Home / Browse projects / Pune, Maharashtra / BHUMI SILVERIIO PHASE 2

Registration lapsed No litigation declared Residential / Group Housing project

BHUMI SILVERIIO PHASE 2

By Bhumi Shelters (India) Pvt Ltd

RG-MH-16156 · RERA P52100025555 · Last updated on MahaRERA portal: 25 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
23 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

BHUMI SILVERIIO PHASE 2 is a Residential / Group Housing project by Bhumi Shelters (India) Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100025555 on 28 Jun 2020. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameBHUMI SILVERIIO PHASE 2
  • TypeResidential / Group Housing
  • Location
    • DEHU ALANDI ROAD
    • CHIKHALI
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100025555
  • ReraGenie IDRG-MH-16156

Builder

  • NameBhumi Shelters (India) Pvt Ltd
  • Entity typeCompany
  • CINU45202PN2007PTC131183
  • GSTIN27AADCB3062B1Z8
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorDinesh Venkatrao Gunthe
  • DirectorsRekha Damodar More, Suresh Uttam Kasbe
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

34 months past promisethis monthRegisteredJun 2020First promiseJun 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Jun 2020
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed42 files

Current status

60.9%Work done, per cost certificate

Figures as on 25 Nov 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHUMI SILVERIIO B WINGNA140000
BHUMI SILVERRIO D WINGNA130000
BHUMI SILVERIIO COMMERCIALNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 25 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

BHUMI SILVERIIO B WING64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BHUMI SILVERRIO D WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BHUMI SILVERIIO COMMERCIAL64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 25 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes40%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed101

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots101
Closed/Covered35
Open Space66
BuildingClosed/CoveredOpen SpaceTotal
BHUMI SILVERIIO B WING14849
BHUMI SILVERRIO D WING341852

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Sep 2024

Approvals and building plan

Sanctioning authorityPIMPARI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI10960.97
Proposed, not sanctioned4,206 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKUDALE PLAZA, NR HOTEL GANESH, PIMPRI 411017
Estimated costRs 42.41 cr
Cost incurredRs 25.81 cr
Work done60.85%
BuildingWingEstimatedIncurred
BHUMI SILVERIIO B WINGNARs 18.23 crRs 14.08 cr
BHUMI SILVERRIO D WINGNARs 14.68 crRs 8.61 cr
-NARs 8.47 crRs 2.83 cr
BHUMI SILVERIIO COMMERCIALNARs 1.03 crRs 28.61 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINATH NAWATHE
EngineerUPENDRA PURANDARE
Chartered AccountantSumeet Suresh Kate & Co
Chartered AccountantS GAUTAM &ASSOCIATES
PartnerRole in project
Bhumi Shelters (INDIA) PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013857Jun 2023 → Dec 2023

Reason as filed by the promoterdue to Covid 19 impact

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Jan 2024

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4- Phase II.pdf25 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: form4.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf9 Feb 2024
Proforma of Agreement for saleFile: GetUserDocumentFileContent.pdf9 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf29 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion cert.pdf9 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: token of completion.pdf29 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2.pdf21 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_.pdf21 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 - Rera_arch_cert.pdf15 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New Form.pdf8 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engr_compressed.pdf8 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_compressed-compressed.pdf8 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5-compressed.pdf8 Mar 2022
Declaration about Commencement CertificateFile: commencement.pdf27 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QA-2019-20.pdf27 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA-2020-21_compressed.pdf27 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form5 Declaration.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5 Declaration.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5 Declaration.pdf23 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2.pdf20 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 _ Q2.pdf20 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf23 Jul 2021
Disclosure of sold/ booked inventoryFile: sold inventory_compressed (1).pdf27 May 2021
OtherFile: Enviornment Clearnce letter-2020_.pdf4 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2.pdf10 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA letter - Form3.pdf10 Jun 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Jun 2020
Proforma of Allotment letterFile: booking agreement.pdf4 Jun 2020
Layout approvalFile: 1_reduce - IOD.pdf11 Mar 2020
Building plan approvalFile: NA_reduce.pdf11 Mar 2020
Details of encumbrancesFile: Encumbrances Certificate.pdf11 Mar 2020
Copy of Layout Approval (in case of layout)File: 1_reduce - IOD.pdf11 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: NA_reduce.pdf11 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement cert.pdf11 Mar 2020
Declaration in FORM BFile: Form_B_-_affidavit_2.pdf11 Mar 2020
PAN CardFile: PAN Bhumi.pdf10 Mar 2020
Copy of the legal title reportFile: Legal Title.pdf10 Mar 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
BHUMI SILVERIIO PHASE 3P52100051295DEHU ALANDI ROAD, Pune104Jun 2023OngoingDec 2026Not due yet
BHUMI SILVERIIO PHASE IGAT NO 114P 124 125 126 127P at Pimpri Chinchwad M Corp Tq Haveli Pune 411062113-CompletedSep 2017Late, Jul 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHUMI SILVERIIO PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKHALI13,700+ in Pune

2 kmBHUMI SILVERIIO PHASE 2Completed 116Lapsed / revoked 116Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: Bhumi Shelters (India) Pvt Ltd

Bhumi Shelters (India) Pvt Ltd has 4 registrations on MahaRERA, including BHUMI SILVERIIO PHASE 1 and Bhumi Pride. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BHUMI SILVERIIO PHASE 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHUMI SILVERIIO PHASE 2 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHUMI SILVERIIO PHASE 2?

The registered promoter entity is Bhumi Shelters (India) Pvt Ltd, a company as per the filing. Its CIN U45202PN2007PTC131183 and GSTIN 27AADCB3062B1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHUMI SILVERIIO PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHUMI SILVERIIO PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHUMI SILVERIIO PHASE 2?

The professionals named in the filing: Architect: AVINATH NAWATHE; Engineer: UPENDRA PURANDARE; Chartered Accountant: Sumeet Suresh Kate & Co; Chartered Accountant: S GAUTAM &ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHUMI SILVERIIO PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHUMI SILVERIIO PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHUMI SILVERIIO PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.