Home / Browse projects / Bhaktamar Residency
Bhaktamar Residency
RG-MH-13050 · RERA P52100022186 · Last updated on MahaRERA portal: 8 May 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Bhaktamar Residency is a Residential / Group Housing project by Bhaktamar Realities LLP in Vadgaonsheri, 411014, registered with MahaRERA as P52100022186 on 5 Sep 2019. Possession was promised by 28 Jun 2025 and is now 16 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameBhaktamar Residency
- TypeResidential / Group Housing
- Location
- VADGAONSHERI SOMNATHNAGAR ROAD
- Vadgaonsheri
- 411014
- Pincode411014
- RERA no.P52100022186
- ReraGenie IDRG-MH-13050
Builder
- NameBhaktamar Realities LLP
- Entity typePartnership
- PartnersSAPS Landmark LLP, Rahul Ramesh Shah, Shubham Surendra Sancheti
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Sep 2019
- Promised completion28 Jun 2025
- Revised completionNone
- Buildings5 building records
- Documents filed103 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 19 | 0 | 0 | 0 | 0 |
| Building B | NA | 18 | 0 | 0 | 0 | 0 |
| Building C | NA | 17 | 0 | 0 | 0 | 0 |
| Building D | NA | 17 | 0 | 0 | 0 | 0 |
| Building Mhada | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 8 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
36 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 95%.
Building A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building D72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building Mhada68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed500
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building A | 136 | 136 |
| Building B | 97 | 97 |
| Building C | 91 | 91 |
| Building D | 138 | 138 |
| Building Mhada | 38 | 38 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAY AERAM ARCHITECTURAL CONSULTANT |
| Engineer | SHAILENDRA PATIL |
| Engineer | STS Consultants LLP |
| Chartered Accountant | P B Shah |
| Chartered Accountant | Parag Patwa and Associates |
| Partner | Role in project |
|---|---|
| Bhaktamar Realities LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12601569 | Rajat Kumar Jain | Bhaktamar Realities LLP | 21/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1.pdf | 8 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2.pdf | 8 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A.pdf | 8 May 2024 |
| Certificates of CA (Form 3)File: Form_3_April2024.pdf | 8 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form_3.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 23 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 23 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 23 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 12 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 12 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 22 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf | 22 Nov 2023 |
| Certificates of CA (Form 3)File: Form-3_.pdf | 22 Nov 2023 |
| Building plan approvalFile: Building Approved Plan_Latest-1-3.pdf | 20 Nov 2023 |
| Building Plan Approval (IOD)File: Building Approved Plan_Latest-1-3.pdf | 20 Nov 2023 |
| Layout approvalFile: Plan.pdf | 4 Sep 2023 |
| Layout approvalFile: Building Approved Plan_Latest-1-3.pdf | 4 Sep 2023 |
| Layout approvalFile: Building Approved Plan_Latest-4-6.pdf | 4 Sep 2023 |
| Layout approvalFile: Building Approved Plan_Latest-7-9.pdf | 4 Sep 2023 |
| Building plan approvalFile: Building Approved Plan_Latest-1-3.pdf | 4 Sep 2023 |
| Building plan approvalFile: Building Approved Plan_Latest-4-6.pdf | 4 Sep 2023 |
| Building plan approvalFile: Building Approved Plan_Latest-7-9.pdf | 4 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Plan.pdf | 4 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Building Approved Plan_Latest-1-3.pdf | 4 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Building Approved Plan_Latest-4-6.pdf | 4 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Building Approved Plan_Latest-7-9.pdf | 4 Sep 2023 |
| Building Plan Approval (IOD)File: Building Approved Plan_Latest-1-3.pdf | 4 Sep 2023 |
| Building Plan Approval (IOD)File: Building Approved Plan_Latest-4-6.pdf | 4 Sep 2023 |
| Building Plan Approval (IOD)File: Building Approved Plan_Latest-7-9.pdf | 4 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed (1)-compressed.pdf | 4 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Details of Sold Inv_25062023.pdf | 4 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: BHAKTAMAR REALTIES LLP_FORM NO_5.pdf | 21 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE-29-07-2023.pdf | 3 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE-29-07-2023.pdf | 3 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3_Signed.pdf | 3 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate.pdf | 26 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer Certificate.pdf | 26 May 2023 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate_compressed.pdf | 26 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_Jay Aeram.pdf | 17 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_EngineerCertificate.pdf | 17 Mar 2023 |
| Certificates of CA (Form 3)File: Form_3_CACertificate.pdf | 17 Mar 2023 |
| Proforma of Allotment letterFile: Draft for RERA Flat Agreement 2103.pdf | 5 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Bhaktamar.pdf | 21 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Bhaktamar.pdf | 14 Jan 2022 |
| Layout approvalFile: PLAN-01-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-02-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-03-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-04-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-05-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-06-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-07-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-08-09_compressed.pdf | 4 Jan 2022 |
| Building plan approvalFile: PLAN-09-09_compressed.pdf | 4 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: PLAN-01-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-02-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-03-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-04-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-05-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-06-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-07-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-08-09_compressed.pdf | 4 Jan 2022 |
| Building Plan Approval (IOD)File: PLAN-09-09_compressed.pdf | 4 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-2140-21 DT 22-10-2021_compressed.pdf | 4 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 10 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Bhaktamar Realities - Sold Inventory Discl.pdf | 31 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Bhaktamar Realities.pdf | 17 May 2021 |
| Proforma of Allotment letterFile: Flat Agreement RERA.pdf | 21 Aug 2020 |
| Proforma of Allotment letterFile: Flat Agreement RERA.pdf | 21 Aug 2020 |
| Building plan approvalFile: Revised Building Plan 1.pdf | 4 Mar 2020 |
| Building plan approvalFile: Revised Building Plan 2.pdf | 4 Mar 2020 |
| Building plan approvalFile: Revised Building Plan 3.pdf | 4 Mar 2020 |
| Building plan approvalFile: Revised Building Plan 4.pdf | 4 Mar 2020 |
| Layout approvalFile: Layout Approval.pdf | 4 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: Layout Approval.pdf | 4 Mar 2020 |
| Building Plan Approval (IOD)File: Revised Building Plan 1.pdf | 4 Mar 2020 |
| Building Plan Approval (IOD)File: Revised Building Plan 2.pdf | 4 Mar 2020 |
| Building Plan Approval (IOD)File: Revised Building Plan 3.pdf | 4 Mar 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Bhaktamar Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vadgaonsheri
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: Bhaktamar Realities LLP
Bhaktamar Realities LLP has 2 registrations on MahaRERA, including Bhaktamar Residency and CHANDRAKAMAL. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that Bhaktamar Residency shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Bhaktamar Residency is delayed beyond 28 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Bhaktamar Residency?
The registered promoter entity is Bhaktamar Realities LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Bhaktamar Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Bhaktamar Residency?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Bhaktamar Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Bhaktamar Residency?
The professionals named in the filing: Architect: JAY AERAM ARCHITECTURAL CONSULTANT; Engineer: SHAILENDRA PATIL; Engineer: STS Consultants LLP; Chartered Accountant: P B Shah; Chartered Accountant: Parag Patwa and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bhaktamar Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.