Home / Browse projects / Mumbai Suburban, Maharashtra / Dadamiyas Deluxe Apartment

Completed No litigation declared Residential / Group Housing project

Dadamiyas Deluxe Apartment

By Dadamiya Infrastructure & Deluxe Infra

RG-MH-29810 · RERA P51800030492 · Last updated on MahaRERA portal: 11 Dec 2023

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

Dadamiyas Deluxe Apartment is a Residential / Group Housing project by Dadamiya Infrastructure & Deluxe Infra in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030492 on 25 Aug 2021. The registration is recorded completed; possession was promised by 31 Mar 2023.

At a glance

Project

  • NameDadamiyas Deluxe Apartment
  • TypeResidential / Group Housing
  • Location
    • Masrani Lane
    • Kurla West
    • Kurla
    • Mumbai Suburban
    • 400070
  • Pincode400070
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800030492
  • ReraGenie IDRG-MH-29810

Builder

  • NameDadamiya Infrastructure & Deluxe Infra
  • Entity typePartnership
  • PartnersSana Moinuddin Shaikh, Moinuddin Shahid Shaikh, Shakeel Ahmad Mohammad Hussain Siddiqui

Key dates

this monthRegisteredAug 2021PromisedMar 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Aug 2021
  • Promised completion31 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dadamiyas Deluxe ApartmentNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Dadamiyas Deluxe Apartment: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area700 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Meena Lakshman Bhagchandani-Mumbai City

Approvals and building plan

Permissible FSI2162.65
Proposed, not sanctioned2,163 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKohinoor City Mall, Kirol Road, Kurla W, Mumbai - 400070

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMrs Sana N Malik Shaikh
EngineerM Arif Rupalwala
Chartered AccountantA R Sodha & Co
PartnerRole in project
Dadamiya Infrastructure & Deluxe Infra-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016730Mar 2023 → May 2023

Reason as filed by the promoterThe construction was completed in all respect, however, due to pending compliance of separate PR Card for road set-back in favour of BMC, the full OC was restricted to the area of extent of set-back area. Part OC i.e Full OC for Sale Wing i.e wing 'A' was obtained and possession thereof has also been given to prospective buyers. The full OC has now been issued on 23/05/2023 and inorder to avail the completion of project from MahaRERA, this extension is applied for. Since the project has been completed, post facto extension may please be granted and the completion may please be accepted.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 May 2023

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Masrani - new.pdf11 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Nov 2023
Declaration in FORM BFile: Affidavit.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 202223 Engg Certificate.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory Details.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory Details.pdf14 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf8 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2365443_OC_signed.pdf23 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf11 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13-10-2022.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12-01-2023.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annexure F - Dadamiya deluxe.pdf25 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for RERA-12012022.pdf12 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf12 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf12 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Certificate 28072022.pdf12 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Certificate 12012023.pdf12 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for RERA-13102022.pdf13 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf13 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for RERA (revised).pdf19 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE.pdf19 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for RERA.pdf15 Jan 2022
Disclosure of sold/ booked inventoryFile: CA Certificate on Project Cost (Form 3).pdf15 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate on Project Cost (Form 3).pdf14 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: 2290599_FurtherCC_signed.pdf25 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf21 Aug 2021
Details of encumbrancesFile: Details of encumbrances.pdf16 Aug 2021
Declaration about Commencement CertificateFile: Format D.pdf16 Aug 2021
Declaration in FORM BFile: Adobe Scan Aug 09, 2021.pdf9 Aug 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE - Model DD.pdf9 Aug 2021
Proforma of Allotment letterFile: Allotment Letter - Model DD.pdf9 Aug 2021
Layout approvalFile: Layout.pdf27 Jul 2021
Building plan approvalFile: Building Plan Approval.pdf27 Jul 2021
PAN CardFile: PAN Card Deluxe.pdf27 Jul 2021
Copy of the legal title reportFile: Title Certificate.pdf27 Jul 2021
Copy of Layout Approval (in case of layout)File: Layout.pdf27 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf27 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Jul 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dadamiyas Deluxe Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla West6,700+ in Mumbai Suburban

2 kmDadamiyas Deluxe ApartmeCompleted 88Lapsed / revoked 87Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 284 registered projects within 2 km.

Builder: Dadamiya Infrastructure & Deluxe Infra

Dadamiya Infrastructure & Deluxe Infra has 1 registration on MahaRERA, including Dadamiyas Deluxe Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Dadamiyas Deluxe Apartment is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dadamiyas Deluxe Apartment?

The registered promoter entity is Dadamiya Infrastructure & Deluxe Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dadamiyas Deluxe Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Dadamiyas Deluxe Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dadamiyas Deluxe Apartment?

The professionals named in the filing: Architect: Mrs Sana N Malik Shaikh; Engineer: M Arif Rupalwala; Chartered Accountant: A R Sodha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dadamiyas Deluxe Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dadamiyas Deluxe Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dadamiyas Deluxe Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.