ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Ganesh Paradise Phase I

Registered No litigation declared Residential / Group Housing project

Ganesh Paradise Phase I

By EKDANTA NEST LLP

RG-MH-16007 · RERA P52100024550 · Last updated on MahaRERA portal: 8 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 18 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 98%
66 of 238Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 175 documents Report an error

Ganesh Paradise Phase I is a Residential / Group Housing project by EKDANTA NEST LLP in Pune, Maharashtra, registered with MahaRERA as P52100024550 on 18 Feb 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 18 months from the original filing. 172 of the 238 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGanesh Paradise Phase I
  • TypeResidential / Group Housing
  • Location
    • Chikhali
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • RERA no.P52100024550
  • ReraGenie IDRG-MH-16007

Builder

  • NameEKDANTA NEST LLP
  • Entity typePartnership
  • PartnersSATISH BASWANT PATIL, AKASH SATISH PATIL
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2020First promiseJun 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Feb 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2025)
  • Buildings2 building records
  • Documents filed175 files

Current status

72%172 of 238 units booked
90.3%Work done, per cost certificate

Figures as on 8 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA24191440144
H WINGNA141294094

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

A WING99%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
H WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.55%

Progress on shared amenities15

As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed117

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots117
Closed/Covered3
Open Space114
BuildingClosed/CoveredOpen SpaceTotal
A WING27476
H WING14041

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,523 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Mar 2026
LandownerVillageDistrict
Ganesh MalekarPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI10785.21
Proposed, not sanctioned10,785 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShivajinagar Pune
Estimated costRs 31.00 cr
Cost incurredRs 28.00 cr
Work done90.32%
BuildingWingEstimatedIncurred
A WINGNARs 13.75 crRs 12.30 cr
H WINGNARs 13.75 crRs 12.30 cr
-NARs 3.50 crRs 3.40 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnuradha Gowardhan
EngineerManoj Shinde
EngineerAVINASH ANDENAPPA GADAVE
Chartered AccountantGajanan Sakla
Chartered AccountantRUTUJA NILANGE
Chartered AccountantABHILASH NEGI
PartnerRole in project
EKDANTA NEST LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23032620343Jun 2025 → Dec 2026

Reason as filed by the promoter1. The project stands at 90% completion. 2. The consent of 51.74% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a. The project experienced delays due to unforeseen and unavoidable circumstances beyond our control, including delays in statutory approvals and intermittent disruptions in material supply and manpower availability. These factors affected the planned construction schedule, and therefore additional time is requir

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600420Irfan Ahmed Shafi Ahmed DeshnoorEKDANTA NEST LLP23/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed175

