ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / CRD Gardenia Apartments 2

Completed No litigation declared Residential / Group Housing project

CRD Gardenia Apartments 2

By Dr Chandrashekhar Raghunath Dound

RG-MH-25899 · RERA P99000010008 · Last updated on MahaRERA portal: 19 Dec 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 75%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

CRD Gardenia Apartments 2 is a Residential / Group Housing project by Dr Chandrashekhar Raghunath Dound in Palghar, Maharashtra, registered with MahaRERA as P99000010008 on 23 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2022. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameCRD Gardenia Apartments 2
  • TypeResidential / Group Housing
  • Location
    • Manor Velgaon Road
    • Palghar
    • Velgaon
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000010008
  • ReraGenie IDRG-MH-25899

Builder

  • NameDr Chandrashekhar Raghunath Dound
  • Entity typeIndividual
  • Other registrations12 more →
  • Completed7 of 13
  • No longer live4 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Aug 2017
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA50000
Wing BNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 75%.

Wing A57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes40%
Street LightingYes40%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Open Space4
BuildingOpen SpaceTotal
Wing A22
Wing B22

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,574 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1948.64
Proposed, not sanctioned1,949 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShram Sadhana Trust, Bandra East, Mumbai 400051

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTrupti Jadhav
EngineerVidyadhar Joshi
PartnerRole in project
Dr Chandrashekhar Raghunath Dound-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000001350Dec 2019 → Dec 2020

Reason as filed by the promoterAs per the revision in layout and revised approval, the height of the apartment is increased from Ground + 4 to Ground + 7 stories and the built up area of the apartment is also increased. We are registering the additional area as different project. But due to this revision; the time required for construction of this apartment will increase. Therefore we require extended date of completion to which all our existing customers have given consent.

EXT99000012626Dec 2019 → Dec 2022

Reason as filed by the promoterThe construction work of the building is complete and we have applied for occupation certificate on 29/06/2022. Since the occupation certificate is still not issued by the concerned authorities, we need extension for the project.

EXT99000009831Dec 2019 → Mar 2022

Reason as filed by the promoterDue to the COVID 19 pandemic , it was difficult to continue to the construction work at the same speed as prior to March 2020. The factories & workers of vendors supplying lift, windows and doors were affected and were not able to deliver material in time. Therefore we are requesting to extend the completion period of the project by atleast nine month.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2022

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - APT 2 FY 2022-23.pdf19 Dec 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 APT 2.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22 Apt 2.pdf2 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Certificate Apartment 2.pdf28 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - apt 2.pdf11 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: CRD Gardenia Lotus CHSL, Apt 2, Reg Certificate.pdf11 Oct 2022
Disclosure of sold/ booked inventoryFile: APT 2 DISCLOSURE SOLD UNSOLD.pdf1 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 APT 2 Q4 FY 2021-22.pdf13 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apt 2 phase II From 2 (seen Regulation 3) Q4 FY 21-22.pdf13 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apt 2 From 2 Q4 FY21-22.pdf13 Aug 2022
Certificates of CA (Form 5)File: form 5 - apt 2 phase ii.pdf13 Aug 2022
Certificates of CA (Form 5)File: Form 5 - apt 2.pdf13 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q1 FORM 1.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q 1 compressed.pdf14 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: NA Order 020119.pdf2 Jul 2021
Declaration about Commencement CertificateFile: CRD Gardenia Apartment 2.pdf2 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Apartment 2 Scanned.pdf16 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-2-March 20.pdf14 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-2-March 21.pdf14 Jun 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold flats_Bldg 2.pdf14 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: APT 2 FY 2018 19.pdf28 Dec 2019
Building plan approvalFile: NA Order 020119.pdf19 Jan 2019
Layout approvalFile: Layout.pdf19 Jan 2019
Layout approvalFile: Bldg 2.pdf19 Jan 2019
Copy of Layout Approval (in case of layout)File: Layout.pdf19 Jan 2019
Copy of Layout Approval (in case of layout)File: Bldg 2.pdf19 Jan 2019
Building Plan Approval (IOD)File: NA Order 020119.pdf19 Jan 2019
Certificates of CA (Form 5)File: CRD Form 5 Apt 2.pdf26 Oct 2018
Proforma of Allotment letterFile: Agreement for sale draft.pdf2 Oct 2018
Building plan approvalFile: NA order-compressed.pdf30 Jul 2017
Building Plan Approval (IOD)File: NA order-compressed.pdf30 Jul 2017
Layout approvalFile: Layout.pdf29 Jul 2017
Layout approvalFile: BLDG 2 3.pdf29 Jul 2017
PAN CardFile: PAN.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate 48-1A-1B.pdf29 Jul 2017
Details of encumbrancesFile: encumberance 2.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: BLDG 2 3.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf29 Jul 2017
Declaration in FORM BFile: Form B-2.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-2.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-2.pdf29 Jul 2017
Certificates of CA (Form 3)File: CRD Gardenia Apartmens 2.pdf29 Jul 2017
Proforma of Allotment letterFile: Declaration regading draft agreements.pdf29 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 36 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CRD Gardenia Apartments 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palghar3,200+ in Palghar

2 kmCRD Gardenia Apartments Completed 6Lapsed / revoked 4Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: Dr Chandrashekhar Raghunath Dound

Dr Chandrashekhar Raghunath Dound has 13 registrations on MahaRERA, including CRD Gardenia Apartments 1 and CRD Gardenia Apartments 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if CRD Gardenia Apartments 2 is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CRD Gardenia Apartments 2?

The registered promoter entity is Dr Chandrashekhar Raghunath Dound, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CRD Gardenia Apartments 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CRD Gardenia Apartments 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CRD Gardenia Apartments 2?

The professionals named in the filing: Architect: Trupti Jadhav; Engineer: Vidyadhar Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CRD Gardenia Apartments 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CRD Gardenia Apartments 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CRD Gardenia Apartments 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.