Home / Browse projects / Pune, Maharashtra / BHALCHANDRA VIHAR PHASE-III/M1,M2

Registration lapsed No litigation declared Residential / Group Housing project

BHALCHANDRA VIHAR PHASE-III/M1,M2

By N B BHONDVE BUILDERS

RG-MH-69185 · RERA P52100046946 · Last updated on MahaRERA portal: 17 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

BHALCHANDRA VIHAR PHASE-III/M1,M2 is a Residential / Group Housing project by N B BHONDVE BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100046946 on 26 Sep 2022. Possession was promised by 29 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBHALCHANDRA VIHAR PHASE-III/M1,M2
  • TypeResidential / Group Housing
  • Location
    • BHONDVE BAUG
    • RAVET
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046946
  • ReraGenie IDRG-MH-69185

Builder

  • NameN B BHONDVE BUILDERS
  • Entity typePartnership
  • PartnersSHREYAS NANDKUMAR BHONDVE, SUMEET SOMNATH BHONDVE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredSep 2022First promiseJun 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Sep 2022
  • Promised completion29 Jun 2025
  • Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING M1NA140000
WING M2NA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

WING M173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING M273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed166

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots166
Closed/Covered126
Open Space40
BuildingClosed/CoveredOpen SpaceTotal
WING M1482068
WING M2782098

Land and ownership12

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,395 sq m
Land owned byThe promoter, with other names on the file
Named landowners12
LandownerVillageDistrict
UMESH SHIVAJI MANEPimpri Chinchawad (M Corp.)Pune
SANDHYA VILAS DESHMUKHPimpri Chinchawad (M Corp.)Pune
MOHAN SHIVAJI PATELPimpri Chinchawad (M Corp.)Pune
CHETAN MOHAN PATELPimpri Chinchawad (M Corp.)Pune
PRATIBHA SUBHASH PATKEPune (M Corp.)Pune
JITENDRA ARJUNBHAI PATELPimpri Chinchawad (M Corp.)Pune
KISHOR ARJUNBHAI PATELPimpri Chinchawad (M Corp.)Pune
JAYANTILAL SHIVJI PATELPimpri Chinchawad (M Corp.)Pune
JOYKUMAR JAYANTILAL PATELPimpri Chinchawad (M Corp.)Pune
RAHUL VALMIK MANEPimpri Chinchawad (M Corp.)Pune
ASHOK TUKARAM DEVKARPimpri Chinchawad (M Corp.)Pune
SANDEEP VITTHAL JADHAVPimpale GuravPune

Approvals and building plan

Permissible FSI12100.0
Proposed, not sanctioned8,600 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhondve Corner, Sector No 29, Ravet, Pune - 412101

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHENDRA THAKUR
EngineerRAVINDRA A. KARNAVAT
EngineerASHOK MOTE
Chartered AccountantDHIRAJ MANOJ BALDOTA
PartnerRole in project
N B BHONDVE BUILDERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024241Jun 2024 → Jun 2025

Reason as filed by the promoterWe have completed 90% construction of our project but no objection certificates from our Town Planning Department are yet to come so we are submitting this extension application to you requesting your approval.

Litigation declared1

CaseCourtStatus
608/2024Civil Judge Senior Division PunePending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000371038Sunilkumar Vinodbhai PatelN B BHONDVE BUILDERS30/05/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Jun 2024

