Home / Browse projects / Palghar, Maharashtra / CENTRUM VILLAS

Registered No litigation declared Residential / Group Housing project

CENTRUM VILLAS

By SUN REALTORS

RG-MH-64674 · RERA P99000050756 · Last updated on MahaRERA portal: 3 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
44 of 165Construction stages doneacross 15 buildings; furthest along: Staircases, 90%
10 of 15Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 102 documents Report an error

CENTRUM VILLAS is a Residential / Group Housing project by SUN REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000050756 on 28 Apr 2023. Possession is promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 5 of the 15 units on this registration are recorded sold or booked, and 44 of 165 construction stages are filed complete.

At a glance

Project

  • NameCENTRUM VILLAS
  • TypeResidential / Group Housing
  • Location
    • PALGHAR BOISAR ROAD
    • PALGHAR West
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000050756
  • ReraGenie IDRG-MH-64674

Builder

  • NameSUN REALTORS
  • Entity typePartnership
  • GSTIN27ACRFS5787R1ZM
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersBHAVESH SOHANLAL BAFNA, SUKANRAJ GULABCHAND PARMAR
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2023
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2025)
  • Buildings15 building records
  • Documents filed102 files

Current status

33%5 of 15 units booked
70.9%Work done, per cost certificate

Figures as on 3 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building no-18 Type-E1NA11101
Building No-17 Type-E1NA11101
Building No-16 Type-E1NA11101
Building No-15 Type-E1NA11101
Building No-14 Type-E1NA11101
Building No-13 Type-E1NA11101
Building no-12 Type- INA11101
Building No-11 Type-ENA11101
Building No - 10 Type - ENA11101
Building No - 9 Type - FNA11101
Building No - 8 Type - GNA11101
Building No -07 Type - HNA11101
Building No-06 Type-DNA11101
Building No-09 Type-F1NA11101
Building No-05 Type-DNA11101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building15

As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

44 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Staircases, at 90%.

Building no-18 Type-E162%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-17 Type-E161%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-16 Type-E161%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-15 Type-E164%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-14 Type-E161%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-13 Type-E160%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building no-12 Type- I53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-11 Type-E53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No - 10 Type - E41%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No - 9 Type - F0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No - 8 Type - G53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No -07 Type - H43%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-06 Type-D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-09 Type-F10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No-05 Type-D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Open Space16
BuildingOpen SpaceTotal
Building no-18 Type-E111
Building No-17 Type-E111
Building No-16 Type-E111
Building No-15 Type-E111
Building No-14 Type-E111
Building No-13 Type-E111
Building no-12 Type- I11
Building No-11 Type-E11
Building No - 10 Type - E11
Building No - 9 Type - F22
Building No - 8 Type - G11
Building No -07 Type - H11
Building No-06 Type-D11
Building No-09 Type-F111
Building No-05 Type-D11

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,478 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Dec 2025
LandownerVillageDistrict
Pralhad Prabhakar KadamPalghar Palghar
Rajendra Prabhakar KadamPalghar Palghar
Ravindra Prabhakar KadamPalghar Palghar

Approvals and building plan

Sanctioning authorityPALGHAR MUNCIPAL COUNCIL
Permissible FSI3058.63
Proposed, not sanctioned3,059 sq m
Buildings approved15
Buildings sanctioned15

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear Panch Batti, Palghar West
Estimated costRs 6.06 cr
Cost incurredRs 4.29 cr
Work done70.87%
BuildingWingEstimatedIncurred
Building No -07 Type - HNARs 48.20 lakhRs 45.79 lakh
Building no-12 Type- INARs 41.63 lakhRs 39.55 lakh
Building No - 8 Type - GNARs 40.37 lakhRs 38.35 lakh
Building No-06 Type-DNARs 40.25 lakhRs 4.43 lakh
Building No-05 Type-DNARs 40.25 lakhRs 4.43 lakh
Building no-18 Type-E1NARs 39.04 lakhRs 37.08 lakh
Building No-17 Type-E1NARs 39.04 lakhRs 37.08 lakh
Building No-16 Type-E1NARs 39.04 lakhRs 37.08 lakh
Building No-15 Type-E1NARs 39.04 lakhRs 39.04 lakh
Building No-14 Type-E1NARs 39.04 lakhRs 37.08 lakh
Building No-13 Type-E1NARs 39.04 lakhRs 37.08 lakh
Building No-11 Type-ENARs 39.04 lakhRs 37.08 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNishant Patil
EngineerHiren M Tanna
EngineerTEJAS V CHAUDHARI
EngineerHIMANSHU J RAUT
Chartered AccountantZenith M Jain
Chartered AccountantNANDISH SALOT SALOT
Chartered AccountantN J Shah & Associates LLP
PartnerRole in project
SUN REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31122519195Dec 2025 → Dec 2026