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 175 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf8 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf8 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (1).pdf8 May 2026
Withdrawal Update Form 1File: FORM 1.pdf5 May 2026
Withdrawal Update Form 1File: FORM 1.pdf5 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf5 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf5 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf5 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf5 May 2026
Form 1File: Form 1 Mar 20.pdf15 Jan 2026
Form 2File: FORM-2 MAR 20.pdf15 Jan 2026
Form 3File: FORM-3 MAR 20.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD MAR 20.pdf15 Jan 2026
Form 1File: Form 1 Jun 20.pdf15 Jan 2026
Form 2File: FORM-2 JUN 20.pdf15 Jan 2026
Form 3File: FORM-3 JUN 20.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD JUN 20.pdf15 Jan 2026
Form 1File: Form 1 Sep 20.pdf15 Jan 2026
Form 2File: FORM-2 SEP 20.pdf15 Jan 2026
Form 3File: FORM-3 SEP 20.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD SEP 20.pdf15 Jan 2026
Form 1File: Form 1 Dec 20.pdf15 Jan 2026
Form 2File: FORM-2 DEC 20.pdf15 Jan 2026
Form 3File: FORM-3 DEC 20.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD DEC 20.pdf15 Jan 2026
Form 1File: Form 1 Mar 21.pdf15 Jan 2026
Form 2File: FORM-2 MAR 21.pdf15 Jan 2026
Form 3File: FORM-3 MAR 21.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD MAR 21.pdf15 Jan 2026
OthersFile: FORM 5 MAR 21.pdf15 Jan 2026
Form 1File: Form 1 Jun 21.pdf15 Jan 2026
Form 2File: FORM-2 JUN 21.pdf15 Jan 2026
Form 3File: FORM-3 JUN 21.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD JUN 21.pdf15 Jan 2026
Form 1File: Form 1 Sep 21.pdf15 Jan 2026
Form 2File: FORM-2 SEP 2021.pdf15 Jan 2026
Form 3File: FORM-3 SEP 21.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD SEP 21.pdf15 Jan 2026
Form 1File: Form 1 Dec 21.pdf15 Jan 2026
Form 2File: FORM-2 DEC 21.pdf15 Jan 2026
Form 3File: FORM-3 DEC 21.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD DEC 21.pdf15 Jan 2026
Form 1File: Form 1 Mar 22.pdf15 Jan 2026
Form 2File: FORM-2 MAR 22.pdf15 Jan 2026
Form 3File: FORM-3 MAR 22.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD MAR 22.pdf15 Jan 2026
OthersFile: FORM 5 MAR 22.pdf15 Jan 2026
Form 1File: Form 1 Jun 22.pdf15 Jan 2026
Form 2File: FORM-2 JUN 22.pdf15 Jan 2026
Form 3File: FORM-3 JUN 22.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD JUN 22.pdf15 Jan 2026
Form 1File: Form 1 Sep 22.pdf15 Jan 2026
Form 2File: FORM-2 SEP 2022.pdf15 Jan 2026
Form 3File: FORM-3 SEP 22.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD SEP 22.pdf15 Jan 2026
Form 1File: Form 1 Dec 22.pdf15 Jan 2026
Form 2File: FORM-2 DEC 22.PDF15 Jan 2026
Form 3File: FORM 3 DEC 22.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD DEC 22.pdf15 Jan 2026
Form 1File: Form 1 Mar 23.pdf15 Jan 2026
Form 2File: FORM-2 MAR 23.pdf15 Jan 2026
Form 3File: FORM-3 MAR 23.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD MAR 23.pdf15 Jan 2026
OthersFile: FORM 5 MAR 23.pdf15 Jan 2026
Form 1File: Form 1 Jun 23.pdf15 Jan 2026
Form 2File: FORM-2 JUN 23.pdf15 Jan 2026
Form 3File: FORM-3 JUN 23.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD JUN 23.pdf15 Jan 2026
Form 1File: Form 1 Sep 23.pdf15 Jan 2026
Form 2File: FORM-2 SEP 2023.pdf15 Jan 2026
Form 3File: FORM-3 SEP 23.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD SEP 23.pdf15 Jan 2026
Form 1File: Form 1 Dec 23.pdf15 Jan 2026
Form 2File: FORM-2 DEC 23.pdf15 Jan 2026
Form 3File: FORM-3 DEC 23.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD DEC 23.pdf15 Jan 2026
Form 1File: Form 1 Mar 24.pdf15 Jan 2026
Form 2File: FORM-2 MAR 24.pdf15 Jan 2026
Form 3File: FORM-3 MAR 24.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD MAR 24.pdf15 Jan 2026

How this compares with Pune

72%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ganesh Paradise Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali13,700+ in Pune

Builder: EKDANTA NEST LLP

EKDANTA NEST LLP has 7 registrations on MahaRERA, including GANESH ORCHID and URBAN FOREST A WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ganesh Paradise Phase I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ganesh Paradise Phase I?

The registered promoter entity is EKDANTA NEST LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ganesh Paradise Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ganesh Paradise Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ganesh Paradise Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ganesh Paradise Phase I?

The professionals named in the filing: Architect: Anuradha Gowardhan; Engineer: Manoj Shinde; Engineer: AVINASH ANDENAPPA GADAVE; Chartered Accountant: Gajanan Sakla; Chartered Accountant: RUTUJA NILANGE; Chartered Accountant: ABHILASH NEGI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ganesh Paradise Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ganesh Paradise Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ganesh Paradise Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.