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Final.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 M1-M2.PDF17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 31.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: N B BHONDAVE BUILDER.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30062024.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 II.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Information.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 II.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Xerox Scan_16072024122027.PDF16 Jul 2024
Declaration in FORM BFile: FORM B BHARCHANDRA VIHAR.pdf3 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Part N B bhondve 109 Vihar_11zon.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 19-4-24_compressed.pdf7 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.PDF23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bhalchandra Vihar Phase III Form 2.pdf23 Apr 2024
Copy of the legal title reportFile: Vihar Search Feb 2024.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.PDF15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf15 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.PDF29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adobe Scan 29 Dec 2023 (3).pdf29 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 28-12-2023.pdf29 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30092023.PDF23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.PDF20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.PDF20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 46946.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A 22-23.pdf8 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 M1, M2.PDF21 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2.pdf21 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3.pdf21 Aug 2023
Declaration about Commencement CertificateFile: Polite Buildtech Format D.pdf15 Sep 2022
Declaration in FORM BFile: Form B Vihar M1,M2.pdf15 Sep 2022
CERSAI detailsFile: Polite Cersai Report.pdf15 Sep 2022
CERSAI detailsFile: CERSAI Search.pdf15 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold M1_merged.pdf15 Sep 2022
Proforma of Allotment letterFile: Allotment Letter_merged_organized.pdf15 Sep 2022
Proforma of Allotment letterFile: Draft Agreement to Sale Model for M1,M2 Final.pdf15 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account.pdf15 Sep 2022
Deviation Report with respect to Allotment letterFile: Deviation Report.pdf15 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation AFS.pdf15 Sep 2022
Layout approvalFile: 0001.pdf14 Sep 2022
Layout approvalFile: 0002.pdf14 Sep 2022
Building plan approvalFile: MYSCAN_20220504_0009_compressed.pdf14 Sep 2022
Building plan approvalFile: MYSCAN_20220504_0008_compressed.pdf14 Sep 2022
Building plan approvalFile: MYSCAN_20220504_0007_compressed.pdf14 Sep 2022
Building plan approvalFile: MYSCAN_20220504_0006_compressed.pdf14 Sep 2022
Building plan approvalFile: MYSCAN_20220504_0005.PDF14 Sep 2022
PAN CardFile: Pan.pdf14 Sep 2022
Copy of the legal title reportFile: REVISED TITLE VERIFICATION and SEARCH REPORT 1-16.pdf14 Sep 2022
Copy of the legal title reportFile: REVISED TITLE VERIFICATION and SEARCH REPORT-17-33.pdf14 Sep 2022
Copy of the legal title reportFile: REVISED TITLE VERIFICATION and SEARCH REPORT-34-48.pdf14 Sep 2022
Details of encumbrances concerned to FinanceFile: To Finance.pdf14 Sep 2022
Details of encumbrances concerned to LegalFile: To Legal.pdf14 Sep 2022
Copy of Layout Approval (in case of layout)File: 0001.pdf14 Sep 2022
Copy of Layout Approval (in case of layout)File: 0002.pdf14 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20220504_0009_compressed.pdf14 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20220504_0008_compressed.pdf14 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20220504_0007_compressed.pdf14 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20220504_0006_compressed.pdf14 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20220504_0005.PDF14 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE NEW_repaired.pdf14 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bldg M1, M2 Form-1.pdf14 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bhalchandra Vihar M1, M2.pdf14 Sep 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHALCHANDRA VIHAR PHASE-III/M1,M2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

2 kmBHALCHANDRA VIHAR PHASE-Completed 103Lapsed / revoked 51Other 102Dot size: filed unitsN

Filed coordinates, straight-line distance. 256 registered projects within 2 km.

Builder: N B BHONDVE BUILDERS

N B BHONDVE BUILDERS has 2 registrations on MahaRERA, including BHALCHANDRA VIHAR PHASE - IV/M3 and BHALCHANDRA VIHAR PHASE-III/M1,M2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BHALCHANDRA VIHAR PHASE-III/M1,M2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHALCHANDRA VIHAR PHASE-III/M1,M2 is delayed beyond 29 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHALCHANDRA VIHAR PHASE-III/M1,M2?

The registered promoter entity is N B BHONDVE BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHALCHANDRA VIHAR PHASE-III/M1,M2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BHALCHANDRA VIHAR PHASE-III/M1,M2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BHALCHANDRA VIHAR PHASE-III/M1,M2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHALCHANDRA VIHAR PHASE-III/M1,M2?

The professionals named in the filing: Architect: MAHENDRA THAKUR; Engineer: RAVINDRA A. KARNAVAT; Engineer: ASHOK MOTE; Chartered Accountant: DHIRAJ MANOJ BALDOTA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHALCHANDRA VIHAR PHASE-III/M1,M2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHALCHANDRA VIHAR PHASE-III/M1,M2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHALCHANDRA VIHAR PHASE-III/M1,M2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.