MAHARERA_FORM2A_Quality Assurance_03-06-2022.pdf14 Jun 2022
Disclosure of sold/ booked inventoryFile: 07_MAHARERA_FLAT SALE_Status_2022.pdf14 Jun 2022
CERSAI detailsFile: 09_Reconveyance Deed.pdf14 Jun 2022
Certificates of CA (Form 3)File: 08_MAHARERA_CA_CERTIFICATE.pdf14 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupency letter.pdf17 Dec 2020
Declaration in FORM BFile: Declaration in FORM B.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificates of Engineer.pdf31 Jul 2017
Certificates of CA (Form 3)File: RERA CERTIFICATE.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: Draft of agreement to sale version.pdf28 Jul 2017
OtherFile: Development Agreement.pdf28 Jul 2017
Layout approvalFile: Plan Layout.pdf27 Jul 2017
Building plan approvalFile: Building Plan Approval.pdf27 Jul 2017
Building plan approvalFile: Building Plan Approval2.pdf27 Jul 2017
Building plan approvalFile: Building Plan Approval3.pdf27 Jul 2017
Building plan approvalFile: Building Plan Approval4.pdf27 Jul 2017
PAN CardFile: Pan Cards.pdf27 Jul 2017
Copy of the legal title reportFile: Legal Opinion Report.pdf27 Jul 2017
Details of encumbrancesFile: Sanction Letter.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan Layout.pdf27 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval.pdf27 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval2.pdf27 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval3.pdf27 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval4.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf25 Jul 2017

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one moved by 73 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is among them

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep DATTATIRTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nrusinhawadi880+ in Kolhapur

Builder: GAJRAJ BUILDERS

GAJRAJ BUILDERS has 1 registration on MahaRERA, including DATTATIRTH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What does it mean that DATTATIRTH shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DATTATIRTH is delayed beyond 28 Aug 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DATTATIRTH?

The registered promoter entity is GAJRAJ BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DATTATIRTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DATTATIRTH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DATTATIRTH?

The professionals named in the filing: Architect: BHALCHANDRA S PATIL; Engineer: PARIKH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DATTATIRTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DATTATIRTH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DATTATIRTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.