Home / Browse projects / Palghar, Maharashtra / BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI
BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI
By A R INFRA
RG-MH-34369 · RERA P99000018827 · Last updated on MahaRERA portal: 3 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 61 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI is a Residential / Group Housing project by A R INFRA in Palghar, Maharashtra, registered with MahaRERA as P99000018827 on 6 Dec 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 61 months from the original filing. 2 of the 29 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameBLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI
- TypeResidential / Group Housing
- Location
- BUILDING NO.-05
- TYPE-H
- WING-A
- PARASNATH NAGARI
- NEAR RAILWAY STATION
- UMROLI EAST
- Umroli
- Palghar
- 401404
- Pincode401404
- RERA no.P99000018827
- ReraGenie IDRG-MH-34369
Builder
- NameA R INFRA
- Entity typePartnership
- PartnersRAMJI RAMDEV SINGH, AJAY GRIHNATH SINGH, AZAD OPENDRA PRATAP SINGH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Dec 2018
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 28 Nov 2022)
- Buildings1 building record
- Documents filed32 files
Current status
Figures as on 3 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO-5, WINGA, TYPE-H, VEER-3, PARASNATH NAGARI, UMROLI EAST | NA | 6 | 6 | 26 | 3 | 29 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
BUILDING NO-5, WINGA, TYPE-H, VEER-3, PARASNATH NAGARI, UMROLI EAST: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| HOLYSTONE CONTRUCTION PRIVATE LIMITED | Mira-Bhayandar (M Corp.) | Thane |
| HOLYSTONE CONSTRUCTION PRIVATE LIMITED | Mira-Bhayandar (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO-5, WINGA, TYPE-H, VEER-3, PARASNATH NAGARI, UMROLI EAST | NA | Rs 2.10 cr | Rs 1.26 cr |
| - | NA | Rs 50.00 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE & ASSOCIATES |
| Architect | DEVANG DILIP MHATRE |
| Engineer | JAY SHREE KRISHNA |
| Engineer | MUKESH KUMAR |
| Chartered Accountant | ASHWIN NAIR |
| Partner | Role in project |
|---|---|
| A R INFRA | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject will take time to complete
Reason as filed by the promoterDUE TO COVID AND LOCKDOWN THE PROJECT COULD NOT BE COMPLETED ON TIME
Reason as filed by the promoterDUE TO SOME UNAVOIDABLE REASON THE PROJECT CANNOT BE COMPLETED BEFORE TIME
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Nov 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Nov 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Nov 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed32
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form 1.pdf | 3 Jan 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 3 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 3 Jan 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 24 Sep 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 24 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 24 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD (2).pdf | 12 Nov 2023 |
| Declaration about Commencement CertificateFile: FORM D AR.pdf | 25 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: A R INFRA 2A.pdf | 25 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A R INFRA 2A.pdf | 25 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: A R INFRA 2A.pdf | 25 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD AR.pdf | 25 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: AR 18-19.pdf | 25 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: A R 19-20.pdf | 25 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: AR 20-21 COMPRESSED.pdf | 25 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AR INFRA compressed.pdf | 25 Nov 2022 |
| Layout approvalFile: Layout Plan (1).pdf | 29 Nov 2018 |
| Building plan approvalFile: Building Plan.pdf | 29 Nov 2018 |
| Copy of Layout Approval (in case of layout)File: Layout Plan (1).pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Building Plan.pdf | 29 Nov 2018 |
| Certificates of CA (Form 3)File: CA Certificate-Form No 3.pdf | 8 Nov 2018 |
| PAN CardFile: PAN Card of Firm.pdf | 7 Nov 2018 |
| Copy of the legal title reportFile: Certificate of Advocate.pdf | 7 Nov 2018 |
| Details of encumbrancesFile: Self Declaration on Letter Head-Non Encumrance.pdf | 7 Nov 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate (1).pdf | 7 Nov 2018 |
| Declaration in FORM BFile: Form B (1).pdf | 7 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect.pdf | 7 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate-Jay Shree Krishna.pdf | 7 Nov 2018 |
| Proforma of Allotment letterFile: Page 1 T0 15 (1).pdf | 7 Nov 2018 |
| Proforma of Allotment letterFile: Page 16 To 30 (1).pdf | 7 Nov 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Deed of Partnership (2).pdf | 7 Nov 2018 |
| Status of ConveyanceFile: Developement Agreement (1).pdf | 7 Nov 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 32 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near UMROLI EAST3,200+ in Palghar
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: A R INFRA
A R INFRA has 1 registration on MahaRERA, including BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI?
The registered promoter entity is A R INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI?
The professionals named in the filing: Architect: AJAY WADE & ASSOCIATES; Architect: DEVANG DILIP MHATRE; Engineer: JAY SHREE KRISHNA; Engineer: MUKESH KUMAR; Chartered Accountant: ASHWIN NAIR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BLD NO.-5, WING-A, TYPE-H, VEER-3, PARASNATH NAGARI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback