ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BHOOMI ORABELLE PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

BHOOMI ORABELLE PHASE II

By PANKAJ PRAKASH YEOLA

RG-MH-20561 · RERA P52100007858 · Last updated on MahaRERA portal: 23 Jan 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 70 months past the filed date
  • 48 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2020Possession promised70 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
48Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

BHOOMI ORABELLE PHASE II is a Residential / Group Housing project by PANKAJ PRAKASH YEOLA in Pune, Maharashtra, registered with MahaRERA as P52100007858 on 18 Aug 2017. Possession was promised by 4 Dec 2020 and is now 70 months past that date. The completion date has moved by 18 months from the original filing. 48 complaints are on record with the regulator.

At a glance

Project

  • NameBHOOMI ORABELLE PHASE II
  • TypeResidential / Group Housing
  • Location
    • NEAR S B PATIL SCHOOL
    • RAVET
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007858
  • ReraGenie IDRG-MH-20561

Builder

  • NamePANKAJ PRAKASH YEOLA
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

70 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toDec 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion4 Dec 2020
  • Revised completionRevised to 4 Dec 2020 (originally 5 Jun 2019)
  • Buildings2 building records
  • Documents filed15 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHOOMI 0RABELLE PHASE II WING CNA160000
BHOOMI ORABELLE PHASE II WING DNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jan 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

BHOOMI 0RABELLE PHASE II WING C80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)85%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
BHOOMI ORABELLE PHASE II WING D80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)85%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 23 Jan 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes58%
Open ParkingYes0%

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered121
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
BHOOMI 0RABELLE PHASE II WING C60464
BHOOMI ORABELLE PHASE II WING D61364

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,364 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
DIWANJI PANDURANG BHONDAVEPimpri Chinchawad (M Corp.)Pune
PRAKASH SHANKAR BHONDAVEPimpri Chinchawad (M Corp.)Pune
VIJAY SHANKAR BHONDAVEPimpri Chinchawad (M Corp.)Pune
RAJENDRA SHANKAR BHONDVEPimpri Chinchawad (M Corp.)Pune
SANDIP BALKRUSHNA BHONDVEPimpri Chinchawad (M Corp.)Pune
SACHIN BALKRUSHNA BHONDVEPimpri Chinchawad (M Corp.)Pune
SANJAY BALKRUSHNA BHONDVEPimpri Chinchawad (M Corp.)Pune
BALKRUSHNA BHONDVEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI7962.02
Proposed, not sanctioned7,962 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUpper Ground Floor, ABC TIARA, Shop no 9, 10 11, H-17,ADC next to Akurdi Railway Station,Nigdi Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHASHANK PHADAKE
EngineerYOGESH DHAMALE
PartnerRole in project
PANKAJ PRAKASH YEOLA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005447Jun 2019 → Jun 2020

Reason as filed by the promoterDelayed in completing Project.

Complaints filed with MahaRERA48

Case no.ComplainantRespondentFiled
CC005000000022486Abhijeet Bhimashankar MashalePankaj Prakash Yeola21/01/2019
CC005000000023098umesh kadamPankaj Yeola11/06/2019
CC005000000023109MANSI KSHEMKALYANIPANKAJ YEOLA11/06/2019
CC005000000023110DINESH WADEKARPANKAJ YEOLA11/06/2019
CC005000000023114SUNANDA DAREKARpankaj yeola11/06/2019
CC005000000023277ROHINI ABHYANKARPANKAJ YEOLA30/07/2019
CC005000000053828VINOD RAJARAM PATELpankaj yeola25/12/2019
CC005000000053825SAGAR DAGDU PATILpankaj yeola25/12/2019
CC005000000053823SUNIL N. BADKARpankaj yeola25/12/2019
CC005000000053822Ashutosh pradip deokarPANKAJ YEOLA25/12/2019
CC005000000053829MAHESHWARI NITN SHINDEpankaj yeola25/12/2019
CC005000000053830AMOL AHIWARPANKAJ YEOLA25/12/2019
CC005000000053831SAURABH PRAKASHRAO AHIWARpankaj yeola25/12/2019
CC005000000053827MURLIDHAR GENU SHEVAKARIpankaj yeola25/12/2019
CC005000000053984SAGAR SHETEDIVANJI BHONDVE26/01/2020
CC005000000053983HEMRAJ CHOUDHARYPANKAJ YEOLA26/01/2020
CC005000000053986HINA PENDHARISANTOSH CHENGEDIA26/01/2020
CC005000000054017Tushar PatilPankaj Prakash Yeola26/02/2020
CC005000000054023Snehal Sagar BadgePankaj Yeola15/02/2020
CC005000000064616Nirad Charul SmartPankaj Prakash Yeola19/09/2020
CC005000000064696Sanjul Ashokkumar LalwaniPankaj Prakash Yeola27/12/2020
CC005000000064703Vasant HolkarMr.pankaj prakash yeola03/10/2020
CC005000000064708MAYANK ROTHEPankaj Prakash Yeola10/11/2020
CC005000000064710Sharad Waman JagtapPankaj Prakash Yeola05/10/2020
CC005000000064741MANOJ MUDGALMr.Pankaj Prakash Yeola26/10/2021
CC005000000064818Snehal Sunil DahalePankaj Prakash Yeola10/11/2020
CC005000000064843Amol Dnyandev PatilPANKAJ YEOLA18/11/2020
CC005000000064962Piyush Subhash WanarePankaj Prakash Yeola23/12/2020
CC005000000075099Bhavin ChauhanM/s. Bhoomi Construction Through proprietor Mr. Pankaj Prakash Yeola20/01/2021
CC005000000075168AMOL ABASAHEB GHADAGEM/s. Bhoomi Construction Through proprietor Mr. Pankaj Prakash Yeola16/04/2021
CC005000000085256SOMNATH DASPANKAJ PRAKASH YEOLA25/02/2021
CC005000000085439Vinayak Ashok ManePankaj Yeola27/07/2021
CC005000000095804Mr. Swapnil Reva SawdekarM/s. Bhoomi Constructions Through its proprietor Mr. Pankaj Prakash Yeola30/07/2021
CC005000000096039Sachin Balkrushna BhondaveBhoomi Constructions Through Pankaj Prakash Yeola20/09/2021
CC005000000096178Nitin Nathuram GhadgePankaj Yeola02/12/2022
CC005000000096281SHARAD VASANT NIMBALKARPANKAJ PRAKASH YEOLA21/11/2021
CC005000000106469Chetan Janardan YewalePankaj Prakash Yeola15/01/2022
CC005000000106747MAHESH SABLEPankaj Yeola10/03/2022
CC005000000106748Amrut Mahadeorao DhaskatM/s Bhoomi Construction (Pankaj Prakash Yeola)23/02/2023
CC005000000177962Paresh Vishwanath KothawadePANKAJ YEOLA21/12/2022
CC005000000228379Akshay Prakash MahajanPankaj Prakash Yeola27/02/2023
CC005000000228429preetam padhypankaj prakash yeola03/03/2023
CC005000000228431Ramavtar Jagdish YadavPankaj Prakash Yeola03/03/2023
CC005000000258796SANDEEP SHANTARAM BADVEPANKAJ YEOLA01/05/2023
CC005000000258797SONALI SANDEEP BADVEPANKAY YEOLA01/05/2023
CC005000000258869Mrs. Shilpa Sanjit DhepeMr. Sanjay Balkrishna Bhondve24/05/2023
CC12504494Mrs. Shilpa Sanjit DhepePANKAJ PRAKASH YEOLA16/12/2025
CC12600945jitendra Ashok shinkarPANKAJ PRAKASH YEOLA20/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: CA Certificate Form 5 - Orabelle Phase II.pdf23 Jan 2019
Copy of the legal title reportFile: SEARCH REPORT.pdf31 Jul 2017
Details of encumbrancesFile: ORABELLE 2 ENCUMBRANCEMENT.pdf31 Jul 2017
Details of encumbrancesFile: Orabelle Index - II for IIFL Loan.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ORABELLE 2 ENGN CERT.pdf31 Jul 2017
Certificates of CA (Form 3)File: ORABELLE 2 CA CERT.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT AS PER RERA - Phase II.pdf31 Jul 2017
Layout approvalFile: ORABELLE LAYOUT.pdf30 Jul 2017
Building plan approvalFile: ORABELLE IOD.pdf30 Jul 2017
PAN CardFile: ORABELLE PAN CARD.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: ORABELLE LAYOUT.pdf30 Jul 2017
Building Plan Approval (IOD)File: ORABELLE IOD.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: ORABELLE COMENCEMENT.pdf30 Jul 2017
Declaration in FORM BFile: ORABELLE 2 FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ORABELLE 2 AR CERT.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
BHOOMI KSHITIJBHHOMI KSHITIJ SURVEY NUMBER 48 TO 10 NAKHATE VASTI RAHATANI PUNE 41101763CompletedDec 2016Jul 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHOOMI ORABELLE PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

2 kmBHOOMI ORABELLE PHASE IICompleted 104Lapsed / revoked 42Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 236 registered projects within 2 km.

Builder: PANKAJ PRAKASH YEOLA

PANKAJ PRAKASH YEOLA has 3 registrations on MahaRERA, including BHOOMI BLESSINGS and BHOOMI ORABELLE PHASE I. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BHOOMI ORABELLE PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHOOMI ORABELLE PHASE II is delayed beyond 4 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHOOMI ORABELLE PHASE II?

The registered promoter entity is PANKAJ PRAKASH YEOLA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHOOMI ORABELLE PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BHOOMI ORABELLE PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BHOOMI ORABELLE PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHOOMI ORABELLE PHASE II?

The professionals named in the filing: Architect: SHASHANK PHADAKE; Engineer: YOGESH DHAMALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHOOMI ORABELLE PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHOOMI ORABELLE PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHOOMI ORABELLE PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.