Reason as filed by the promoterWe are committed to completing the project at the earliest and expect to wrap up all pending tasks within the extended period. We assure MahaRERA that we remain fully compliant with regulations and continue to prioritize the interests of homebuyers

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed102

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1-Jun26_compressed.pdf3 Aug 2026
Withdrawal Update Form 1File: Form-1-Jun26_compressed.pdf3 Aug 2026
Withdrawal Update Form 1File: Form-1-Jun26_compressed.pdf3 Aug 2026
Withdrawal Update Form 2File: Centrum Villas - Jun 26 - Form 2.pdf3 Aug 2026
Withdrawal Update Form 2File: Centrum Villas - Jun 26 - Form 2.pdf3 Aug 2026
Withdrawal Update Form 2File: Centrum Villas - Jun 26 - Form 2.pdf3 Aug 2026
Withdrawal Update Form 3File: JUN26-FORM-3-CENTRUM VILLAS_compressed.pdf3 Aug 2026
Withdrawal Update Form 3File: JUN26-FORM-3-CENTRUM VILLAS_compressed.pdf3 Aug 2026
Withdrawal Update Form 3File: JUN26-FORM-3-CENTRUM VILLAS_compressed.pdf3 Aug 2026
Form 3File: JUN24-FORM3-CENTRUM VILLAS.pdf31 Jul 2026
Disclosure of Sold and Booked InventoryFile: JUN24-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Jul 2026
Form 2File: JUN24-FORM2-CENTRUM VILLAS.pdf31 Jul 2026
Form 1File: FORM1-CENTRUM VILLAS.pdf31 Jul 2026
Form 1File: FORM1-CENTRUM VILLAS.pdf31 Jul 2026
Form 2File: SEP24-FORM2-CENTRUM VILLAS.pdf31 Jul 2026
Form 3File: SEP24-FORM3-CENTRUM VILLAS.pdf31 Jul 2026
Disclosure of Sold and Booked InventoryFile: SEP24-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Jul 2026
Form 1File: FORM1-CENTRUM VILLAS.pdf31 Jul 2026
Form 2File: DEC24-FORM2-CENTRUM VILLAS.pdf31 Jul 2026
Form 3File: DEC24-FORM3-CENTRUM VILLAS.pdf31 Jul 2026
Disclosure of Sold and Booked InventoryFile: DEC24-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Jul 2026
Withdrawal Update Form 1File: Centrum Villas Form1_30042026.pdf30 Apr 2026
Withdrawal Update Form 2File: MAR26-FORM2-CENTRUM VILLAS.pdf30 Apr 2026
Withdrawal Update Form 3File: MAR26-CENTRUM VILLAS-FORM3-com.pdf30 Apr 2026
Withdrawal Update Form 1File: Dec25--CENTRUM VILLA-FORM1.pdf3 Feb 2026
Withdrawal Update Form 2File: Dec25-Centrum Villas-Form2.pdf3 Feb 2026
Withdrawal Update Form 3File: Dec25-Centrum Villas-Form3.pdf3 Feb 2026
Form 1File: MAR25-FORM1-CENTRUM VILLAS.pdf31 Dec 2025
Form 2File: MAR25-FORM2-CENTRUM VILLAS.pdf31 Dec 2025
Form 3File: MAR25-FORM3-CENTRUM VILLAS.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: MAR25-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Dec 2025
Form 2File: DEC23-FORM2-CENTRUM VILLAS.pdf31 Dec 2025
Form 3File: DEC23-FORM3-CENTRUM VILLAS.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: DEC23-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Dec 2025
Form 1File: DEC23-FORM1-CENTRUM VILLAS.pdf31 Dec 2025
Form 1File: SEP23-FORM1-CENTRUM VILLAS.pdf31 Dec 2025
Form 2File: SEP23-FORM2-CENTRUM VILLAS.pdf31 Dec 2025
Form 3File: SEP23-FORM3-CENTRUM VILLAS.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: SEP23-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Dec 2025
Form 1File: edited_MAR24-FORM1-CENTRUM VILLAS.pdf31 Dec 2025
Form 2File: MAR24-FORM2-CENTRUM VILLAS.pdf31 Dec 2025
Form 3File: MAR24-FORM3-CENTRUM VILLAS.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: MAR24-SOLDUNSOLD-CENTRUM VILLAS.pdf31 Dec 2025
Withdrawal Update Form 1File: JUN25-FORM1-CENTRUM VILLAS_compressed.pdf30 Dec 2025
Withdrawal Update Form 1File: Sep25-Form1-Centrum Villas.pdf30 Dec 2025
Withdrawal Update Form 1File: Sep25-Form1-Centrum Villas.pdf30 Dec 2025
Withdrawal Update Form 2File: edited_FORM 2 JUN 25_30122025.pdf30 Dec 2025
Withdrawal Update Form 2File: edited_FORM 2 JUN 25_30122025.pdf30 Dec 2025
Withdrawal Update Form 2File: villas Form2 SEP 25 -1.pdf30 Dec 2025
Withdrawal Update Form 3File: JUNE25-FORM3-CENTRUM VILLAS_27122025.pdf30 Dec 2025
