Bhumi Shelters (India) Pvt Ltd: RERA track record

CIN U45202PN2007PTC131183 · Company · attribution by exact filing name, entity resolution in progress

Bhumi Shelters (India) Pvt Ltd has 4 registrations in this build, including BHUMI SILVERIIO PHASE 1 and Bhumi Pride. Its filings disclose 4 earlier MahaRERA projects: 1 of 3 past projects completed on time.

4Registrations in this build
4Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
BHUMI SILVERIIO PHASE 1Pune, Maharashtra--Completed
Bhumi PridePune, Maharashtra--Completed
BHUMI SILVERIIO PHASE 2Pune, Maharashtra--Registration lapsed
BHUMI SILVERIIO PHASE 3Pune, Maharashtra10485%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
BHUMI SILVERIIO PHASE I
30 Sep 201715 Jul 2019+21 months
Bhumi Pride
30 Oct 201731 Dec 2017+2 months
BHUMI SILVERIIO PHASE 2
P52100025555
31 Dec 202331 Dec 2023On time
BHUMI SILVERIIO PHASE 3
P52100051295
31 Dec 2026Not completed yetOngoing

Frequently asked questions

How do I verify Bhumi Shelters (India) Pvt Ltd as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45202PN2007PTC131183 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Bhumi Shelters (India) Pvt Ltd?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.