Home / Browse projects / CLOVER GALLERIA
CLOVER GALLERIA
By CLOVERBLAKEFIELD REALTY LLP
RG-MH-44520 · RERA P52100019387 · Last updated on MahaRERA portal: 25 Aug 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 47 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CLOVER GALLERIA is a Commercial project by CLOVERBLAKEFIELD REALTY LLP in Kharadi near World Trade Centre, 411014, registered with MahaRERA as P52100019387 on 29 Jan 2019. The registration is recorded completed; possession was promised by 15 Nov 2026. The completion date has moved by 47 months from the original filing. 40 of the 42 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameCLOVER GALLERIA
- TypeCommercial
- Location
- 36 m wide DP road
- Kharadi near World Trade Centre
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019387
- ReraGenie IDRG-MH-44520
Builder
- NameCLOVERBLAKEFIELD REALTY LLP
- Entity typePartnership
- GSTIN27AARFB6499B1Z1
- PartnerNikhil Agarwal
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Jan 2019
- Promised completion15 Nov 2026
- Revised completionRevised to 15 Nov 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed83 files
Current status
Figures as on 25 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C1 | NA | 4 | 3 | 0 | 42 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 95%.
C1: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 95% |
| Plinth | 100% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed60
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C1 | NA | Rs 7.88 cr | Rs 7.63 cr |
| - | NA | Rs 1 | Rs 1 |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Satish Joshi |
| Architect | RAMESHWRI SANGANI |
| Engineer | Consultants & Engineers |
| Engineer | VASTECH & CONSULTANT & ENGINEERS LLP |
| Chartered Accountant | Param & Co |
| Partner | Role in project |
|---|---|
| CLOVERBLAKEFIELD REALTY LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCovid-19 pandemic lockdown has been the main reason for the delay to deliver the project. Due to the pandemic, non-availability of materials and migration of the workers has been the main reason. However we are about to complete the project and all the required NOC for applying completion except FIRE NOC are received. We are going to apply for completion / occupation certificate within a month. Requesting you to kindly issue the extension for the completion of the balance work for the period of 90 days.
Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 18/09/2023 and we have also initiated the process for the possession as well. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure a
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Nov 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Jan 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Nov 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Nov 2024
Documents filed83
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 25 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_FY_ 2023-2024.pdf | 25 Aug 2026 |
| Occupational CertificateFile: Occupancy Certificate.pdf | 25 Aug 2026 |
| Occupational CertificateFile: OC Verification Mail Screenshot.pdf | 25 Aug 2026 |
| Occupational CertificateFile: Commencement Certificate.pdf | 25 Aug 2026 |
| Occupational CertificateFile: CC Plan 1.pdf | 25 Aug 2026 |
| Occupational CertificateFile: CC Plan 2.pdf | 25 Aug 2026 |
| Occupational CertificateFile: Declaration For Full OC.pdf | 25 Aug 2026 |
| Certificates of CA (Form 3)File: Jan24 Mar24.pdf | 17 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: F5.pdf | 17 Feb 2025 |
| PAN CardFile: PAN.pdf | 10 Feb 2025 |
| Certificates of CA (Form 3)File: F3.pdf | 7 Feb 2025 |
| Certificates of CA (Form 3)File: F3.pdf | 7 Feb 2025 |
| Certificates of CA (Form 3)File: F3.pdf | 7 Feb 2025 |
| Proforma of Agreement for saleFile: Galleria-OFA-final draft.pdf | 7 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: F4.pdf | 4 Dec 2024 |
| Other - TechnicalFile: PMC.pdf | 4 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: 4.pdf | 5 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: soc.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 5 Nov 2024 |
| Other - TechnicalFile: FORM 4 FOR C1_merged.pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 11 May 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Clover Galleria.pdf | 25 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 31 Dec 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 31 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate compressed.pdf | 9 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate compressed.pdf | 9 Aug 2022 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 22 Jun 2022 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 22 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 16-04-2022.pdf | 9 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate 16-04-2022.pdf | 9 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 16-01-2022.pdf | 6 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Form 2 15-01-2022.pdf | 6 Apr 2022 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 9 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect April 2021.pdf | 23 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect July 2021.pdf | 23 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Form 2 April 2021_compressed.pdf | 23 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Form 2 July 2021_compressed.pdf | 23 Aug 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Application to Co-operative 2021-07-23.pdf | 20 Aug 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 13 Aug 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 13 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5-CB.pdf | 13 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Clover Galleria.pdf | 6 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf | 3 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2a - 1 ( 2019-2020).pdf | 15 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2a- 1 ( 2020-2021).pdf | 15 Jul 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 8 Jun 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 26 May 2021 |
| Certificates of CA (Form 3)File: CA Certificate-blake.pdf | 12 May 2021 |
| Certificates of CA (Form 3)File: Clover Blakefield_Mar 2021_1.pdf | 29 Apr 2021 |
| Details of Restarting of Construction work post lockdownFile: COVID 19 - LETTER.pdf | 29 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: From 5 Clover Blakefield.pdf | 5 Apr 2020 |
| Certificates of CA (Form 3)File: CA cloverblakefield.pdf | 18 Feb 2020 |
| Certificates of CA (Form 3)File: clover blakefield 3006 CAA.pdf | 9 Dec 2019 |
| Certificates of CA (Form 3)File: clover blakefield 3009 CAA.pdf | 9 Dec 2019 |
| Certificates of CA (Form 3)File: CLOVER BLAKEFIELD CA.pdf | 23 Jul 2019 |
| Layout approvalFile: LAYOUT DWG - COMMERCIAL BLDG.pdf | 23 Jan 2019 |
| Copy of Layout Approval (in case of layout)File: LAYOUT DWG - COMMERCIAL BLDG.pdf | 23 Jan 2019 |
| Declaration in FORM BFile: Decalartion Form B.pdf | 23 Jan 2019 |
| Details of encumbrancesFile: Encumbrance certificate.pdf | 5 Jan 2019 |
| Building plan approvalFile: commercial building plans.pdf | 20 Nov 2018 |
| Copy of the legal title reportFile: Tital search report.pdf | 20 Nov 2018 |
| Building Plan Approval (IOD)File: commercial building plans.pdf | 20 Nov 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 83 filed documents as one ZIP, foldered, with a manifest
Keep CLOVER GALLERIA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kharadi near World Trade Centre
Filed coordinates, straight-line distance. 102 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: CLOVERBLAKEFIELD REALTY LLP
CLOVERBLAKEFIELD REALTY LLP has 1 registration on MahaRERA, including CLOVER GALLERIA. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if CLOVER GALLERIA is delayed beyond 15 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CLOVER GALLERIA?
The registered promoter entity is CLOVERBLAKEFIELD REALTY LLP, a partnership as per the filing. Its GSTIN 27AARFB6499B1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CLOVER GALLERIA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CLOVER GALLERIA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CLOVER GALLERIA?
The professionals named in the filing: Architect: Satish Joshi; Architect: RAMESHWRI SANGANI; Engineer: Consultants & Engineers; Engineer: VASTECH & CONSULTANT & ENGINEERS LLP; Chartered Accountant: Param & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CLOVER GALLERIA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback