BRAMHA SKYCITY
RG-MH-20384 · RERA P52100005193 · Last updated on MahaRERA portal: 12 Jan 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BRAMHA SKYCITY is a Residential / Group Housing project by BRAMHA MULTICON PVT LTD in DHANORI, 411014, registered with MahaRERA as P52100005193 on 10 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameBRAMHA SKYCITY
- TypeResidential / Group Housing
- Location
- DHANORI KALWAD
- DHANORI
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100005193
- ReraGenie IDRG-MH-20384
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Aug 2017
- Promised completion30 Dec 2022
- Revised completionNone
- Buildings1 building record
- Documents filed90 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| L | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
L: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | REZA KABUL ARCHITECTS PVT LTD |
| Architect | SUNIL DIGAMBAR VARTA & ASSOCIATES |
| Engineer | JW CONSULTANTS LLP |
| Partner | Role in project |
|---|---|
| BRAMHA MULTICON PVT LTD | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000023105 | DRISHTI NAVIN JETHWANI AND NAVIN JETHWANI | Bramha Multicon Private Limited through its Director MR VISHAL SURENDRAKUMAR AGARWAL | 08/07/2019 |
| CC005000000023138 | SANGEETA KARTAR BUDHRANI | BRAMHA MULTICON PRIVATE LTD THROUGH ITS DIRECTOR MR VISHAL SURENDRAKUMAR AGARWAL | 08/07/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 May 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Aug 2020
Documents filed90
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Proforma of Agreement for saleFile: 6 Proforma of Allotment letter.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: 1 Skyciti RERA CA 30-06-2021_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 2 Skyciti RERA CA 30-09-2021_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 3 Skyciti RERA CA 31-12-2021_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 4 Skyciti RERA CA 31-03-2022_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 5 Skyciti RERA CA 30-06-2022_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 6 Skyciti RERA CA 30-09-2022_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 7 Skyciti RERA CA 31-12-2022_Edit.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: 8 Skyciti RERA CA 31-03-2023_Edit.pdf | 1 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DOI Vishal Sir 08-06-2023 Brmaha Multicon.pdf | 10 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DOI Shivani Agarwal 08-06-2023 Bramha Multicon.pdf | 10 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DOI S K Sir 08-06-2023 Bramha maulticon.pdf | 10 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Skycity Phase 2.pdf | 27 Oct 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: BSC Society Registration Certificate- Bramha Sky City.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity 31 12 2020.PDF | 1 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity 31 12 2020.PDF | 1 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q A Certificate Form 2A Skycity 31 12 2020.PDF | 1 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 31-03-2021.pdf | 19 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 31-03-2021.pdf | 19 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Q A Certificate Form 2A Skycity 31-03-2021.pdf | 19 Jun 2021 |
| Certificates of CA (Form 3)File: Form 3 Bramha Leisures 30 June 2020 _compressed.pdf | 22 Jan 2021 |
| Certificates of CA (Form 3)File: Form 3 Bramha Leisures Q2.pdf | 22 Jan 2021 |
| Certificates of CA (Form 5)File: bramha multicon form 5 20 21.PDF | 20 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity June 2020.PDF | 19 Oct 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity June 2020.PDF | 19 Oct 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Q A Certificate Form 2A Skycity 2020.PDF | 19 Oct 2020 |
| Certificates of CA (Form 3)File: B Multicon Form 3 Q1 .pdf | 19 Oct 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: L 1101 Completion Dhanori.pdf | 1 Aug 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 31-03-2020.pdf | 8 Jul 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 31-03-2020.PDF | 8 Jul 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate Form 2A Skycity 31-03-2020.PDF | 8 Jul 2020 |
| Certificates of CA (Form 3)File: ENGG CRETIFICATE Skycity - 31-03-2020.PDF | 8 Jul 2020 |
| Details of Restarting of Construction work post lockdownFile: Bramha SkyCity Dhanori.PDF | 22 Jun 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion 0652_2018.PDF | 14 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 31-12-2019.PDF | 4 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 31-12-2019.PDF | 4 Feb 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate Form 2A Skycity 31-12-2019.PDF | 4 Feb 2020 |
