CALLISTO

By NAYAN BUILDERS

RG-MH-20976 · RERA P52100009925 · Last updated on MahaRERA portal: 18 Jan 2025

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
10 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 90%
10Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

CALLISTO is a Others project by NAYAN BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100009925 on 22 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameCALLISTO
  • TypeOthers
  • Location
    • UNDRI ROAD
    • NEAR BISHOPS SCHOOL
    • UNDRI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100009925
  • ReraGenie IDRG-MH-20976

Builder

  • NameNAYAN BUILDERS
  • Entity typePartnership
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings4 building records
  • Documents filed86 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING BNA100000
BUILDING ANA100000
BUILDING CNA30000
BUILDING DNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 90%.

BUILDING B78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
BUILDING A78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
BUILDING C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes25%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered3
Open Space53
BuildingClosed/CoveredOpen SpaceTotal
BUILDING B12021
BUILDING A11314
BUILDING C11516
BUILDING D055

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,695 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHIVNAGAR COOPERATIVE HOUSING SOCIETY LTDUNDRIPune

Approvals and building plan

Permissible FSI4985.48
Proposed, not sanctioned4,281 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor, Aditya Business Centre, Nibm Road, Kondhwa Khurd, Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR ATIT ADMULWAR
EngineerMR DEVDATTA MADHAV HERLEKAR
PartnerRole in project
NAYAN BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017994Dec 2023 → Dec 2024

Reason as filed by the promoterRespected Sir / Madam, Due to covid scenario and labour's problems, the project will not be completed in due course of time. As on date the project is almost 75% completed. We require further 1 year to complete the project henceforth. Please approve the our request and give us the extension of 1 year. Thanks in advance.

EXT52100025242Dec 2023 → Dec 2026

Reason as filed by the promoterRespected Sir, Due to labour problems, we want to extend completion date of our project.

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC005000000096234Mr.Dabi Manohar GovindramNayan Builder23/11/2021
CC005000000167351Geeta Sudhakar PolNayan Builders30/08/2022
CC005000000371004Juliet Margaret Dsouzam/s Nayan Builders thruogh partner Amit Surendra Sing05/06/2024
CC005000000471177Mr. Kishor Ramchandra KatkarM/s. Nayan Builders Through its Partners 1. Mr. Amit Surendra Singh 2. Mr. Ranjan Prasad Verma12/07/2024
CC005000000471286Mr. Ajay Chotelal MaheshwariM/s. Nayan Builders Through its Partners 1. Mr. Amit Surendra Singh 2. Mr. Ranjan Prasad Verma12/07/2024
CC005000000471378Pravin Eknath PawarM/s. Nayan Builders Through its Partners 1. Mr. Amit Surendra Singh 2. Mr. Ranjan Prasad Verma12/08/2024
CC005000000471536Nitin Manohar KarandeM/s. Nayan Builders Through its Partners 1. Mr. Amit Surendra Singh 2. Mr. Ranjan Prasad Verma12/08/2024
CC12501233sameerkhan pathanNAYAN BUILDERS14/04/2025
CC12501296JULIET MARGARET DSOUZANAYAN BUILDERS19/04/2025
CC12503013JAMES DAVID PATELNAYAN BUILDERS26/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B New.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM - 3 -CA - 010125.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM - 3 -CA - 01 10 24.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM 3 CA 01 07 24.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM 3 0104 24.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM 3 CA 010124.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM 3 CA 01 10 23.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM - 3 -CA - 01 07 23.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 2 Engineers Certificate 01 07 23.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM 3 CA 01 04 23.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 01 04 23.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 01 07 23.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 01 10 23.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 010124.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 01 04 24.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 01 07 24.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 0110 24.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 010125.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure sold unsold.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 31 03 24.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 New.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - 310318.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 310319.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 310320.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 310321.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 310322.pdf17 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - Form 2.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - New.pdf16 Feb 2024
Layout approvalFile: 1 Plan.pdf8 Feb 2024
Building plan approvalFile: 2 Plan.pdf8 Feb 2024
Building plan approvalFile: 3 Plan.pdf8 Feb 2024
Building plan approvalFile: 4 Plan.pdf8 Feb 2024
Building plan approvalFile: 5 Plan.pdf8 Feb 2024
Building plan approvalFile: 5 Plan.pdf8 Feb 2024
Building plan approvalFile: 6 Plan.pdf8 Feb 2024
Copy of Layout Approval (in case of layout)File: 1 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 2 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 3 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 4 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 5 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 5 Plan.pdf8 Feb 2024
Building Plan Approval (IOD)File: 6 Plan.pdf8 Feb 2024
Declaration about Commencement CertificateFile: Declaration CC.pdf8 Feb 2024
Declaration in FORM BFile: Form B.pdf8 Feb 2024
CERSAI detailsFile: Cersai Report.pdf8 Feb 2024
Disclosure of sold/ booked inventoryFile: Circular No 29.pdf8 Feb 2024
Certificates of CA (Form 3)File: FORM - 3 -CA - New.pdf8 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure - Amit.pdf8 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure - Ranjan.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 310323.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 310323.pdf8 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Bank.pdf8 Feb 2024
Declaration in FORM BFile: Form-B Affidavit 16122023.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A Quality Assurance Certificate 31032020.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A Quality Assurance Certificate 31032021.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A Quality Assurance Certificate 31032022.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Quality Assurance Certificate 31032023.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Details.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - 310318.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 310319.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 310320.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 310321.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 310322.pdf18 Feb 2023
Declaration in FORM BFile: FORM B.pdf17 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: 1.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: 4.pdf10 Apr 2018
Details of encumbrancesFile: Certificate of Nayan Builders.pdf31 Jul 2017
Declaration in FORM BFile: Nayan Builders Form B.pdf31 Jul 2017
Building plan approvalFile: WING B EVEN.pdf30 Jul 2017
Building plan approvalFile: WING B.pdf30 Jul 2017
Building plan approvalFile: WING A EVEN.pdf30 Jul 2017
Building plan approvalFile: AA_230_MD_001_R15_TP_30-05-2014-002 (6 files merged)-5.pdf30 Jul 2017
Layout approvalFile: LAYOUT PLAN.pdf30 Jul 2017
PAN CardFile: Nayan Builders.pdf30 Jul 2017
Copy of the legal title reportFile: Search Tital 1-2.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf30 Jul 2017
Building Plan Approval (IOD)File: AA_230_MD_001_R15_TP_30-05-2014-002 (6 files merged)-5.pdf30 Jul 2017
Building Plan Approval (IOD)File: WING A EVEN.pdf30 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CALLISTO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR BISHOPS SCHOOL13,700+ in Pune

2 kmCALLISTOCompleted 101Lapsed / revoked 32Other 96Dot size: filed unitsN

Filed coordinates, straight-line distance. 229 registered projects within 2 km.

Builder: NAYAN BUILDERS

Nayan Builders has 2 registrations on MahaRERA, including Mahavir Galaxy and CALLISTO. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if CALLISTO is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CALLISTO?

The registered promoter entity is NAYAN BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CALLISTO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CALLISTO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CALLISTO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CALLISTO?

The professionals named in the filing: Architect: MR ATIT ADMULWAR; Engineer: MR DEVDATTA MADHAV HERLEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CALLISTO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CALLISTO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CALLISTO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.