Home / Browse projects / Mumbai Suburban, Maharashtra / Crystal Armus A to C

Registration lapsed No litigation declared Residential / Group Housing project

Crystal Armus A to C

By Sterling Buildcon Pvt Ltd

RG-MH-11942 · RERA P51800000753 · Last updated on MahaRERA portal: 23 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
27 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 90%
0Complaints at MahaRERAon this registration
Jump to the 209 documents Report an error

Crystal Armus A to C is a Residential / Group Housing project by Sterling Buildcon Pvt Ltd in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000753 on 23 Jul 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameCrystal Armus A to C
  • TypeResidential / Group Housing
  • Location
    • Vaibhav nagar
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000753
  • ReraGenie IDRG-MH-11942

Builder

  • NameSterling Buildcon Pvt Ltd
  • Entity typeCompany
  • CINU45200MH2005PTC153466
  • DirectorsMukesh Maganlal Doshi, Darshan Nitinkumar Dhami
  • Declared earlier projects1 →

Key dates

34 months past promisethis monthRegisteredJul 2017PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jul 2017
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed209 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Crystal Armus Wing ANA260000
Crystal Armus Wing BNA260000
Crystal Armus Wing CNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

Crystal Armus Wing A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Crystal Armus Wing B76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Crystal Armus Wing C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes66%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes66%
Landscaping & Tree PlantingYes66%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes66%
Electrical meter room, sub-station, receiving stationYes66%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
STPYes100%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,261 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Permissible FSI17868.0
Proposed, not sanctioned17,868 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANGAL AASHIRWAD GROUND FLOOR SV ROAD SANTACRUZ WEST MUMBAI 400054

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVishwas Satodia Jivraj Satodia
EngineerJayprakash Rajbhavan Mishra
EngineerSura And Associates
Chartered AccountantSawant & Kadrekar LLP
Chartered AccountantTolia & Associates
Chartered AccountantJW AND ASSOCIATES
Chartered AccountantAmee Dipen Tolia
Chartered AccountantKiran P Tolia
PartnerRole in project
Crystal Estates Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jun 2022

Documents filed209

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 209 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2025 03 31.pdf23 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2024 12 31.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2024 09 30.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2024 03 31.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2024 06 30.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2023 09 30.pdf25 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2023 12 31.pdf25 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C - 2024 03 31.pdf17 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus - A to Wing - June 2023 1.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Crystal Armus A to C Wing - March 2023_compressed.pdf3 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 CRYSTAL ARMUS DEC 2022V.pdf14 Feb 2023
Certificates of CA (Form 3)File: FORM 3 SBPL JUNE 2022VV.pdf7 Feb 2023
Certificates of CA (Form 3)File: FORM 3 SBPL SEPT 2022VV.pdf7 Feb 2023
Certificates of CA (Form 3)File: FORM 3 SBPL DEC 2022VV.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SBPL MARCH 2022.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SBPL JUNE 2022.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SBPL SEPT 2022.pdf13 Jan 2023
Certificates of CA (Form 5)File: FORM 5 STERLING BUILDCON.pdf29 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SBPL DEC 2021 A WING.pdf20 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SBPL DEC 2021 B WING.pdf20 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SBPL DEC 2021 C WING.pdf20 Aug 2022
Certificates of CA (Form 3)File: SBPL FORM 3 DEC 2021.pdf18 Aug 2022
Certificates of CA (Form 3)File: SBPL FORM 3 MARCH 2022.pdf18 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Crystal Armus A.pdf30 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Crystal Armus B.pdf30 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Crystal Armus C.pdf30 Jul 2022
Disclosure of sold/ booked inventoryFile: CRYSTAL ARMUS MAY 2022.pdf14 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SBPL FULL OC FOR WINGS A C.pdf7 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Crystal Armus March 2021.pdf27 May 2022
Disclosure of sold/ booked inventoryFile: Crystal Armus.pdf24 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Combined v_compressed.pdf19 Apr 2022
Declaration about Commencement CertificateFile: SBPL-Declaration about CC_Format D.pdf7 Apr 2022
Declaration about Commencement CertificateFile: SBPL CC UPDATED 2021.pdf1 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SBPL 2019-2020 FORM 5.pdf16 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CRYSTAL ARMUS 31032021.pdf15 Mar 2022
Certificates of CA (Form 3)File: Form 3- SBPL- Mar 2021.pdf23 Feb 2022
Certificates of CA (Form 3)File: Form 3- SBPL- June 21.pdf23 Feb 2022
Certificates of CA (Form 3)File: Form 3- SBPl- Sept 21.pdf23 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A wing June-2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B wing June- 2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: C wing - june-2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A wing Sep- 2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B wing Sep- 2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: C wing Sep- 2021.pdf3 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 A wing march 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 B wing march 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 C wing march 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 A wing June 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 B wing June 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 C wing June 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 A wing September 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 B wing September 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 C wing September 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 A wing December 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 B wing December 2020.pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBPL Form-1 C wing December 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2-A - Wing - March 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2 - B - Wing - March 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2- C - Wing - March 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2 -A - Wing - June 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2-B - Wing - June 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM- 2-C - Wing - June 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 -A - Wing - September 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2-B - Wing - September 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 -C Wing - September 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2- A- Wing - December 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 -B - Wing - December 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2-C - Wing - December 2019.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A- Wing -March 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B - Wing -March 2020 .pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C - Wing - March 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A- Wing -June 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B - Wing - June 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C - Wing - June 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B - Wing - September 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C -Wing - September 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A - Wing - September 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A - Wing - December 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B - Wing - December 2020.pdf30 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C - Wing - December 2020.pdf30 Sep 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Crystal Armus A to C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmCrystal Armus A to CCompleted 116Lapsed / revoked 91Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 310 registered projects within 2 km.

Builder: Sterling Buildcon Pvt Ltd

Sterling Buildcon Pvt Ltd has 1 registration on MahaRERA, including Crystal Armus A to C. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Crystal Armus A to C shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Crystal Armus A to C is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Crystal Armus A to C?

The registered promoter entity is Sterling Buildcon Pvt Ltd, a company as per the filing. Its CIN U45200MH2005PTC153466 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Crystal Armus A to C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Crystal Armus A to C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Crystal Armus A to C?

The professionals named in the filing: Architect: Vishwas Satodia Jivraj Satodia; Engineer: Jayprakash Rajbhavan Mishra; Engineer: Sura And Associates; Chartered Accountant: Sawant & Kadrekar LLP; Chartered Accountant: Tolia & Associates; Chartered Accountant: JW AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Crystal Armus A to C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Crystal Armus A to C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Crystal Armus A to C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.