| Certificates of CA (Form 3)File: CA Certificate SkyCity.PDF | 4 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 30-09-2019.PDF | 9 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 30-09-2019.PDF | 9 Nov 2019 |
| Certificates of CA (Form 3)File: Certificates of CA (Form 3).PDF | 9 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form5a multicon.PDF | 9 Nov 2019 |
| Certificates of CA (Form 3)File: CA Certificate Multicon.PDF | 23 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 30-06-2019.PDF | 25 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 30-06-2019.PDF | 25 Jul 2019 |
| Layout approvalFile: 18-1-2019 layout.pdf | 8 May 2019 |
| Copy of Layout Approval (in case of layout)File: 18-1-2019 layout.pdf | 8 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Dhanori CC 3241 18012019 Latest_page-0001 (1).pdf | 8 May 2019 |
| Certificates of CA (Form 3)File: Certificates of CA (Form 3).pdf | 8 May 2019 |
| Proforma of Allotment letterFile: LATEST SKY CITY SALE AGREEMENT AMENDED ON 070519.pdf | 8 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 31-03-2019.PDF | 6 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 31-03-2019.PDF | 6 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar FORM 1 SkyCity - 31-12-2018.PDF | 25 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CRETIFICATE Skycity - 31-12-2018.PDF | 25 Jan 2019 |
| Certificates of CA (Form 3)File: BRAMHA MULTICON PRTVATE LIMITED.PDF | 25 Jan 2019 |
| Certificates of CA (Form 5)File: skycity from 5.PDF | 22 Oct 2018 |
| Proforma of Allotment letterFile: AGRREMENT.pdf | 22 Sep 2018 |
| Layout approvalFile: lAYOUT.pdf | 1 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: lAYOUT.pdf | 1 Aug 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SkyCity Eng cert 30-06-2018.PDF | 31 Jul 2018 |
| Certificates of CA (Form 3)File: CERTIFICATE OF CA.pdf | 31 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SkyCity Arc cert 31-03-2018.PDF | 20 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SkyCity Eng cert 31-03-2018.PDF | 20 Apr 2018 |
| Certificates of CA (Form 3)File: BRAMHA Sky CITY.PDF | 20 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Skycity 31-12-2017.PDF | 9 Mar 2018 |
| Certificates of CA (Form 5)File: BRAMHA SKY CITY.PDF | 9 Mar 2018 |
| Details of encumbrancesFile: Details of encumbrances.pdf | 6 Nov 2017 |
| Declaration in FORM BFile: Declaration in FORM B.pdf | 6 Nov 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SkyCity Arc cert 30-09-2017.PDF | 4 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SkyCity Eng cert 30-09-2017.PDF | 4 Nov 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE multicon.PDF | 4 Nov 2017 |
| Proforma of Allotment letterFile: download sky city1.pdf | 4 Nov 2017 |
| Copy of the legal title reportFile: Search Title.pdf | 26 Aug 2017 |
| Proforma of Allotment letterFile: AGREEMENT UPLOAD.pdf | 17 Aug 2017 |
| Proforma of Allotment letterFile: AGREEMENT UPLOAD.pdf | 17 Aug 2017 |
| Details of encumbrancesFile: Encumbrances.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: 123456.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Declare allotment and agreement for sale.PDF | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Certificates of CA.PDF | 30 Jul 2017 |
| OtherFile: NEW LAYOUT- PHASE 1 2 3 4 5.pdf | 30 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| BRAMHA SKYCITY PHASE- 1 | SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE | 270 | Completed | Sep 2016 | Sep 2016 |
| BRAMHA SKYCITY PHASE- 1 | SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE | 253 | Completed | Sep 2016 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 90 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep BRAMHA SKYCITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHANORI
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: BRAMHA MULTICON PVT LTD
BRAMHA MULTICON PVT LTD has 2 registrations on MahaRERA, including BRAMHA SKYCITY and BRAMHA SKYCITY PHASE 3. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that BRAMHA SKYCITY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if BRAMHA SKYCITY is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BRAMHA SKYCITY?
The registered promoter entity is BRAMHA MULTICON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BRAMHA SKYCITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against BRAMHA SKYCITY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for BRAMHA SKYCITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BRAMHA SKYCITY?
The professionals named in the filing: Architect: REZA KABUL ARCHITECTS PVT LTD; Architect: SUNIL DIGAMBAR VARTA & ASSOCIATES; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BRAMHA SKYCITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.