Withdrawal Update Form 3File: SEP25-FORM3-CENTRUM VILLAS_27122025.pdf30 Dec 2025
Withdrawal Update Form 3File: SEP25-FORM3-CENTRUM VILLAS_27122025.pdf30 Dec 2025
Form 2A (FY 2023-2024)File: Form2A-Centrum Villas-23-24.pdf30 Dec 2025
Form 2A (FY 2024-2025)File: Form2A-SUN Realtors-24-25.pdf30 Dec 2025
Form 5 (FY 2023-2024)File: FORM5-CERNTRUM VILLAS23-24.pdf30 Dec 2025
Form 5 (FY 2024-2025)File: FORM5-CERNTRUM VILLAS24-25.pdf30 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VILLAS FORM 1 MAR 25_11zon.pdf6 May 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CENTRUM VILLAS DEC24.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: CENTRUM VILLAS SOLD UNSOLD_000111.pdf23 Jul 2024
Disclosure of sold/ booked inventoryFile: CENSTRUM VILLAS SOLD UNSOLD _000051.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Centrum Villas CA Certificate _000135.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTRUM VILLAS ART CERTIFICATE _000078.pdf23 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Centrum Villas Art Certificate _000020.pdf31 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE _000161.pdf20 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure Rajesh Bafna.pdf15 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure Bhavesh Bafna.pdf15 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: parmar.pdf15 Apr 2023
Details of encumbrances concerned to FinanceFile: FINACE_000152.pdf12 Apr 2023
Details of encumbrances concerned to LegalFile: FINACE_000152.pdf12 Apr 2023
Copy of the legal title reportFile: Title Report.pdf11 Apr 2023
CERSAI detailsFile: CERSAI_Search_Report_200265855251_For_Asset_Based_Search_11_04_2023_14_59_02_027.pdf11 Apr 2023
Details of encumbrances concerned to FinanceFile: DECLARATION_000140.pdf3 Apr 2023
Details of encumbrances concerned to LegalFile: DECLARATION_000140.pdf3 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ANNEXURE A_000141.pdf3 Apr 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Villas_000106.pdf28 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: new_SUN Comencement Certificate_compressed.pdf23 Feb 2023
Building plan approvalFile: typeD.pdf19 Feb 2023
Building plan approvalFile: typeE.pdf19 Feb 2023
Building plan approvalFile: typeE1.pdf19 Feb 2023
Building plan approvalFile: typeF.pdf19 Feb 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
CENTRUM BUSINESS PARKP99000033071Palghar West, Palghar-Feb 2022CompletedDec 2024Late, Apr 2025
BAFNA CENTRUM PHASE-1PALGHAR OPP MIDC PALGHAR BOIAR ROAD1-CompletedDec 2023Dec 2022

How this compares with Palghar

33%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CENTRUM VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR West3,200+ in Palghar

2 kmCENTRUM VILLASCompleted 28Lapsed / revoked 14Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: SUN REALTORS

SUN REALTORS has 5 registrations on MahaRERA, including BAFNA CENTRUM PHASE-1 and SHIVAALIK PARK. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if CENTRUM VILLAS is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CENTRUM VILLAS?

The registered promoter entity is SUN REALTORS, a partnership as per the filing. Its GSTIN 27ACRFS5787R1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CENTRUM VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CENTRUM VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CENTRUM VILLAS?

The professionals named in the filing: Architect: Nishant Patil; Engineer: Hiren M Tanna; Engineer: TEJAS V CHAUDHARI; Engineer: HIMANSHU J RAUT; Chartered Accountant: Zenith M Jain; Chartered Accountant: NANDISH SALOT SALOT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CENTRUM VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CENTRUM VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CENTRUM VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.