Home / Browse projects / BRAMHA SKYCITY PHASE 3
BRAMHA SKYCITY PHASE 3
RG-MH-17533 · RERA P52100029056 · Last updated on MahaRERA portal: 1 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BRAMHA SKYCITY PHASE 3 is a Residential / Group Housing project by BRAMHA MULTICON PVT LTD in DHANORI, 411014, registered with MahaRERA as P52100029056 on 23 Apr 2021. Possession is promised by 1 Apr 2027. The completion date has moved by 12 months from the original filing. 71 of the 92 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameBRAMHA SKYCITY PHASE 3
- TypeResidential / Group Housing
- Location
- DHANORI VILLAGE ROAD
- DHANORI
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029056
- ReraGenie IDRG-MH-17533
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Apr 2021
- Promised completion1 Apr 2027
- Revised completionRevised to 1 Apr 2027 (originally 1 Apr 2026)
- Buildings2 building records
- Documents filed194 files
Current status
Figures as on 1 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| S1 | NA | 16 | 14 | 46 | 0 | 46 |
| S2 | NA | 16 | 14 | 46 | 0 | 46 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.
S195%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
S276%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed47
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| S1 | 46 | 46 |
| S2 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VISHNU CO-OPERATIVE HOUSING SOCIETY LIMITED | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| S1 | NA | Rs 12.21 cr | Rs 9.46 cr |
| S2 | NA | Rs 12.21 cr | Rs 9.46 cr |
| - | NA | Rs 4.31 cr | Rs 3.34 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Cubic Architects Associates |
| Engineer | imran shaik |
| Chartered Accountant | ASAK & Co |
| Chartered Accountant | Patel and Sharma Chartered Accountants |
| Chartered Accountant | RSVA & CO |
| Chartered Accountant | AGARWAL SARAWGI AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| BRAMHA MULTICON PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project was initiated in the period following the outbreak of the COVID-19 pandemic; however, construction activities from March 2020 to February 2022 were severely disrupted due to nationwide lockdowns, restrictions on movement, and the implementation of mandatory health and safety protocols. These unprecedented circumstances led to prolonged site inactivity and significantly reduced work progress, primarily owing to disruptions in the availability of both skilled and unskilled labour, as well as interruptions in the supply chain for construction materials and equipment. In the post-pande
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603338 | Nishant Ranjan | BRAMHA MULTICON PVT LTD | 01/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Apr 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 Apr 2027
Documents filed194
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 194 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: BMPL ARCHITECT CERTIFICATE 31-03-2026.pdf | 1 Aug 2026 |
| Withdrawal Update Form 2File: BMPL FORM-2.pdf | 1 Aug 2026 |
| Withdrawal Update Form 3File: BMPL FORM-3.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: form 1 dec 25 f_0001.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: form 1 dec 25 f_0001.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2 dec_0001.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2 dec_0001.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Bramha multicon pvt ltd 1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Bramha multicon pvt ltd 1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: form 1 june 25 f_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: form 1 sep 25 f_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: form 1 dec 25 f_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: form 1 dec 25 f_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2_0001 june 25.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2 sep_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2 sep_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: sky city form 2 sep_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Bramha Multicon pvt ltd 3.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Bramha multicon pvt ltd 2.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Bramha multicon pvt ltd 1.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Bramha multicon pvt ltd 1.pdf | 24 Jan 2026 |
| Form 2A (FY 2021-2022)File: form 2a 21-22 new_0001.pdf | 17 Jan 2026 |
| Form 2A (FY 2022-2023)File: form 2a 22-23 new_0001.pdf | 17 Jan 2026 |
| Form 2A (FY 2023-2024)File: form 2a 23-24 new_0001.pdf | 17 Jan 2026 |
| Form 2A (FY 2024-2025)File: form 2a 24-25 new_0001.pdf | 17 Jan 2026 |
| Form 1File: FORM 1.pdf | 12 Jan 2026 |
| Form 2File: form 2_0001.pdf | 12 Jan 2026 |
| Form 3File: FORM 3.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Jan 2026 |
| Form 1File: FORM 1.pdf | 12 Jan 2026 |
| Form 2File: form 2_0001.pdf | 12 Jan 2026 |
| Form 3File: FORM 3.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Jan 2026 |
| Form 5 (FY 2021-2022)File: form 5 21-22.pdf | 12 Jan 2026 |
| Form 5 (FY 2022-2023)File: form 5 2022-23.pdf | 12 Jan 2026 |
| Form 5 (FY 2023-2024)File: form 5 23-24.pdf | 12 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: Form 3 Signed.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 10 Jan 2026 |
| Form 2File: FORM 2.pdf | 10 Jan 2026 |
| Form 3File: FORM 3.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 10 Jan 2026 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| BRAMHA SKYCITY PHASE- 1 | SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE | 270 | Completed | Sep 2016 | Sep 2016 |
| BRAMHA SKYCITY PHASE- 1 | SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE | 253 | Completed | Sep 2016 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 194 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BRAMHA SKYCITY PHASE 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHANORI
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: BRAMHA MULTICON PVT LTD
BRAMHA MULTICON PVT LTD has 2 registrations on MahaRERA, including BRAMHA SKYCITY and BRAMHA SKYCITY PHASE 3. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What are my rights if BRAMHA SKYCITY PHASE 3 is delayed beyond 1 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BRAMHA SKYCITY PHASE 3?
The registered promoter entity is BRAMHA MULTICON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BRAMHA SKYCITY PHASE 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against BRAMHA SKYCITY PHASE 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for BRAMHA SKYCITY PHASE 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BRAMHA SKYCITY PHASE 3?
The professionals named in the filing: Architect: Cubic Architects Associates; Engineer: imran shaik; Chartered Accountant: ASAK & Co; Chartered Accountant: Patel and Sharma Chartered Accountants; Chartered Accountant: RSVA & CO; Chartered Accountant: AGARWAL SARAWGI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BRAMHA SKYCITY PHASE 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback